Building contract – Breach of contract – Practical completion
Building contract – Breach of contract – Practical completion
Building contract – Breach of contract – Practical completion
Building contract Arbitration
Building contract – Arbitration – Defective premises – Remedial works – House built with benefit of NHBC Buildmark policy – Claimant owner claiming for defects in property – Partial award…
Building contract Collateral warranty
Building contract – Breach of contract – Collateral warranty – Time limit – Claimant lessee claiming damages in respect of breach of collateral warranty for works carried out on stadium…
Building contract Delay
Building contract – Delay – Extension of time – Prevention principle – Liquidated damages – Respondent engaging appellant to design and build property – Works being delayed – Appellant seeking…
Building contract Implied term
Building contract – Construction – Implied term – Respondent undertaking to demolish, reconstruct and refurbish buildings owned by appellant – Dispute arising concerning construction of contract – Whether judge rightly…
Building contract Exclusion clause