Land Compensation Act 1961 – Compulsory purchase order (CPO) – Landfill site owned by appellant – CPO withdrawn but appellant kept out of possession of land for three years –…
Taxation – Compensation
Compulsory purchase, Compensation
Compulsory purchase order (CPO) – Compensation claim – Defendants acquiring claimant’s underlease – Whether compensation to be reduced to take account of dilapidations liability from which claimant relieved as result…
Compensation Disturbance Remoteness Grant of statutory wayleave for electricity cables Paragraph 6 of Schedule 4 to Electricity Act 1989 Land not yet in use for…
Adviser’s failure to give proper advice
Town and country planning – Compensation
Land – Depreciation in value – Compensation – Highway – Respondents failing to adopt new highway within three-year time limit – Whether appellants eligible for compensation – Whether highway maintainable…
Statutory wayleave – Electricity cables – Compensation to landowners – Whether loss of profits from business recoverable as separate head from diminution in value of land – Whether loss too…
Compulsory purchase order — Water authority acquiring land for sewage treatment works — Landowner claiming compensation — Lands Tribunal making award for loss of use of land — Defendants treating…
Compensation for depreciation — Part I of Land Compensation Act 1973 — New highway — Section 19(3) three-year time limit — Highway not adopted within three years — Claim for…
When property is compulsorily purchased by, for example, a local authority acting in their capacity as a highway authority, the owner receives compensation.