Back
Legal

Menzies Motors Ltd v Stirling District Council

Acquisition of motor workshop and garage at Stirling–Claim on alternative bases of development value and existing use value plus disturbance–Planning permission for supermarket held unlikely because of traffic problems–Disturbance claim for move to temporary and permanent premises–Allowed items include (a) heating of temporary premises, despite council’s ‘value for money’ argument; (b) adaptation of temporary premises on jobbing basis without detailed costs; (c) difference between statutory interest on unpaid compensation and overdraft interest due prior to payments to account by acquiring authority–Disallowed items include (i) overdraft interest on disturbance claim expenditure incurred after payments to account; (ii) architect’s fee for new building and costs of site investigation; (iii) surveyor’s fees for inspecting alternative premises before notice to treat–Existing use value plus disturbance ‘as high if not higher than development value’

Mr W L K Cowie
QC and Mr P Fraser (instructed by J & R A Robertson, of Edinburgh) appeared
for the claimants, and Mr D B Weir QC and Mr T C Dawson (instructed by Robson
McLean & Paterson, of Edinburgh) represented the acquiring authority.

Giving their
decision, THE TRIBUNAL said: This reference arises from a dispute as to the
compensation payable for a workshop and garage with land attached at Orchard
Place, Stirling, known as Menzies Motors Ltd and extending to 0.76 of an acre
(3,667 sq yds).

The claimants
are Menzies Motors Ltd, whose interest as owner-occupier was compulsorily
acquired by the Royal Burgh of Stirling under the Burgh of Stirling
(Comprehensive Development Area–No 1) Compulsory Purchase Order 1967 confirmed
by the Secretary of State for Scotland on July 26 1971. Notice to treat was
served on August 19 1971. It was agreed that July 9 1973 was the date of
valuation.

Buildings
Demolished

At the date of
the hearing the buildings had been demolished. The buildings had been
reconstructed in 1942 to accommodate a car showroom, petrol filling station and
a workshop for repairs, service and maintenance. The buildings occupied the
greater part of the site with a frontage to Orchard Place of 80 ft and to
Thistle Street/Goosecroft Road of 365 ft. Part of the Goosecroft Road frontage
was to an area of open land extending to 751 sq yds. This land was at a lower
level than Orchard Place (about 12 ft) and was not normally used by the garage
for parking of cars.

The claim
submitted was supported by evidence from Mr Henry J Crone FRICS FRTPI and was
stated in alternative forms.

Firstly, it
was claimed that as the site was suitable for the erection of a supermarket the
market value with that potential was £220,020, being 3,667 sq yds at £60 per sq
yd, and, in addition, that the costs involved in moving to temporary premises
should be paid as compensation. If it were held that a supermarket could not be
established, it was claimed that the site was suitable for other developments,
eg warehousing, in which case Mr Crone maintained that a rate of £60 per sq yd
was still appropriate.

Secondly and
alternatively, the existing use value of £168,145 plus the disturbance claim
should be determined.

It was
submitted that the higher figure of these alternatives should be determined as
the compensation.

The acquiring
authority’s contention, supported by valuation evidence from Mr Alexander T S
Cargill ARICS, senior valuer in the Inland Revenue Valuation Office in
Stirling, was that the value of the site for development purposes was £73,340,
being 3,667 sq yds at £20 per sq yd. The existing use value was £100,000 and in
addition he was prepared to accept a disturbance claim of £10,000. As the
£110,000 was higher than the value as a development site the £110,000 should be
the compensation.

In determining
the development value of the site, the question of whether planning permission
for a supermarket would be obtained was a fundamental issue. Planning
permission, in turn, depended on whether vehicular traffic could enter or leave
the site without creating a traffic hazard.

Evidence from
Mr Colin A J Beckett FRICS was led to establish that the site was a suitable
commercial one for a supermarket. He visualised the design being such that
there would be a basement area with a frontage to Goosecroft Road, which would
be used jointly for customer car parking and service facilities. He had not,
however, considered in any detail the solution to the traffic problems which
Goosecroft Road entry and exit would cause.

Mr Crone
recognised that there would be traffic problems but considered that a solution
to these would be a matter for the purchasers. He maintained that traffic
engineers could, by the design of slip roads, solve any problem which might
arise. Servicing of the site could take place from Orchard Place as an
alternative.

A contrary
view was expressed by two witnesses for the acquiring authority.

Traffic
Problem

Mr A F Goodwin
MSc MICE, burgh surveyor at the time, said that his advice was sought as to the
traffic problem if a supermarket were to replace the garage relative to the
traffic conditions at July 1973. If there had been no comprehensive development
of the area, he said, Thistle Street would have remained. The cost of altering
the public services would be a strong argument for that decision. He said that
if a plan demonstrating a method of entry and exit to and from the site had
been produced with a planning application for a supermarket he would have had
to consider it, but in regard to the standards laid down, he did not consider
that a visi-168 bility attainment sufficient to allow approval could have been devised. This
view was derived from the curve of Thistle Street, the habitual lane-changing
by owners and the danger to pedestrian use which would result from the removal
of a sufficient length of pavement to allow the formation of a slip lane in and
out of the site. It was difficult, in his view, to visualise a scheme which
would allow sight lines sufficient to achieve the requisite stopping distances.
He was against Orchard Place being used as a service access.

Mr G A
McLennan, who is now depute director of planning, Clackmannan District Council,
but was formerly with the Burgh of Stirling, stated that, in his view, planning
permission for a supermarket would not have been approved of a part from the
comprehensive development proposals. The main objection would be the question
of access. His advice to the planning authority would be to refuse the
application on traffic grounds. He agreed that permission had been given for a
Littlewoods store and a Fine Fare supermarket with only a temporary solution to
servicing access but that these permissions were in the context of the central
area being comprehensively developed.

Having regard
to the apparent traffic difficulty in connection with use of the site and the
conflicting views of the claimants and the acquiring authority on such a vital
matter affecting the value, we consider that it is for the claimants to
persuade us that the traffic problem can be solved. The claimants provided no plan
to demonstrate that a solution could be reached, and in absence of such plan it
is our view that it would be difficult, if not impossible, to provide a
satisfactory access and exit for servicing a supermarket development to and
from Goosecroft Road. We also consider that servicing from Orchard Place would
not be satisfactory or acceptable because of the congested nature of this
cul-de-sac.

We cannot
find, therefore, that it was likely that planning permission would have been
obtained for the erection of a supermarket on this site.

Mr Crone
considered that even if a supermarket was not allowable, the site could be
developed for offices or warehousing. Before dealing with the value of the site
for such a purpose, we prefer to deal with the existing use value and
disturbance and thereafter to test that figure against the development value of
the site.

Existing Use
Value

We firstly set
out the conflicting values of Mr Crone and Mr Cargill adjusted to the agreed
areas and related to capital rate 5 per sq ft.

Mr Crone

Mr Cargill

sq
ft

@

@

(i)

Showroom and offices

2,272

£10.50

£23,856

£5.50

£12,500

(ii)

Upper floor

2,352

£2.60

£6,115

£1.50

£3,528

(iii)

Garage

23,391

£5.25

£122,802

£2.75

£64,325

(iv)

Forecourt

(v)

Pump-tanks

2,831

£2.60

£7,360

£2.58

£7,300

(vi)

Land

751
sq yds

£12.00

£9,012

£15.00

£11,265

£169,145

£98,918

Deduct 
ground burdens of £30 x 10 YP

£300

£98,618

£169,145

say

£100,000

Mr Crone did not try to support his valuation by any comparable
sales or lets and thought, in any event, that any comparisons would not be of
much help in valuing the special property of Menzies Motors.

Mr Cargill
relied on the comparison of a sale of a central site garage in Stirling in
April 1974. The garage at Allan Park, Stirling, together with four houses and
an area of land was sold for £120,000 in a transaction between the owners and
Stirling Town Council. It was said to be a market transaction and without
compulsory powers. Mr Cargill’s analysis of this transaction is as follows:

Showroom and offices

2,170
sq ft

@

£10.00

£21,700

Garage–workshop

21,304
sq ft

@

£3.00

£63,912

Forecourt
(covered) including  lock-ups

5,602
sq ft

@

£2.25

£12,604

Upper-floor office

400
sq ft

@

£2.00

£800

£99,016

Add

Four 3-apartment flats with vacant possession  £4,000 each

£16,000

Ground 381 sq yds @ £15

£5,715

£21,715

£120,731

say

£120,000

In arriving at the value of Allan Park, Mr Cargill had regard to his
analysis of two sales in Bishopriggs and Airdrie in 1969 which, so far as the
buildings were concerned, brought out rates, adjusted for the time factor, at
£3 and £3.20 per sq ft overall. His analysis of an overall rate for the Allan
Park buildings was £3.90 per sq ft and for Menzies Motors £2.90 per sq ft. We
think the £3.90 is wrongly calculated and should be £3.67.

Mr Crone said
that his firm had valued Allan Park when it was on the market at £100,000. There
appeared to be some doubt in his mind as to whether the houses had been rent
restricted. In any event, he considered the ultimate sale price of £120,000
‘was probably just about right.’

Neither valuer
considered the throughput of petrol sufficiently high to value the forecourt on
a throughput basis nor did they consider it necessary for a town centre garage
to have land attached to it. This was in contrast to the valuation approach of
the valuers in the recent tribunal case of Park Automobile Co Ltd v City
of Glasgow District Council
(1975) 235 EG 307, 385.

Allan Park is
the only comparable we have before us and we consider it as close a comparison
as one may expect to have. The sale is about the same date. The property is in
the town centre of Stirling and is about the same size. We therefore accept the
sale as a comparison to be used in valuing Menzies Motors.

Mr Cargill
considered that the showroom and offices of Allan Park were superior in both
standard and location to Menzies Motors. Mr Crone did not give an opinion on
the differences between the two properties. Having inspected Allan Park we can
see that there is a distinction in standard, but we are not convinced that so
far as a car showroom is concerned the location would influence a purchaser, provided
that it is reasonably central. The assessor has apparently placed a much higher
gross annual value on Allan Park, but this may be due to his placing a shopping
rate on the showroom consistent with the rates he has applied to adjacent
shops. This analysis was not revealed to us. We consider that the differential
determined by Mr Cargill is too large and determine a rate for the showroom of
£7 per sq ft. He had made a slight distinction in the garage parts. We have
inspected Allan Park and do not consider the distinction justified. As Menzies
Motors has been demolished we cannot make a comparison by visual inspection.
From the information available, however, we do not consider that the rate for
the workshop should be less than £3 per sq ft. The upper-floor office at Allan
Park appears superior and we determine the upper floor of Orchard Place at
£1.50 per sq ft.

The two
valuations of the forecourt of Menzies Motors were about the same. Mr Cargill
had placed a higher value on the vacant land than Mr Crone.

169

Our
determination for the existing use value is therefore as follows:

Showroom–offices

2,272
sq ft

@

£7.00

£15,904

Garage

23,391
sq ft

@

£3.00

£70,173

Upper-floor stores

2,352
sq ft

@

£1.50

£3,528

Forecourt

2,831
sq ft

@

£2.58

£7,300

Land

751
sq yds

@

£15.00

£11,265

£108,170

Deduct 
ground burdens of £30 x 10 YP

£300

£107,870

say

£108,000

Disturbance Claim

We now deal
with the disturbance claim. Mr Arthur Willcox-Jones, the managing director of
Menzies Motors Ltd, explained that steps had been taken over a number of years
since the compulsory purchase order was made to find suitable alternative
premises. A permanent site in Goosecroft Road has been offered by the acquiring
authority, and provided that suitable terms can be reached it is proposed, if
financially viable, to erect new garage premises on it. He considered it
essential to stay near the centre of Stirling to maintain his business.
Pressure was put on him to vacate Orchard Place in July 1973 and he moved to
temporary premises in Goosecroft Road made available by the town council. No
financial terms were or are agreed so far for the use of these premises. The
disturbance items relate to the temporary move and the permanent move as and
when it takes place.

A number of
items have been agreed and amount to £3,174.63. The remaining items are in
dispute and we shall refer to them by item numbers as shown in the claimant’s
schedule.

Items 11
and 12.
These were for heating the temporary
premises and consist, firstly, of the hire of heaters at £145.75 and, secondly,
the installation of a more permanent heating installation by the gas board at a
cost of £3,751, being £1,493 for the installation and £2,258 for the supply of the
units.

These items
are not admitted by the acquiring authority, first as being extravagant and
second as representing ‘value for money’ in that heating was included in the
value of Orchard Place and that the rent for the temporary premises would
reflect that they were unheated and the rental saving would cover the heating
costs.

The ‘value for
money’ argument applies not only to this item but also to other items, so we
shall deal with it first. We accept that heating has been included in the value
of Orchard Place, and in the normal way if heating had to be provided in
purchased premises or premises taken on lease, such expenditure, if it
increased the value of the interest, would not be allowed. If a reduction in
rent were given for a temporary let and that reduction equated with the costs
involved, then these costs might not be allowed. In this case, however, we were
not informed what the rent terms are and therefore cannot determine whether the
costs will equate with any reduction in rent. It is clear, however, and
accepted by Mr Cargill, that the expenditure has not increased the value of
Menzies Motors’ interest in the temporary premises and that on removal the
money spent will be lost. There was no indication that the owners will
reimburse Menzies Motors for any expenditure on the premises. We do not
consider the ‘value for money’ argument valid in this case.

With regard to
the charge of extravagance it appears to us that the hire of heaters was not
unreasonable and that the sum of £145.75 should be accepted.

The gas board
account is more difficult. Mr Willcox-Jones himself expressed some dismay at
the amount of the account. Owing to a misunderstanding it had been thought that
a sum of £1,642.30 was involved compared with a tender for oilfired units at
£1,139. The units can probably be reused in the final premises and therefore a
credit against the total cost should be made for their value. We therefore
allow the actual cost of the temporary installation amounting to £1,493
together with a sum of £1,250 for the units, a total of £2,743.

Adaptation of
Temporary Premises

Item 13. The structural alterations, repairs and renovations were carried out
on a jobbing basis costing £8,915.68. Details of the work proposed to be
carried out were provided to us. No details of the work done or the detailed
cost was supplied to us at the hearing. We accept that as the work was done on
a jobbing basis it was difficult to provide the cost of each item.

Again there is
criticism of this item by the acquiring authority on the basis of ‘value for
money’ and that more was done than was necessary for a temporary period. We
have dealt with the ‘value for money’ argument in the previous item and
consider that what we have said applies to this item as well. Mr Cargill made
his own estimates against the various items which he was prepared to concede
and proposed that £637 be paid under this heading.

We have
inspected the work carried out on the temporary premises. Our inspection
revealed that the total cost included items which were not on the list given to
us. In particular, a substantial amount of electrical work had been carried
out. We did not find any signs of extravagant expenditure on the premises and
it all appeared necessary to allow the business to continue and to meet the
requirements of the appropriate authorities and in particular the fire officer.
Some of the items such as lighting fittings may be able to be used in the
permanent premises, but the value of these items could be offset by the cost of
dismantling and removing.

Counsel for
the acquiring authority conceded that as no detailed costs had been provided by
his witness, he was not challenging the claimants’ figure if we rejected his
arguments on extravagance and value for money. We allow the cost of £8,915.68.

Item 14. Architect’s fees for temporary accommodation at £1,950. This is
accepted in principle by the acquiring authority, but the amount was rejected
on the basis that the work on which the fee is based included items which were
not admitted. As we have accepted that the work carried out on the temporary
premises is allowable we shall allow the claim. We accept that the claimants
were entitled to employ an architect to arrange and supervise the work.

Item 15. Supplying and fitting compressor, steam cleaner and two hoists at
£1,890.81. This item was criticised by the acquiring authority on the grounds
that a new compressor was not necessary and that the hoists should have been
removed from the old premises. The steam cleaner was accepted.

Mr Willcox-Jones
explained that the compressor was necessary for all air lines and that this
together with the two hoists had to operate until removal. It was essential to
have the hoists and compressor functioning at the temporary premises to
continue the work. The compressor in Orchard Place was six/seven years old and
worth £50/£60. He has this in his possession. The lifts in Orchard Place were
fairly old and worth about £50; they had been left.

We consider
that the new compressor can be used in the new permanent premises and the
reserve one used during the changeover. So far as the new lifts are concerned,
we consider that these will be utilised in the new premises. We are prepared to
allow the installation of the lifts at the temporary premises and the removal
to the new premises. We shall allow the removal of the compressors. Taking into
account the inconvenience during these changeovers we shall allow a sum of £900
to cover this item.

Item 16. This is for resiting the lubricating equipment and is agreed at £362.76.

170

Overdraft
Interest

Item 17. This is a claim for overdraft interest on the amounts expended on
the disturbance items. At the date of the hearing it had amounted to £3,132.71.

This claim is
rejected by the acquiring authority in view of the fact that two payments to
account had been made, one of £50,000 on November 27 1973 and one of £53,500 on
May 3 1974, which payments exceed the expenses incurred in removal.

Interest will
accrue on the total compensation figure from the date of entry at the statutory
rate. The payments to account will be reflected in the calculation of interest.
It was suggested by the claimants that the payments to account were for the
property, but, as counsel for the acquiring authority pointed out, section 48
of the Land Compensation (Scotland) Act 1973, which authorises such payment to
account, refers to ‘any compensation’ without specifying property or
disturbance. We consider, therefore, that these payments to account cover the
outlays which have been made and that no claim for overdraft interest for the
period following the first payment to account can be allowed. Interest is, of
course, still accruing on any balance of the final compensation as determined.

There appears
to be an overdraft interest amounting to just under £60 due prior to the first
payment to account, but any claim can only be for the difference between the
statutory rate of interest and the overdraft interest. We have no information
as to what this amounts to, but assuming a 2 per cent difference and an overdraft
interest rate of 14 per cent the amount involved is one-seventh of £60, say £9.
We accordingly allow this £9. In effect, the cost of bridging finance is offset
by the accrual of statutory interest.

Items
18-19.
Architect’s fees for new building and costs
of site investigation amounting to £13,503.65.

These are
rejected by the acquiring authority as being a part of the cost of the new
building. If the basis of compensation was the reasonable cost of equivalent
reinstatement under section 12 (5) of the Land Compensation (Scotland) Act
1963, then these could be allowed. In the present case, however, where
compensation is being assessed under section 12 (2), this is not so.

Counsel for
the acquiring authority further argued that if the claimants chose to spend
their compensation on building new premises that was the claimant’s own
decision. Accordingly the acquiring authority were not liable for any costs
involved in a new building. We agree with this view and cannot allow the item.

If the
claimants were unable to re-establish themselves with the compensation for the
property, it would have been open to them to pursue a claim for extinguishment
of business as an alternative. No such claim was made.

Surveyors’
Fees

Item 20. This is Henry J Crone & Partners’ account for £4,693.33. Leaving
out the scale 5 fee, which is calculated on the amount of the compensation, the
net amount is £2,456.33. A substantial part of this amount is in connection
with inspecting alternative premises, some of which inspections were done prior
to the date of the notice to treat. These latter items were conceded by counsel
for the claimants as being irrecoverable in law because they were incurred
before August 19 1971, although a plea was made to us to include them in the
special circumstances of this case. No legal basis, however, was argued before
us to justify this and we are left having to exclude them. The acquiring
authority admitted four items (it should be five) amounting to £890 and we
accept that.

A sum of £615
is charged for meetings and correspondence in connection with alternative
sites. The acquiring authority consider this excessive and, in any event, state
that some of this account is relative to work done prior to the notice to
treat. They propose £300. We allow a sum of £400.

A sum of £455
is claimed as the fee for negotiating the Goosecroft Road site. No details have
been given to us about this negotiation. The acquiring authority say it is
incompetent because no agreement has been reached. We cannot accept that, as it
is an expense which the claimants will have to meet as a consequence of the
compulsory purchase. If the claimants had purchased alternative premises,
professional fees would have been reimbursed. No alternative figure has been
put forward, so we accept the £455. Expenses amounting to £100.08 are also
claimed. No reasons were given for challenging that amount and we allow it. The
total under this item is accordingly £1,845.08.

Expenses of
Second Removal

Items
21-30.
These are the expenses involved in the final
move and are a repeat of the earlier items. The same amounts have been put
forward with an increase of 25 per cent, being the anticipated cost at the
estimated time of removal. The acquiring authority have allowed most of the
items in principle, although Mr Cargill has taken the same figure as the cost
of the first removal on the basis that the projected cost would have to be
deferred to take into account the accruing interest. Interest will accrue on
the sums awarded from the date of entry and if we took the projected costs we
would require to defer these back to July 9 1973 to take into account the
interest accruing from that date. The position is complicated in this case by
the payments to account, but on the whole we consider that the way Mr Cargill has
dealt with it should be accepted. If we took the projected cost and did not
defer, the claimant would get more than he is entitled to.

Items 21-27 amount to £2,910.41 and on the basis stated above we allow that.

Item 28 is rejected by the acquiring authority. This is a sum of £46.90 for
fire appliances being removed and upgraded. It was, however, allowed in the
first move. Mr Cargill said he had been generous in the first place and that
servicing was a continuing process. Having accepted the principle for the first
move, it is difficult to see how we can reject it in the second move. We
accordingly allow it.

Items
29-30.
These are items involving the installation
by the gas board of the units from the temporary premises and the architect’s
and surveyor’s fees if the revised scheme is proceeded with. The acquiring
authority reject these as incompetent. We consider the installation of heating
into the new premises as part of the building costs and, therefore, as
explained before, not allowable. We also accept that the architect’s fees are
disallowable for the reasons set out previously in relation to the cost of a
new building.

The
determination for the existing use value and disturbance is therefore as shown
at the top of the next column.

A calculation
was made by Mr Cargill purporting to show the value as a going concern by
analysing sales relative to turnover and there was then added disturbance items
arising from extinguishment of the business. This produced a figure of £88,200,
but it was not applied as his estimate of the compensation for the loss was
£110,000. We do not therefore feel it is necessary to consider this analysis.
We should say, however, that we consider it would be necessary to investigate
the profit and loss accounts of the various transactions before accepting an
analysis on turnover.

We still have
to consider whether the value of the site available for commercial development
which creates no traffic problem is greater than the existing value plus
disturbance stated above. Our determination of compensation of £130,857
relative to the site of 3,667 sq yds represents a rate of just over £35 per sq
yd.

Mr Crone’s £60
per sq yd was derived from two sales:171

(a)  Property

£108.000

(b)  Disturbance

Agreed items

£3,174.63

Heating (temporary)

2,743.00

Adaptation of temporary
property

8,915.68

Fees (architect)

1,950.00

Compressor etc

900.00

Lubrication

362.76

Overdraft interest

  9.00

Fees (valuer)

1,845.08

Second removal

2,957.31

22,857.46

130,857.46

Add  surveyor’s fee–scale 5 of the RICS scale of
charges

1,401.75

£132,259.21

(1)  A sale in 1970 to Fine
Fare in Murray Place at a price of £85,050. This related to an area of 1,494 sq
yds, representing about £57 per sq yd. This was for a supermarket, planning
permission having been received and satisfactory arrangements made about
servicing and parking.

(2)  A sale of the Plaza Cinema in May 1973 to the
Post Office at a price of £55,000 for a site of 571 sq yds: the rate per sq yd
is about £96. Mr Crone had been of the opinion that the rate was £61.90 per sq
yd, but he did not appear to dispute Mr Cargill’s information about the price
or area.

Mr Cargill’s
£20 per sq yd was based on the following:

(1)  The Picture House, Orchard Place (adjoining
Menzies Motors) in August 1972 purchased by the acquiring authority for
£27,500, representing a rate of about £25.50 for 1,077 sq yds.

(2)  The TA Centre, Goosecroft Road purchased by
Samuel Properties in July 1972 for £75,000–a rate of £16 per sq yd.

(3)  The Gas Works site east of Goosecroft Road
purchased by the acquiring authority in September 1973 for £40,000,
representing a rate of £14 per sq yd.

(4)  May Day Yard, Thistle Street, purchased by
the acquiring authority from British Rail for £40,000 in May 1971, representing
a rate of £6.57 per sq yd overall or £20 per sq yd for first 40-ft zone. There
was an area of 1.258 acres.

(5)  Area adjacent to Menzies Motors with various
owners. The total cost was £54,950 and the price represented an overall rate of
£10 per sq yd.

(6)  Littlewoods purchased a site in September
1970 for £169,000 at the corner of Port Street and Dumbarton Road. The area was
2,253 sq yds and the price represents £75 per sq yd. Mr Cargill considered that,
relative to 1973 values the price could be equivalent to £85/£90 per sq yd.

(7)  If the sale of Allan Park garage is analysed
as a development site it represents £25.30 per sq yd.

We have
considered all these transactions. The two highest sales have planning
permission for intensive retail developments, and as we have determined that an
intensive retail development would not be allowed on the Menzies Motors site we
do not accept them as direct comparisons. The high rate brought out for the
Plaza Cinema, which is not a prominent retail site, confirms the view expressed
by Mr Cargill, and accepted in the record by the claimants, that the price paid
was for its value as a bingo hall. The fact that the Post Office may use it for
redevelopment purposes does not establish that the price is for a development
site. Statutory authorities, for technical reasons, have often to purchase at
values for existing use, including disturbance, which are more than the value
as a cleared site available for development.

The rates
produced by Mr Cargill tend to support his £20 per sq yd and in any event do
not justify a rate of more than £35 per sq yd.

We therefore
consider that the compensation of £130,857.46 is as high if not higher than the
development value of the site and determine it at that figure. Including
surveyor’s fees the sum is £132,259.21. We meantime reserve the question of
expenses.

Up next…