Back
Legal

Farmer Giles Ltd v Wessex Water Authority and another

Damages — Collapse of wall — Liability admitted — Conflict as to measure of damages — Whether cost of reinstatement, market value of property without development potential or compensation for deprivation of development potential — Appeal and cross-appeal from decision of Peter Pain J

Plaintiffs
owned a plot of land close to a river, of which land about one-tenth, known as
Unit 7, was contiguous to the river — By an agreement between the plaintiffs
and the water authority (the first defendants in the action) the authority
agreed to pay compensation for, or make good, any damage sustained for the
carrying out of certain works — The authority employed a construction company
(the second defendants) which carried out excavations close to the wall of Unit
7 as a result of which the wall collapsed into the river — Plaintiffs sued both
defendants and the judge awarded plaintiffs £34,100 plus interest of £18,470.69
— He assessed the loss of the plaintiffs in the following way — He found that
the appropriate rent to be anticipated after refurbishment would be £5,000 per
annum, which, capitalised at 12 1/2%, would produce £40,000 — He deducted the
probable costs of refurbishment at £13,000 and the value of the cleared site at
£1,000 from the £40,000, resulting in a loss of £26,000 — To this were added
certain undisputed and minor items amounting to £8,100, producing the total
above mentioned of £34,100 — The judge rejected both the suggestion of complete
rebuilding, at £117,000 to £155,000 (according to conflicting evidence) and the
defendants’ figure of £9,000, being the market value of £10,000 at the date of
the collapse less £1,000 for the value of the cleared site

The
defendants appealed to the Court of Appeal on the ground that the judge’s award
was excessive and the plaintiffs cross-appealed on the ground that it was
inadequate — The court found that the judge’s approach to the assessment of
damages was correct and in accordance with authority — It rejected the
defendants’ contention that in all cases where a building was damaged or
destroyed by tort the ceiling figure for damages was the value of the property
at the time of the tort without any regard to potential development in the
future, in the present case £10,000 less site value — The court also rejected
the plaintiffs’ cross-appeal, based on a construction of their agreement with
the water company, by which they claimed an entitlement to reinstatement, for
which the figures of £117,000 and £155,000 had been quoted — The court was not
restricted to a choice between the cost of complete reinstatement on the one
hand and the market value of the property as it stood on the other — Unit 7 had
development potential and the plaintiffs had been deprived by the destruction
of the building of the benefit of this potential — The figure at which the
judge had arrived accurately represented the loss suffered by the plaintiffs —
Appeal and cross-appeal dismissed

The following
cases are referred to in this report.

Admiralty
Commissioners
v SS Chekiang (The Chekiang)
[1926] AC 637

Livingstone v Rawyards Coal Co (1880) 5 App Cas 25, HL

Philips v Ward [1956] 1 WLR 471; [1956] 1 All ER 874, CA

Taylor
(CR)(Wholesale) Ltd
v Hepworths Ltd [1977] 1
WLR 659; [1977] 2 All ER 784; (1976) 244 EG 631, [1977] 2 EGLR 31

This was an
appeal by the defendants, Wessex Water Authority and Johnston Construction Ltd,
and a cross-appeal by the plaintiffs, Farmer Giles Ltd, from the decision of
Peter Pain J, reported at [1988] 2 EGLR 189, in regard to a claim by the
plaintiffs for damage caused by the collapse of the wall of a building known as
Unit 7 in a commercial area called Meadow Works, Trowbridge, Wiltshire.

Roderick
Denyer (instructed by Barkers, of Bristol) appeared on behalf of the appellants
(defendants); David Spens (instructed by Withy King & Lee, of Bath)
represented the respondents (plaintiffs).

Giving the
first judgment at the invitation of Purchas LJ, RUSSELL LJ said: In 1981
at Trowbridge, Wiltshire, there was a plot of land some 33,000 sq ft in area
which contained 17 commercial-type buildings. The composite whole was known as
Meadow Works, Trowbridge. It was purchased by the plaintiff company, Farmer
Giles Ltd, for the sum of £100,000. The directors of Farmer Giles Ltd were Mr
and Mrs Giles. The plot was close by the River Biss and, in particular, a unit
representing about 10% of the total square footage178 of the plot was contiguous to the river. That unit was known as Unit 7. The
first defendants, the Wessex Water Authority, found it necessary to do
extensive works involving the river and its bed. They employed the second
defendants, Johnston Construction Ltd, to carry out the work. It involved the
digging of a trench close to one of the main walls of Unit 7.

Before the
work began the first defendants entered into an agreement with the plaintiffs
which contained the following clause so far as material to this appeal:

Compensation.

The Wessex
Water Authority agrees to pay compensation for or make good any damage which
may be sustained as a result of carrying out the works subject to section 17(5)
of the Land Drainage Act 1976.

On August 12
1983 the second defendants, having excavated close to the wall of Unit 7, left
that wall without support, in consequence of which it collapsed into the river.
Liability for the disaster was admitted by both the first and second
defendants, and proceedings were instituted by the plaintiff company against
both defendants. The matter came before Peter Pain J, sitting in Bristol, in
February 1988. He heard evidence which occupied four or five days, and then
adjourned the hearing for argument to London, where, on April 29 1988, the
judge awarded the plaintiff damages in the sum of £34,100 together with
interest of £18,470.69, making a total inclusive award of £52,570.69.

This court now
has before it the defendants’ appeal against that award, it being contended
that it is excessive; and the plaintiff’s cross-appeal, it being contended on
behalf of Farmer Giles Ltd that the award was inadequate, having regard to the
circumstances of the case and, in particular, what is said to have been the
contractual obligations of the first defendants.

During the
course of the hearing in Bristol the judge heard a great deal of evidence from
expert witnesses. At the time of the collapse of the wall Unit 7 was occupied
by a troop of Sea Scouts who had a lease for seven years at a nominal rent of
£1 a year. That lease was due to expire in September 1983, about a month after
the disaster. In addition, a small company had the use of part of Unit 7 for
storage purposes; nothing turns upon their occupation.

The premises
undoubtedly were in a poor state of repair. Mr Giles, the managing director of
the plaintiff company, was anxious to obtain possession from the troop of sea
scouts so that his company could redevelop the building for commercial
purposes. He had the structure surveyed in the early part of 1983 by a
gentleman, who gave evidence, named Mr K Hodges Cole [ARICS]. Mr Cole did not
prepare any written report. But his evidence heard by Peter Pain J was to the
effect that at the time of his inspection, prior to the collapse of the wall,
the property was capable of economical refurbishment. The judge accepted that
evidence.

Mr Giles, upon
receipt of Mr Cole’s report, instructed the plaintiffs’ solicitors to write to
the troop of Sea Scouts indicating to the troop that the property was unsafe
and consequently there could be no question of any extension of the troop’s
occupation. That, as Mr Giles readily acknowledged when he came to give evidence,
was a ploy, some might say a lie, in order to achieve for the plaintiff company
that which Mr Giles desired, namely the return of the premises to the company
with possession of them so that refurbishment could be carried out in
accordance with Mr Cole’s recommendations and so that thereafter the property
could be put to good commercial use.

It was the
case for the defendants that what the solicitors wrote to the Sea Scout troop
represented the reality of the situation and that this building in fact was of very
little value, was dangerous and could not have been refurbished. There was
support for those propositions in evidence called before the judge. Having seen
all the witnesses (and it is unnecessary in this judgment to analyse their
evidence) the judge made the plainest possible finding that this building when
it collapsed in August 1983 was in such a condition that, with the expenditure
of money upon it, it could be refurbished to the extent that it was a viable
commercial property capable of generating rent on a comparatively substantial
scale.

The judge,
therefore, had the task of assessing the true loss sustained by the plaintiff.
He went about it in this way. First, he determined what would be the
appropriate rent to be anticipated after refurbishment. Upon this issue, as
upon virtually every other issue in the case, there was conflict. The judge
received evidence from two local valuers, respectively Mr H Steele-Perkins
[FRICS FSVA], who was called on behalf of the plaintiff, and Mr B F Fitchett
[FRICS], who was called on behalf of the defendants. Mr Steele-Perkins
contended that, after refurbishment the property would and could be let at a
rental of £6,300 per annum. Mr Fitchett for the defendants, who took the view
that no refurbishment was really possible, not surprisingly submitted a very
much lower rental value for a very limited period, namely £1,500 per annum.

The judge,
having considered those conflicting views and having expressed his dismay at
the extent of disagreement, said he found in relation to this aspect of the
matter, after making proper allowance for the factors which he indicated in his
judgment as mitigating the rent, that it was probable that there would be a
recoverable rent of £5,000 per annum. No complaint is made by either the plaintiff
or the defendants about that finding of fact.

The judge then
had to consider the question of the return on capital. Mr Steele-Perkins took
the view that the appropriate percentage return on capital in the circumstances
of this case after refurbishment would be 10%. Mr Fitchett contended for 15%.
The difference, once the judge fixed upon £5,000, was between about £33,000 and
£50,000. At p 13 of the judgment* the judge fixed upon 12 1/2%, that
representing, as it were, the half-way house between the 15% canvassed by Mr
Fitchett and the 10% canvassed by Mr Steele-Perkins. Accordingly, basing
himself upon 12 1/2% and on £5,000, the judge arrived at a figure of £40,000
from which, as he found, he had to deduct the cost of creating that asset. He
also had to deduct from the figure at which he arrived the value of the cleared
site that was left to the advantage of the plaintiff company after demolition.

*Editor’s
note: Reported at [1988] 2 EGLR 189 at p 192K

The evidence
as to the cost of refurbishment was sparse. The judge had described Mr Giles
not only as an entrepreneur who had demonstrated in the past an ability to buy
properties, refurbish them and thereafter let them at a substantial profit, but
also as a man who was able to work himself in the manual sense. What the
plaintiff company’s managing director, Mr Giles, told the judge was that, had
it not been for the disaster, he would have used his own personal labour to
effect the refurbishment. He would not have made any charge for his own
personal labour and that consequently the cost to the company would have been
something like one half of what it would have cost the company if Farmer Giles
Ltd had put the work out to tender and had obtained some outside organisation
to do the refurbishment. Mr Giles in evidence said that the cost on the basis
of his working on the property would have been about £10,000-£12,000. The judge
made a finding that there should be deducted from the £40,000, arrived at by the
process to which I have earlier referred, the sum of £13,000 representing the
probable cost to the company of refurbishment, using Mr Giles’ own labour.
There was no evidence before the court, so we are told, as to the value of that
labour. Mr Giles was paid a salary, the extent of which did not emerge, by the
plaintiff company in his capacity as managing director. There had to be a
further deduction from the £40,000 to represent the value of the cleared site,
and there is no dispute but that the figure of £1,000 for that feature of the
case was appropriate. Accordingly, the judge found that the loss sustained in
relation to this building by the plaintiff company was £40,000, less £14,000,
ie £26,000. It is against that award that the appeal on behalf of the
defendants is launched. The balance of the judgment, totalling £34,100, was
made up as to an undisputed claim relating to the river bank of £5,830 and an
additional sum of £2,270 for items which need not be identified in this
judgment.

The only other
finding to which I need refer is this. There was conflicting evidence as to the
cost of rebuilding. On the one hand it was said to be £117,000. On the other
hand it was said to be £155,000. The judge did not find it necessary to say how
much it would have cost to rebuild this structure. He described the effect of
rebuilding as being ‘grotesque’. In other words, he rejected outright the
suggestion that this was a case that called for the defendants to rebuild.

At the date of
the wall collapse there were two opinions expressed as to the fair market value
of the property without its commercial potential. The judge said, at p 7 of the
judgment, having listened to the conflicting evidence:

I find that a
fair figure for market value at the date of collapse was £10,000.

It is that
figure which the defendants contend represented the true loss occasioned to the
plaintiff company by their negligence.

The submission
of counsel for the defendants before this court (he did not appear in the court
below), Mr Denyer, to whom I would wish179 to pay tribute for the care and succinctness of what he had to say, is that in
all cases where a building is damaged or destroyed by negligence, the ceiling
figure for damages is the value of the property at the time of the tort without
any regard being paid to its potential development in the future. Applying that
submission to the facts of this case, Mr Denyer, on behalf of the appellants,
contends that the true measure of damages here must be the sum of £9,000
representing the market value, so-called, of the property at the date of
collapse without development potential, less the £1,000 that the judge found as
the value of the cleared site.

In my view,
that approach to the problem flies in the face of reality. Had anyone asked Mr
Giles immediately prior to the collapse of the wall: ‘What is the value of Unit
7?’  I do not believe that he or indeed
anybody else apprised of the facts would have replied: ‘£10,000’. This unit, as
earlier indicated, was but one of 17 units on this composite commercial site.
It was manifestly plain to all and sundry that it was no different from any of
the other units on the site which either had been or were in the course of or
were about to be commercially developed by this company with whom the
defendants were in contact prior to embarking upon the works on the river bed.
Mr Giles or anybody else would have replied: ‘This building has development
potential.’  They would have added,
provided always that the figures were available to them, that the real value of
the property was £26,000, the figure found by the judge.

In reality,
therefore, in making that award, I take the view that the judge has done no
more than reflect in the damages the true diminution in value of this site in
the circumstances of this case caused by the destruction of the building. The
award, particularly when contrasted with the cost of full reinstatement, in my
judgment, also passes the test of reasonableness. I add that test of
reasonableness because the authorities to which we have been referred indicate
that reasonableness always has to be taken into account. The judge must stand
back, when he has done his arithmetic, and ask himself whether the figure
achieved by his findings is fair both to the plaintiff and the defendants.

We have been
referred to a number of authorities by Mr Denyer, and by Mr Spens, on behalf of
the plaintiff. I propose to cite only one case, and that is C R Taylor
(Wholesale) Ltd
v Hepworths Ltd [1977] 1 WLR 659. It was a case
tried by May J (as he then was) and, in my view, sets out in a fairly lengthy
passage in the judgment all that need be known as to the law to be applied to
the case which is before this court. It is unnecessary that I should cite
extensively from the judgment, but the material passage is to be found at pp
667E-669C. Peter Pain J referred briefly to this authority in his judgment, and
I cannot improve upon what he said at p 6:

I have been
referred to a number of authorities as to the measure of damage in tort. In
some cases the court has awarded the diminution in market value of the building
or property; in other cases the measure of damages has been the cost of
reinstatement. But in none of the cases have the facts been similar to the
present case. I do not regard the authorities as confining me to award either
diminution in market value or cost of rebuilding.

Pausing there
for a moment, I have already observed that in my judgment what the judge went
on to do in this case was, in reality, an assessment of the diminution in
market value of Unit 7. The difference between the valuation placed upon it by
the defendants and that placed upon it by the plaintiff does not destroy the
proposition that in reality the award was for diminution in value. The real
difference between the parties here is as to how one goes about measuring that
diminution in value. Does one have regard to the potential of the
building?  Or is one disqualified from so
doing, although, as in this case, there is a specific finding that there was an
intention on the part of this plaintiff to redevelop, and although, as I have
already observed, the property formed part of a plot where precisely that form
of redevelopment was occurring?

Returning to
the judgment of Peter Pain J, he continued:

Looking at the
rather unusual facts of the present case, damages should be: ‘that sum of money
which will put the party that has been injured . . . in the same position as he
would have been if he had not sustained the wrong for which he is now getting
his compensation . . .’

per Lord Blackburn in Livingstone v Rawyards Coal Co
(1880) 5 App Cas 25 at p 39. The authorities have turned upon the question
whether that end is best achieved by an award of diminution in value or cost of
reinstatement.

I do not
think it necessary to review the authorities, but rather to confine myself to
quoting from a passage from the judgment of May J (as he then was) in C R
Taylor (Wholesale) Ltd
v Hepworths Ltd [1977] 2 All ER 784 at p
792a: ‘These two basic principles are, first, that whenever damages are to be
awarded against a tortfeasor or against a man who has broken a contract, then
those damages shall be such as will, so far as money can, put the plaintiff in
the same position as he would have been had the tort or breach of contract not
occurred. But secondly, the damages to be awarded are to be reasonable,
reasonable that is between the plaintiff on the one hand and the defendant on
the other.’

I would merely
emphasise what is there said by citing, as did May J in Taylor’s case,
the words of Lord Sumner in Admiralty Commissioners v SS Chekiang
(The Chekiang)
[1926] AC 637 at p 643:

The measure
of damages ought never to be governed by mere rules of practice, nor can such
rules override the principles of law on this subject.

And, as
Denning LJ (as he then was) in Philips v Ward [1956] 1 WLR 471,
at p 473, said:

It all
depends on the circumstances of the case . . . The general rule is that the
injured person is to be fairly compensated for the damage he has sustained,
neither more nor less.

It follows
that, in my judgment, subject to what I have later to say about matters of
detail, the judge’s approach to the assessment in this case was right and in
accordance with authority. Unit 7 had development potential. The plaintiff
company, by the destruction of the building, was deprived of that development
potential, and the figure which the judge found and the basis upon which he
made his calculations accurately represented that loss suffered by these
plaintiffs.

The rest of
the defendants’ appeal against the award turned upon factual matters which
realistically Mr Denyer abandoned, with but one exception. I must now deal with
that.

Mr Denyer
submitted that the figure of £13,000 did not represent objectively the proper
cost of refurbishment because, as Mr Giles acknowledged in evidence, his own
labour charges did not form a part of the equation. Hence, submits Mr Denyer,
the defendants should not be burdened with the additional sum that the absence
of such a labour charge creates in the equation calculated by the judge. At p 2
of the judgment the judge said:

. . . I can
accept as a rough figure [Mr Giles’] statement that his cost of refurbishment
was about half what he would have had to pay a builder for the same work.

Accordingly,
submits Mr Denyer, instead of £13,000 appearing in the equation, something over
£20,000 should have there appeared.

The problem
with that submission, as I see it, is that this point was never canvassed
before the learned judge and, accordingly, the argument was never ventilated.
Nor was the judge given any more detailed information than that which appears
in his judgment. In my view, it is now too late to introduce into this case the
type of objection raised by Mr Denyer to the calculation. This court simply has
not got the material, nor did the judge have the material, upon which to assess
the effect of Mr Giles — and, let it be remembered, he was not the plaintiff,
he was the managing director of the limited company — upon the cost to the
company of his working, as he said, free of charge. He was, of course, paid a
salary and would not be working free of charge for the company so long as that
salary was paid. Accordingly, I would not make any addition to the figure of
£13,000 to represent any gain that the plaintiff might have achieved as a result
of the finding that Mr Giles was prepared to work at a much cheaper rate than
any rival organisation. I repeat, the point was not taken before the learned
judge, and it is manifest from his judgment that it was not taken.

I turn to the
plaintiffs’ cross-appeal. It is now confined to two points, and I can dispose
of them quite briefly.

In the
forefront of Mr Spens’ submission to this court (and it was made in the court
below) is that, on a proper construction of the clause in the agreement to
which I have earlier referred, his client was entitled to the cost of
reinstatement, namely some figure between £117,000 and £155,000. The submission
of Mr Spens is that the wording of the clause imposed an obligation upon the
Wessex Water Authority to make good the physical damage that they had done. In
other words, it imposed upon the Wessex Water Authority not an obligation to
pay damages for diminution in value but an obligation to pay damages
representing the cost of reinstatement and nothing else. The judge dealt with
this short point of construction at p 5. He said, referring to leading counsel,
Mr Bursell, who appeared in the court below:

Mr Bursell’s
argument is that these words

— and he was
referring to clause 7 —

give the first
defendants a choice should damage be done: they may either180 make good the damage or pay compensation for it. Mr Spens’ argument for the
plaintiff was that those words bound the first defendants to reinstate the
premises if damage were done. The choice was merely as to who should do the work.
If compensation were paid, the amount should be cost of reinstatement.

I do not
think the words will support Mr Spens’ contention. As a matter of plain English
it seems to me that they gave the first defendants a choice. They can choose
whichever method is less costly. But it has to be noted that the letter refers
to ‘any damage’. These words do not limit compensation to the market value of
the building, but are wide enough to cover the loss that the plaintiff
sustained by reason of the frustration of its intention to refurbish and let
Unit 7.

I cannot
improve upon that ruling. In my judgment, it is virtually unarguable to
contend, as Mr Spens contends, that the proper measure of damages here on a
contractual basis is the cost of reinstatement. For the reasons given by the
judge in that succinct passage, I would dismiss the plaintiff’s appeal upon
that ground.

The other
point canvassed by Mr Spens on behalf of the plaintiff relates to the judge’s
finding that the proper percentage to apply by way of return on capital was 10%
and not the 12 1/2% that the judge found. It is worth looking at what the judge
said about this aspect of the case. It is to be found at pp 12-13 of the
judgment. Referring to Mr Steele-Perkins, he noted that his return figure was
10%, and he continued:

. . . Mr
Fitchett’s view was that a return of 15% would be appropriate on small units
such as these. Mr Giles proposed to let on 10 or 12 year leases, with full
repairing covenants. Further, he said that he often attracted tenants by taking
a reduced rent for the first year. It would have taken a little time to have
let the premises fully, especially as there might have been some tenant
resistance in view of their poor condition. Although Mr Steele-Perkins’ yield
of 10% is supported by impressive figures, I think it would be appropriate in
this case to allow for a yield of 12 1/2%.

We have been
taken by counsel to passages in the transcript where Mr Fitchett canvasses his
15% and where Mr Steele-Perkins canvasses his 10%. Both of these gentlemen were
experts in the field, both were local valuers. The judge saw and heard each of
them give his evidence. In my view, it is always appropriate in such a
situation where the judge is confronted with conflicting expert testimony for
the judge, if he thinks fit, to steer a middle course. Of course, he has not
got to fly in the face of the evidence. But, in my view, to make the finding
which he did, halfway between 10% and 15%, was in no sense perverse and was an
exercise upon which the judge was perfectly entitled to embark. He enjoyed an
advantage not enjoyed by this court. Accordingly, I would not interfere with
the finding that he made of 12 1/2%.

It follows
that, in my view, there is no merit in the complaints canvassed here by the
defendants against the judge’s assessment, nor in those canvassed by the
plaintiff.

I would
dismiss both the appeal and the cross-appeal.

GLIDEWELL
LJ
agreed that both the appeal and cross-appeal
should be dismissed for the reasons given by Russell LJ and did not add anything
of his own.

Also agreeing,
PURCHAS LJ said: I wish to add just a few words of my own on the
question of assessment of damages.

Mr Denyer, for
the appellants, submitted that damages could be awarded only on one of two
alternative bases:

(1)  the cost of reinstatement, which would in
this case involve a sum which the judge described as ‘grotesque’; or

(2)  damages representing the diminution in the
value of the property.

Evidence of the
value of the site was undisputed at £10,000; that is the site as it stood
immediately before the commission of the tort. Mr Denyer argued from this
proposition, therefore, that damages could never exceed the amount of the value
of the site as such. He submitted that the judge, having decided that the cost
of reinstatement was not reasonable, was stuck with a limit on the second
alternative.

For my part,
in agreement with Russell LJ, I cannot accept that the law relating to damages
in tort for trespass to property can be so simply stated. The trial judge
rightly, in my view, approached the problem from the long recognised maxim restitutio
in integrum,
which stems from the judgment of Lord Blackburn in Livingstone
v Rawyards Coal Co Ltd (1880) 5 App Cas 25 at p 29. The judge based his
assessment of damages upon the judgment of May J (as he then was) in C R
Taylor (Wholesale) Ltd
v Hepworths Ltd [1977] 2 All ER 784.
Obviously there may be cases in which the damages required to put the victim
back into the position in which he would have been will be the same as the
market value of the property concerned. On the other hand, there may be cases
in which the victim cannot be put back into the position which he enjoyed
unless there is completely physical reinstatement achieved or the cost of so
doing. These two propositions do not mean, however, that the judge, in
calculating the damages in accordance with the maxim, must look at one or other
alternative. For this reason, I cannot accept the submissions made so ably by
Mr Denyer. In my view, Peter Pain J was correct when he said that he was not
obliged to choose between the two alternative approaches.

The present
case does not fall at either end of the spectrum. The judge correctly
identified that the sum to be awarded for damages must include not only the
market value of the property as it stood but also damages to compensate the
victim for the loss of the profit he would have achieved had he been able to
develop Unit 7 along with the rest of the development. This represented the
market value of the property after the refurbishment had been achieved, had
that been possible, less the cost of the work and materials involved, and less
the value of the site after the tort, which was put at £1,000. It so happened
that the plaintiff company had as its director someone who could achieve the
refurbishment at a cost below that which would have been charged by a less
efficient contractor. I am unable to accept the argument that the damages must
be other than those reasonably suffered by the plaintiff company in the circumstances
actually prevailing. I do not think that the tortfeasor can avoid the
obligation to compensate the victim by having resort to some objective standard
or to the absence of knowledge in the tortfeasor about the particular position
of the victim, except in wholly exceptional circumstances, which clearly did
not prevail in this case. I think that the judge was correct to take into
account the estimated cost of refurbishment as it actually would have been
incurred had the company’s plans not been interrupted by the tortfeasor’s
wrong.

For these
reasons and the reasons given in the judgment of my lord, Russell LJ, I also
agree that the appeal and cross-appeal should be dismissed.

The appeal
was dismissed with costs; cross-appeal was also dismissed with costs.

Up next…