Mr Justice Tugendhat :
1. By a judgment delivered on 10 December 2004 [2004] EWHC 3185 (QB) Mitting J made a declaration that a planning permission (“the planning permission”) granted to the claimant on 25th February 1991 had lapsed. The planning permission was in respect of land in
2. In the present proceedings the Claimant seek what is in effect an alternative claim, namely damages for professional negligence against its planning consultant the Defendant (“PLA”). This is a two partner firm in Bishop Auckland.
3. The claimant’s case is that, both before and after the grant the of outline planning permission,
4. The complaints against
5.
6. For PLA it is submitted that the central issue on liability is confined to the questions arising out of the telephone conversation between
7. Alternatively, the defendant’s case is that the claim is statute barred. PLA contend that by 28th November 1996 (the date six years preceding the issue of the Claim Form), the claimant had already suffered significant damage, in that there was by then no longer sufficient time before the 14th December deadline to submit a scheme of landscaping (which the defendant contends would have taken three to four weeks to prepare), that the conditions precedent in fact required approval to have been given before the deadline (not just submission), and that that would have taken a further two weeks. The claimant denies that damage had been suffered by
8. The damages claimed in the Claim Form amounted to some £16 million, being the alleged difference between the value of the land with the planning permission (£18m) and the value once it had lapsed (£2m). By the time the experts on land valuation had met and produced the joint report dated 27th November 2007, it was agreed between the parties that the open market value of the land as at 14th December 1996 with the benefit of the planning permission, and subject to the reserved matters approval, was £1,125,000. The remaining difference between the parties was confined to the value of the land on that date without the benefit of the planning consent. The land was at all times available for business and industrial use, although it was not in fact so used. The claimant contends that without the planning permission the land was worth in the region of £250,000, and PLA contends it was worth £700,000. The issue on damages thus came down from £16 million, to a maximum claim of £875,000, against a minimum claim of £425,000.
9. A significant feature of this case, which is material to understanding the issues of negligence and quantum, is that the proposal to develop the site was closely linked to a proposal of Durham County Council (and now Darlington Borough Council as a unitary authority) to turn a disused railway line running along the North edge of the site into a new road, from which there would be very much better access to the site than there was before. The new road, joining the A1 West of Darlington to the A66, was originally known as Cross Town Route (CTR), and had been expected to be built in 1994. However, the funding was withdrawn, as it happens on 15th December 1994, the day after the reserved matters approval had been given. The road is at the time of the trial before me in the course of being built under a new name, the Eastern Transport Corridor (“ETR”). But the ten year delay in commencing work on that road is part of the explanation of why this case covers so long a timescale. In October 1996 the claimant and a prospective purchaser of the site were contemplating making an application under the Town and Country Planning Act 1990 s.73 for an extension of time, and they did in fact make such an application, albeit that it was unsuccessful. Unless otherwise stated, all further references to a section of a statute are to the Town and Country Planning Act 1990. The works that were done to the site on 11th and 14th December 1996 were no more than was thought to be the minimum to ensure that the permission did not lapse (in the event that the application made for an extension of time were to prove unsuccessful). Interest in the site revived in 2001, and in June 2002,
Events up to February 1994
10. I gratefully adopt Mitting J’s account of many of the facts. I reproduce that with only minor alterations, and make such additions as are necessary to explain the present action. The facts found by Mitting J are now undisputed, save in so far as they relate to Mr Hepker’s evidence in relation to Mr Lavender.
11. The site is about 19.41 hectares on either side of a now disused tobacco factory in
12. In 1989 three planning applications were submitted by John Lavender on behalf of the claimant under its former name, Brencham Properties (
13. The first application was not determined within eight weeks, and the second and third were refused by
14. The conditions relevant to this claim are (i) to (iv), (vi) and (xii) and (xiii) and read as follows:
(i) approval of the details of the siting, design, and external appearance of the buildings, the means of access thereto and the landscaping of the site (hereinafter called ‘the reserved matters’) shall be obtained from the Local Planning Authority,
(ii) application for approval of the reserved matters shall be made to the Local Planning Authority before the expiration of three years from the date of this permission.
(iii) the development hereby permitted shall be begun either before the expiration of five years from the date of this permission, or before the expiration of two years from the date of approval of the last of the reserved matters to be approved, whichever is the later,
(iv) no development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of landscaping which shall include indications of all existing trees and hedgerows on the land, details of any to be retained together with measures for their protection in the course of development, and details of the type and number of trees to be planted and their size at the time of planting. … The scheme required by this condition shall include the provision of:
(i) a planted mount with fence to act as a noise and visual buffer between the Cross Town Route and houses on Red Hall Estate, and
(ii) tree planting along the eastern boundary to reduce the visual impact of the retail development when viewed from the A66 trunk road, ….
(vi) development shall not begin until details of all roads and vehicular means of access have been submitted to and approved by the Local Planning Authority
….
(xii) development shall not begin until details of all means of enclosure on the site have been submitted and approved by the Local Planning Authority,
(xiii) development shall not begin until details of car and pedal cycle parking and of provision for loading and unloading vehicles have been submitted to and approved by the Local Planning Authority.”
15. “Outline planning permission” was defined by Article 1(2) of the Town and Country Planning General Development Order 1988 as:
“a planning permission for the erection of a building, which is granted subject to a condition requiring the subsequent approval of the local planning authority with respect to one or more reserved matters”.
16. “Reserved matters” were also defined in Article 1(2) as:
“in relation to an outline permission, or an application for such permission, means any of the following matters in respect of which details have not been given in the application, namely: (a) siting, (b) design, (c) external appearance, (d) means of access, (e) landscaping of the site”.
17. Section 92(2) of the Town and Country Planning Act 1990 lays down the time within which building or other operations must be commenced pursuant to a grant of outline planning permission:
“(2) Subject to the following provisions of this section, where outline planning permission is granted for development consisting in or including the carrying out of building or other operations, it shall be granted subject to conditions to the effect:
(a) that, in the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of outline planning permission; and
(b) that the development to which the permission relates must be begun not later than
(i) the expiration of five years from the date of the grant of outline permission; or
(ii) if later, the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last of such matters to be approved.”
18. Conditions (ii) and (iii) thus followed the statutory requirements exactly. Condition (i) mirrored the statutory provisions in the General Development Order. Therefore to comply with and so to preserve the planning permission, the claimant had to submit an application for the approval of reserved matters by 25th February 1994.
19. The decision letter was addressed to Healy & Baker, the very well known and large firm in
20. On 1st October 1990 Mr Nicholas Peet, who was then giving instructions on behalf of the claimant, wrote to Mr Lavender, thanking him for his efforts, and asked him to render what he called Mr Lavender’s final account. On 8th October 1990 PLA rendered an account in the sum of £533.97 for which the narrative was:
“Continuing services in connection with the proposals for the development of land at Lingfield Estate Darlington, including liaison with Messrs Healy & Baker on preparation of public inquiry, and provision of information and drawing in connection with the proposed scheme and ownership boundaries”.
21. That account was paid in full by the claimant, but not before May 1991. The claimant had fallen out with Mr Peet. On the next day, 9th October 1991, Mr Hepker wrote to Mr Lavender telling Mr Lavender to apply to Mr Peet for payment, saying “In the event that you do not receive payment from him, kindly revert to us so that we can consider our position”. Mr Lavender reluctantly did as he was asked. There was in fact no basis for the claimant to dispute their liability for PLA’s fees, and the purpose of the request and the delay was to use PLA as a means to get evidence in their dispute with Mr Peet.
22. On 1st March 1991 Mr Lavender received a copy of the decision letter from Healy & Baker. On the very same day he wrote to Mr Hepker. He asked for his outstanding fees, as he had on a number of previous occasions. He then referred to the time when his firm was originally instructed, saying that it was then on the basis that should a planning permission be achieved, his firm would be retained to advise on further stages of the scheme. Although his fees remained unpaid, he was still keen to continue to work for the claimant. He remained keen throughout the time with which I am concerned. This led to him taking the initiative, that is taking steps without prior specific instructions, more often than may have been required to fulfil the claimant’s requirements, although the claimant was generally (but not always) content with his having spent time for which he subsequently sent invoices.
23. Mr Lavender wrote to the claimant and spoke on the telephone to Mr Cartwright on a number of occasions in the following two years, mainly to keep him up to date with information from the
24. On 26th November 1992 PLA submitted an invoice in the sum of £1,054.17 for the period end of September 1990 to the week ending 13th November 1992. It was for 22 hours of Mr Lavender’s time, and 2.5 hours for the time of an assistant. That invoice was paid promptly. The narrative started:
“Continuing monitoring of the planning situation since our last invoice dated 8th October 1990, with particular regard to the progress of the proposed [CTR]…”
25. On 25th March 1993
26. On 24th June 1993
“As we have discussed and agreed previously, it would be a sound tactical move on our part to prepare a Reserved matters application for the construction of the roundabout on the [CTR], as it would send a very clear message to the County and Borough Councils that you have no intention of foregoing your permission won on appeal… As we also agreed, this application should be made sooner rather than later, and to this end, I have discussed the proposal with the firm of Simpson Coulson and Partners, who have submitted a quotation for undertaking the necessary design work for the roundabout. A copy of their letter … is enclosed [it was for £1,550 plus VAT]… and I would be pleased to receive your further instructions as soon as possible”.
27. At the same time Mr Lavender was acting for the claimant jointly with a Mr Petch, who wanted to develop a car showroom on part of the business park site, concerning an application for planning permission for that. Also on 24th June 1993 Mr Lavender wrote to Mr Cartwright for approval of counsel’s fees to be incurred in that connection.
28. On 19th July 1993
29. On 31st July 1993 PLA sent a further invoice to the claimant in the sum of £923.62, for 20.75 hours work from 14th April to 31st July 1993. The narrative started with the same words as in the previous invoice, and referred to a number of meetings with third parties, and occasions of liaison with the claimant.
30. On 4th August 1993
31. Discussions with Darlington proceeded, but
32. Mr Hepker was very displeased with
33. It was in these circumstances, and at the very last moment, that PLA applied for approval of reserved matters by a letter dated 24th February 1994 the relevant parts of which read:
“Further to recent discussions between Messrs. L. Mulrine and J. Smith of your department and
From the Inspector’s decision letter of 25th February 1991 it is noted in Condition (i) that the matters reserved for the Local Planning Authority’s consideration are:
1. The details of the siting, design and external appearance of the buildings.
2. The means of access thereto.
3. The landscaping of the site.
Condition (ii) of that letter requires that an application seeking approval of the reserved matters shall be made before the expiration of three years from the date of the outline planning permission. This timescale has been complied with in the submission of this application, and the drawings enclosed deal with the three areas of reserved matters listed above ….
Whilst details of roads, accesses and landscaping are submitted as required for reserved matters purposes, it is acknowledged that further levels of detail will be required as set out in the various conditions attached to the outline planning permission, but such details will be required, for example, before development is commenced on site, or before buildings are occupied, according to the wording of the conditions.”
34. On the same day
35. On 8th March 1994
The reserved matters application and the judgment of Mitting J
36. In his judgment Mitting J said:
9. An application form of even date in Form RM1 accompanied the letter. It is headed “Application for approval of reserved matters”. It referred to 17 drawings submitted with the application numbered 393/01-15, drawn by PLA and 14773/01 and 02 drawn by Simpson Coulson & Partners, Consulting Engineers. Drawings 393/01 and 02 were amended and supplemented in August 1994 by versions 01A and 02A.
10. The PLA plans contained details of site layout and elevations of buildings and the number and location of car parking spaces. The Simpson Coulson drawings were a location plan for a road to be built along the northern boundary of the site by Durham County Council and a scale drawing of a new roundabout. It is not, and could not reasonably be suggested, that the letter, form and drawings were, when submitted, anything other than an application for approval of reserved matters only, in fulfilment of conditions (i) and (ii). Their timing and express wording leave no room for any other interpretation for the following reasons.
(1) They contain no reference to the remaining conditions of the planning permission other than to state that further details will be required before the development can begin.
(2) The references to the matters specified in conditions (iv), (vi), (xii) and (xiii) are vestigial and incomplete. In particular :
(a) the drawings of the western part do not indicate existing trees or hedgerows or details of any to be retained. Photographs produced this morning indicate that there are in fact a number of trees on the western part.
(b) the drawings of both the east and western parts do not specify the number and type of trees to be planted. There is only a general indication of landscaping of parts of each segment.
(c) the notes against the areas to be landscaped at the borders of both the east and west parts of the site state “Details of planting scheme to be submitted and approved before development commences” and in the car parking areas “Tree-shrub planting to be approved by the Local Planning Authority”.
11. It is arguable that the drawings would be capable of satisfying conditions (xii) and (xiii), if lodged with the Local Planning Authority for that purpose. The conditions do not require means of enclosure of the office development; and the details of the means of enclosure of the retail units are briefly, but arguably, adequately, specified in the relevant drawings and, although details of the car parking, such as bay size, turning areas and pedestrian access could have been required before the Local Planning Authority’s approval was given, the drawings did specify the numbers and locations of loading and car parking spaces. Though unlikely to be approved without more detail, they were capable of being approved.
12. But, beyond question, the drawings did not satisfy condition (iv), for the reasons given.
13. The [claimant]s contend that however matters started,
16. Thus, it is in my view clear, that although the law requires no formality other than the making of an application, ordinarily in writing, it does require that such an application is made and does require that it is made in such a way that the Local Planning Authority understands that it is an application for matters other than reserved matters.
37. On 20th April 1994 PLA sent a further invoice to the claimant in the sum of £1,522.22 for 36 hours work over the eight months period from 31st July 1993 to 31st March 1994. The narrative again started with the words “Continuing monitoring of current planning position…” and referred to the particular matters in which Mr Lavender had been engaged: the potential development of adjacent land to the East, discussions with Darlington and
“Discussions with the clients to agree procedures to be adopted to maintain planning status of development land, and submitting a renewal application in August 1993 on the outline permission granted on appeal in 1991”.
38. On 6th May 1994 Mr. Lavender wrote to
“In all respects, and this was confirmed by Messrs. Mulrine and Miller, the Reserved matters application is entirely in accordance with the requirements and conditions laid out in the outline planning permission, and given that all technical requirements have also been met, there is no reason why the Reserved matters should not be recommended for approval, and in due course, approval should be granted by the Council.”
39. Mitting J said in relation to this letter:
“Again
40. The claimant points to two other passages in that letter. As to the first passage, the claimant submits that what it states is that there were no other matters to be dealt with if reserved matters approval were granted. The passage reads:
“Once Reserved matters approval is granted, it means that even if the County Council at a late date, decided not to build the [CTR] our clients’ site could be developed in accordance with the original outline planning permission”.
41. In my judgment that passage does not add anything. It does not say that the outline planning permission contains no other conditions to be addressed.
42. The second passage in the letter of 6th May 1994 to which the claimant refers is as follows:
“On confirmation of the County Council’s scheme proceeding on site, or perhaps on the letting of the contract, our client’s scheme would be amended in layout terms to cater for the revised accessing arrangements, and
43. The point the claimant makes in relation to that passage is that it demonstrates a mistaken view of the legal position put forward for
44. A question of major importance to both parties and the subject of both conditions (i) and (vi) was the means of access to the site. The original scheme envisaged that access to the eastern part would be gained via a roundabout on the proposed new road at the north eastern corner of the eastern part. Durham County Council proposed that the roundabout should be resited to the
45. Meanwhile,
46. Relations between
47. There were a number of exchanges between
“2. Regard [sic] the landscaping proposals, and given the additional condition contained in the outline planning permission concerning the submission of landscaping details, we agree that a further submission of such details will be made, and we accept a wording on the Reserved matters approval to that effect.”
48. The additional condition referred to is condition (iv). For the claimant it is submitted that the inclusion of that paragraph is evidence that
49. On 24th August 1994, in a document drafted a few days before by
“Planning Policy Background
The application is for the approval of reserved matters and as such there are no policy issues to be addressed …
Planning issues
The main issues to be considered in the determination of this application are whether the proposed layout, access, design, appearance and form of building are acceptable, these are considered in turn. …”
50. The building designs were considered satisfactory. Under the heading “Floorspace and layout”, Mr. Miller observed:
“The floor area of the proposed business park and car parking provisions is acceptable …. Whilst large areas are set aside for landscaping, the landscaping within the car parking areas is not satisfactory and the applicants have stated that they will be willing to discuss these details further.”
51. Two pages of text were then devoted to the means of access and the alterations required by the shifting of the site of the proposed roundabout. Mr. Miller recommended that the Sub-Committee authorise him to negotiate a section 106 agreement to deal with it. His recommendations concluded:
“(b) That upon the satisfactory completion of the said Agreement and the submission of additional satisfactory landscaping details, the Director of Development Services be granted delegated authority to issue an approval for the submitted reserved matters.”
52. The Sub-Committee accepted his recommendations without amendment and produced a resolution to that effect.
53. In relation to these documents Mitting J said this:
26. The text of
27. The reference to “the submission of additional satisfactory landscaping details” in the recommendation and resolution was ambiguous taken in isolation; but, in the context of the paragraphs in the report headed “Floorspace and layout” its meaning is clear: it refers to landscaping within the car parking areas. The context in which that was said to be unsatisfactory is that of the area of such landscaping. It is contrasted in the same sentence with the “large areas set out for landscaping” in the site as a whole. The report does not state or imply that the scheme of landscaping required by condition (iv) would be dealt with as part of the reserved matters.
28. The letter sent by an administrative officer to the [claimant] notifying them of the subcommittee’s decision on 26th August 1994 states:
“I wish to inform you that the Planning Application Sub-Committee at its meeting on 24th August 1994 resolved to approve the details for the proposed development, subject to certain planning conditions and subject also to an agreement being entered into between yourself and the Local Planning Authority under section 106 of the Town and Country Planning Act 1990, to cover other aspects of the proposed development.”
29. Mr. Miller says, and I accept, that the letter adopted standard wording. It did not purport to nor, as a matter of law, could it, alter the effect of what the Sub-Committee had in fact resolved.
54. A draft section 106 agreement was sent by the Borough Solicitor to PLA on or about 5th September 1994. Preamble (4) stated:
“The Council has decided to grant approval for the details subject to certain conditions and subject to the making of this agreement which shall constitute a planning obligation within the meaning of section 106 ….”
55. Mitting J observed in relation to this:
31. The reference to “the details”, though ambiguous, cannot alter the effect of the Sub-Committee’s resolution. Mr. Miller was unable to say what the “certain conditions” were. The most likely explanation is that it was simply a repetition of the words which appeared in the standard notification letter of 26th August 1994 and so had no significance.
32. The [claimant]s were anxious nevertheless that the words should be removed and in due course they were. Mr. Hepker, for the [claimant], asserts in his witness statement and in evidence that the removal of these words was of cardinal importance to him and was one of the matters which led him to believe that
“As I explained when we spoke on Thursday, 17th November, I have met with the Borough Solicitor to amend the wording of the agreement to exclude the reference in (4) of the preamble to any planning conditions, as none are to be attached to the reserved matters approval.”
33. All that the removal of the offending words meant was that the approval of reserved matters would not be subject to conditions. It had no bearing on satisfaction of conditions other than condition (i).
56. The evidence before me includes a number of documents. There is a draft of the s.106 agreement sent by Darlington to Mr Lavender on 31st August 1994, both of which Mr Lavender faxed to Mr Hepker on 5th September 1994. The next day Mr Hepker faxed back to Mr Lavender a draft letter to be sent to
57. On 14th November 1994
58. On 18th November 1994 Mr Lavender wrote two letters on the topic, one to Mr Hepker and one to Mr MacGeagh, each of which enclosed the final version of the agreement. In the letter to Mr Hepker Mr Lavender wrote:
“As I explained when we spoke on Thursday 17th November, I have met with the Borough Solicitor to amend the wording of the agreement to exclude reference in (4) of the preamble to any planning conditions, as none are to be attached to the Reserved matters approval”.
59. In the letter to Mr MacGeagh Mr Lavender wrote:
“You will see that there is no reference to any further conditions – the reference has been deleted as there are no new conditions, the only relevant conditions being those attached at the grant of the outline planning permission in February 1991”.
60. Meanwhile, in the light of the measure of agreement already reached with
61. The section 106 agreement was executed and reserved matters approval was given on 14th December 1994. Recital (4) stated:
“The Council has decided to grant approval for the details subject to the making of this Agreement which shall constitute a planning obligation within the meaning of section 106 of the Act of 1990 … by a document of even date (hereinafter called ‘the Planning Permission’) enclosed as an Appendix.”
Clause 1(b) provided:
“This Agreement shall not come into effect and the covenants on the part of the Company contained in Clause 2 shall not be enforceable unless and until the planning permission has been granted and the development has been commenced by taking material steps in accordance with section 56 of the Act of 1990.”
62. Clause 2 set out the terms of that covenant which, in summary, was to construct an alternative access road linking up with the roundabout proposed by Durham County Council rather than the one originally shown on the submitted plans.
63. The “planning permission” referred to in both preamble (4) and clause 1(b) of the section 106 Agreement was the reserved matters approval of 14th December 1994. It reads:
“Notice of Approval of Reserved matters
Your application dated 24th February 1994 and amended by details received on 11th and 16th August 1994 on behalf of Lingfield Properties Limited,
For details of siting, design and external appearance, means of access and areas to be landscaped for retail park, business park, related commercial development, roads and non-food retail park, business park related commercial development and roads and land at Lingfield Estate, McMullen Road, Darlington,
and submitted pursuant to Planning Permissions won on appeal, reference numbers” — they are then set out — “on 25th February 1991, is hereby approved.”
At the foot of the notice the following words appear:
“Please ensure that you have all necessary consents before commencing the development, including any necessary approval under the Building Regulations 1991.”…
64. As to this Mitting J observed as follows:
38.
39. While I do not doubt the genuineness of
40. As far as condition (vi) is concerned, his belief is well-founded. Darlington clearly accepted the section 106 Agreement in place of, and so in discharge of, condition (vi); but there is no firm evidence that Mr. Lavender negotiated on that footing in respect of the other conditions, let alone procured
“I am of the opinion that in the form of discussions and correspondence involving officers of the Local Planning Authority and myself, all reserved matters submissions arising from the appeal allowed on 25th February 1991 were satisfactorily submitted to Darlington Borough Council on 24th February 1994 and duly approved on 14th December 1994 subject to a section 106 Agreement. Furthermore, through those discussions preceding the approval of reserved matters, all conditions arising from the appeal decision were properly considered and addressed, it being accepted by the Local Planning Authority that details required by those conditions were substantially incorporated into the reserved matters submission, and subsequent areas of minor detail would remain to be addressed during the course of development of the land.”
41. That statement is studiously ambiguous. It is flatly contradicted by
42.
43. I accept that there was a degree of practical compulsion in the matter and some urgency. I accept that Durham County Council and
44. For those reasons, although I accept that there was, in the background, a degree of practical compulsion to get the reserved matters approved, I do not accept that there was any practical compulsion on either side to secure discharge of the remaining conditions.
45. Two ancillary questions arise about the reserved matters approval. First, as far as the mound to the north of the site is concerned,
46. Secondly, the note at the foot of the reserved matters approval does not assist
47. In the event, events followed rapidly the one upon the other because on 15th December 1994 the Government announced that it would not fund the
“11. Up to the said conversation on 11th October 1996,
12. In response to that suggestion, Mr. Hepker instructed Mr. Lavender that the defendant had better get on with it and make sure that the scheme of landscaping was done and Mr. Lavender stated words to the effect that that was fine and that he, on the behalf of the defendant, would get on with it.”
48. Mr. Hepker said that he believed that Mr. Lavender did in fact make such an application. I have seen no evidence of it and do not accept that it was made. If it had been, I would be both surprised and disturbed that
65. The evidence before me was different from the evidence before Mitting J. As Mr Hepker pointed out, the matter came before Mitting J under CPR Part 8, and there was not the disclosure that has taken place in this action. More significantly, Mr Lavender declined to give evidence before Mitting J, and declined even to make in proper form a witness statement based upon what he had written in his document dated 27th July 2001 (to which I shall return). The document dated 27th July 2001 has no heading or other words such is to be expected of a statement to be used in court proceedings.
66. Moreover, Mr Miller gave evidence before Mitting J, but not before me. A witness statement was given by Mr Miller to Mr Lavender for use in the present proceedings, but Mr Lavender chose not to adduce it in evidence. The claimant did not seek to rely on any evidence from Mr Miller.
67. The facts found by Mitting J in his judgment which are in dispute in the present action relate to
68. Having considered the point myself, I respectfully agree with the finding of Mitting J in paras 39 and 40 of his judgment that:
“the change in wording does not bear the weight that he puts upon it for reasons which I have already explained and I am satisfied that the notice of approval of reserved matters was just that and no more. I am also satisfied that the wording of the stamps on the drawings meant nothing more than that their details were approved as reserved matters… As far as condition (vi) is concerned, …
69. I also respectfully agree with what Mitting J said in his paragraphs 43, 44 and 45. But whatever Mr Hepker’s state of mind was at the time he gave evidence before Mitting J, and notwithstanding Mitting J’s findings in relation to that, on the evidence before me I find that Mr Lavender did not believe that the s.106 agreement had the effect that there were no further conditions to be fulfilled before development commenced, and he did not tell Mr Hepker that it did have that effect. If Mr Hepker believed that there were no further conditions to be fulfilled, that was not a belief induced by Mr Lavender. At best it was a case of Mr Hepker being confused.
70. The progress of the negotiations on the form of the s.106 agreement, as set out above, give no basis for a finding that the deletion of the words in Recital (4) was linked in any way to an attempt by
71. It is the claimant’s case that at some point
The position following the grant of Reserved matters Approval
72. In early 1995 Mr Lavender exchanged correspondence with
73. On 7th March 1995 the claimant entered into an agreement with Priory Estates (Glasgow) Ltd (“Priory”) for the sale of the site for £2.275 million subject to the satisfaction of conditions precedent. One of the conditions precedent was that finance be irrevocably committed for the CTR (except for an amount up to £2.5m to be contributed by Priory) such that direct access to the site could be available (without the consent of any third party) when the retail units to be constructed on the site were to be open for trading.
74. Ten days later on 17th March 1995, Priory entered into a related agreement with La Sande (Holdings) Ltd (“La Sande”) for the sale of the land to La Sande. La Sande in turn entered into joint venture agreement with Taylor Woodrow. La Sande were not happy with the proposed layout of the development for which the planning permission made provision. They proposed a development with a substantial element of leisure of facilities, upon which they entered into discussions with
75. On 31st March 1995 PLA invoiced the claimant in the sum of £1,599.64 for 35 hours work in the period 1st October 1994 to 31st March 1995. The narrative started with the words: “Continuing advice and assistance to the client with regard to the planning position and potential future development…” of the site. Particular work referred to included the work on the boundaries, “negotiations with … Darlington … to successfully secure section 106 agreement and release of Reserved matters approval”, and other liaison with
76. There had been another invoice submitted on 20th October 1994, which is not in the bundle, but for which Mr Lavender wrote requesting payment on 7th April 1995. On 19th April 1995 Mr Hepker responded that the invoice of October 1994 was “considerably higher than we had anticipated”. He added:
“Without wishing in any way to deny the attentiveness of your professional service, you appeared to have spent rather more time than we had wished on matters which were peripheral to our central concerns… The sheer size of your invoice created a difficulty for us in that it had not been included in our cash flow projections with our bankers.”
77. Mr Hepker enclosed a cheque for £1,599.64 in settlement of the most recent invoice and four cheques in the sum of £1,348.69 dated 19th May, June, July and August 1995 (total sum of £5,394.76), adding “These will clear our indebtedness to you in as short a period as our cash flow enables”.
78. It is difficult to know what to make of Mr Hepker’s reference to “cash flow projections with our bankers”. I consider below the financial position of the claimant company, which apparently had no income. But the Hepker family was not in a financial position that would have made it difficult to fund the expenses of the claimant, as in fact it did. I do not doubt that those members of the family interested in the claimant could have found the £5,394.76 required to pay PLA’s invoice promptly, and were not constrained by the limited cash flow referred to. This episode, and the earlier delay in paying his fees referred to above, left Mr Lavender with the impression that the claimant was reluctant to spend money on the site. The case advanced at trial was that Mr Lavender did not understand, or ought not to have understood, that there were financial constraints on what should be done in relation to the site. Nevertheless, I find that Mr Lavender did form that view, and reasonably so, in the light of Mr Hepker’s reference to cash flow as a reason for not paying the invoice promptly. On 6th July 1995 he wrote to Mr Hepker about the boundary matter, asking for instructions. He explained: “I have no wish to incur unnecessary expenditure on your part…”
79. The last year for which the accounts of the claimant show any income other than interest is the year ending 30th March 1990. For that year there is shown a rental income of £167,014. For the year ending 30th March 1991 there is shown income by way of interest of £1,125,671.
80. Except for the exchanges about PLA’s invoice and the litigation with Mr Peet, Mr Lavender had very little to do with or for the claimant in 1995 until 20th September. On that date he wrote giving some information relevant to the site. And on 30th September 1995 he sent an invoice in the sum of £975.66 for 19.5 hours work from 1st April 1995 to 30th September 1995. The narrative starts “Continuing advice and assistance to client with regard to matters arising in connection with future development of” the site. The invoice refers to the work on the boundary and adds: “This area of work ceased on instructions from the client on 10th July 1995”. This invoice was not paid until the end of May 1996.
81. In 1996 Mr Lavender had no involvement until the telephone call from Mr Hepker of 11th October. This was not because nothing was happening. On 17th April 1996 a company called Ellkington Developments Ltd wrote to Mr Hpker confirming discussions about a joint development. The letter included a reminder (if Mr Hepker needed one) as follows:
“In order that [the planning permission] remain extant following [13th December 1996], material operations must be held to have been commenced on site, and those operations must relate to the development approved in the Reserved matters submission”.
82. In June 1996 Mr Hepker was in communication with a Mr Adrian James of Barton Willmore Planning Partnership, who were acting for clients who had an interest in the site. Mr Hepker was also in communication with Mr Dunn and Mr Aykroyd of Bradstead Ltd, another company with an interest in the site. Mr Lavender was aware that things were going on, but not of any role he might have. On
83. It is the claimant’s case that
84. Mr Lavender’s explanation for not doing this was that he thought that what Mr Hepker knew about the deadline was sufficient. If the claimant is right that there was such a duty, then they do not have to establish a reason why it was not fulfilled. In fact the case put forward for the claimant was that Mr Lavender was himself confused. I have not so found.
85.
86. Mr Hepker has drafted a high proportion of the documents in this case. While this may have had the effect of saving solicitors’ fees, that was not the primary reason for Mr Hepker acting in this way. Rather it reflected his wish to apply his own skills. He wrote not only the numerous letters from the claimant signed by him, but also other documents, including letters to be sent by solicitors acting for the claimant. In July 1995 he drafted a witness statement to be made by Mr Lavender in proceedings which the claimant was involved in against a Mr Peet, the former director of the claimant through whom Mr Lavender was first instructed by the claimant. In December 1996 Mr Hepker drafted instructions to counsel to advise. He has also carried out a number of tasks in the course of the present proceedings which are commonly carried out by solicitors, including copying documents and approaching witnesses and reviewing drafts of their witness statements.
87. In my judgment the deadline can be easily derived by a lawyer without specialist planning expertise, such as Mr Hepker, from a reading of the 1991 letter communicating the planning permission. There was no requirement upon Mr Lavender to spell things out in more detail than he did, at any rate before October 1996.
88.
89. In my judgment that overlooks the reality of the situation. The investment sunk into the site might be lost in any event, if the CTR were not built. When the reserved matters application was made it was still uncertain whether or when the CTR would go ahead. It was uncertain whether the claimant would itself carry out the development, or whether it would sell the land with the benefit of planning permission. In my judgment, up to October 1996, a reasonable view could have been that a scheme of landscaping was as likely as not to be a waste of money. If the development was to be carried out at all (which was uncertain so long as the CTR was not built) it was to be carried out long after the planning permission had been obtained, and quite likely by a developer other than the claimant. In those circumstances a scheme submitted before October 1996 might well not have been appropriate to the development, (if it was ever going to be carried out at all). Moreover, the time and expense involved in preparing such a scheme is relevant to consideration of this point. The evidence as to this was called, and I consider it, in relation to the limitation point. Moreover, so long as the claimant was looking for another developer to be involved, there was a real possibility that the costs of the scheme of landscaping might not have to be borne by the claimant. This is what happened when the works were carried out in December 1996. The claimant did not bear those costs.
90. There is no dispute that Mr Hepker telephoned Mr Lavender on
91.
92. In cross-examination
93. This account of the conversation is not easy to follow because, as both sides now agree, it assumes a mistaken understanding of the legal position. Mr Hepker stated that it is obvious that Mr Lavender was mistaken.
94.
95. There are a number of contemporaneous, or near contemporaneous, documents which assist me in my findings as to what was said. These include: a memorandum from Darlington’s Head of Development Services,
96. In the memorandum to the Borough Solicitor, dated 1st October 1996,
97. What led to
98. The note of
“John Lavender 11/10/96.
99. The note does not record that Mr Hepker gave any instructions to Mr Lavender. In so far as it is controversial, it is the last sentence of the note that is most in dispute, Mr Lavender saying that that was not a suggestion from himself, and Mr Hepker saying that it did come from Mr Lavender. Mr Lavender said that he did not say that, and that it was a misunderstanding which he had not been under. Mr Lavender also considers the first sentence of Mr Lavender’s note to be curious in using the word “believe”. He said the
100. The significance attached by Mr Ullstein to the first and last sentences of the note was that if Mr Lavender did say what is in those sentencea, then that shows he thought there was no real urgency in fulfilling the landscaping condition. That in turn would be an explanation for why Mr Lavender did not carry out the instructions that Mr Hepker claims to have given on 11th October. This conclusion is said to be supported by the fact that in the case of Mr Petch certain conditions of a planning permission Mr Lavender had obtained for him had not been fulfilled before the commencement of the works.
101. The fax from
“Thank you for sending me a sheet drawn from the fax to you from Bill Parkington…
As to the views expressed in that sheet concerning the effect of an application under s.73 for the variation of Condition (i) [it should be (ii)] of the Planning Consent of 25th February 1991, my comments (on behalf of Lingfield Properties (Darlington) Ltd (“LPDL”) are as follows:
1. It does not make sense for LPDL to apply to vary Condition [(ii)] without varying Condition [(iii)] because there can be no doubt that application for reserved matters approval was made by LPDL before 24th February 1994. This is recited in paragraph (2) of the preamble to the S.106 Agreement executed by Darlington Borough Council on 14th December 1994; and was the specific subject of a Notice of Approval of Reserved matters of that date, attached as a schedule to the S.106 Agreement. I cannot therefore see how they can now argue that they have the power to re-impose this Condition. [I interpose to say that
2. Instead what they might do is to agree (and this would have to be by deed) that the existing S.106 Agreement and Reserved matters Approval should be replaced by a fresh S.106 Agreement and Reserved matters Approval in identical terms, in which case the life of the existing consent would be extended by 2 years from the date of the fresh Agreement and Approval.
3. In answer to Bill’s specific question this does mean that, if no separate extension of time were granted, the life of the planning consent would not be extended merely by the local authority agreeing a variation of Condition [(ii)]. Legally, this might be something of a minefield, since if the local authority had encouraged someone to apply for such a variation on the basis that the variation would have that effect, the local authority might (in legal jargon) be estopped from denying the validity of its assertion. In other words, it might be held to its promise. I suggest that it would not be desirable for our fate to depend upon a tricky legal doctrine such as estoppel; and that it would be preferable to have a fresh S.106 Agreement and Approval.
4. A more promising line lies in the wording of the said paragraph (2) and Notice, which both refer to “details of siting, design and external appearance, means of access and areas to be landscaped…” This contrasts with the wording in Condition (i) [the reference is correct at this point], which refers to “details of … the landscaping”; and with Condition (iv), which requires with a large degree of precision a “scheme of landscaping” to be submitted to and approved by the Local Planning Authority before development can take place. The question arises whether Condition (iv) is an independent condition or whether it is a specification of what is called for in Condition (i) [the reference is correct at this point], i.e. whether or not Condition (iv) is one of the Reserved matters requiring approval. The better view seems to be that it is. If this is right, the difference in wording becomes highly material because in fact no scheme of landscaping (as opposed to an indication of the areas to be landscaped) has ever been submitted to the Local Planning Authority. (I checked this point today with our architect John Lavender, who submitted our Reserved matters Application). This means that it may now be open to LPDL to submit a scheme of landscaping to the Local Planning Authority, the approval of which would trigger off a further two years, since this would become “the last of the reserved matters to be approved” within Condition [(iii)].
4 [A] In summary, the best course of action would appear to be to agree with the Local Planning Authority a s.73 application to vary Condition (ii) [it seems likely that the reference is correct at this point] so as to extend the life of the consent for an agreed period. (My view, though I am not certain, is that this would extend the life of the consent by 2 years, whatever the period agreed, because approval of the last of the Reserved matters would be deemed to have been given on the date of approval of this application).
[5] The next best course of action would be to submit a scheme of landscaping for urgent approval, preferably obtaining the express agreement of the local authority to treat this as the last of the reserved matters to be approved.
[6] If there was any doubt that either of the above would be effectuated before 14th December 1996, and then LPDL should make a commencement of material development, say early November.
[7] Least favoured would be the suggestion of the local authority, that Condition [(ii)] be varied by a s.73 application but that Condition [(iii)] be left intact.
[8] In any event, it may be prudent, if there is any doubt that any of the above might run beyond 14th December 1996, to submit an application under Regulation 3(3), making it clear that this is purely an alternative to one of the above and only to be pursued in the event that it does not materialise by 14th December.”
102.
103. The memo sent by Mr Parkington to Brian Smith dated 14th October 1996 refers to “your” (that is Brian Smith’s) recent comments. But there are no comments in the file from Brian Smith. Mr Parkington also apologises for confusion about the numbering. But that is a point made by Mr Hepker in his comments to Brian Smith. It seems likely that Mr Parkington was sent a copy or summary of Mr Hepker’s fax of
“So far as using the argument that all the reserved matters applications have not yet been approved and hence that the two year period has not yet begun to run, from my discussions with
104. Questioned about this,
105. By the letter of 17th October
106. The part of the memo of 7th November (from Mr Parkington to Brian Smith) that was sent to Mr Hepker includes a list of things needed to develop a site including: (1) planning permission, (2) no outstanding planning conditions and (3) an unblemished title. The document then explicitly addresses the first and third of these three, but at least part of the document which might be expected to include a discussion of point (2) is missing, and the different lengths of the two surviving sheets of paper would be consistent with about one inch of the second sheet having been cut off. Mr Hepker explained in evidence that that is how he received the document, and that he had not himself removed any part of it.
107. Meanwhile it appears that
“The only other option would be to commence implementation. However, as noted in our letter of 26 September [which is not before the court], you are not, and are now unlikely to be, in a position to do so because you have not satisfied conditions (iv) … which require submission and approval of various details prior to the commencement of the development”.
108. On 19 November 1996 La Sande wrote separate letters to different departments of Darlington trying to persuade them that the s.73 application could be entertained by
109. The memo of 22nd November 1996 from Mr Parkington to Mr Smith includes:
“In relation to planning one matter
110. This document demonstrates clearly that by
111. The memo of 27th November (from Mr Parkington to Brian Smith, document numbered 65 by Mr Hepker) notes that Darlington had by then accepted verbally that that s.73 application by La Sande was a valid application, and sets out eight matters which remained unresolved. The last of these reads:
“There is an outstanding argument as to whether all the ‘reserved matters’ were applied for and granted. Apparently the landscaping proposals were not complete although the decision notice clearly includes ‘landscaping’. It is our view that the ‘reserved matters’ obligation has been complied with but it may still be necessary to submit further details in order to comply with a separate planning condition in due course but that is not subject to any time limit”.
112. The memo then continues raising the question whether, bearing in mind the problems with the existing consents, “should we be looking once again at commencing work on the existing scheme before the consent runs out in December”? Mr Parkington notes the problem of what would constitute a meaningful start. He then goes on, in a passage which includes some words which I omit, to make the following observation: “we will inevitably be in breach of a number of other planning conditions such as submission and approval of landscaping details… Can these breaches be viewed as negating a start on site being made”.
113. This passage is a reference to condition (iv) (amongst others). Asked about it in evidence,
114. The letter from Mr Lavender to Mr Hepker dated 27th November is signed by Mr Padgett “pp J Lavender”. It read as follows:
“I trust you will not mind my sending this short letter to note that on 14 December 1996 the Reserved matters approval expires for the retail park site at Lingfield Estate,
115. Mr Hepker mistakenly understood it to be a letter from Mr Padgett and not from Mr Lavender. In chief Mr Hepker said that he read it as suggesting that the claimant should proceed with works which they were planning to commence in any event in December. In cross-examination he said that when he received it he was planning to go to counsel Mr T Comyn for advice on what to do in any event. Mr Lavender was not involved in the conference with counsel (who also advised that works be commenced). On 6th December, the day after the conference Mr Hepker did contact Mr Lavender to ask him to attend to witness the works to be undertaken on 11th December.
116. Mr Hepker gave evidence that he spoke to Mr Padgett in November 1996. He at first linked the conversation to the date of the letter, but he kept no note and in evidence accepted that he could not be sure of the date. It is common ground that they had spoken to one another by telephone from time to time in the past when Mr Hepker wished to pass a message to Mr Lavender. Mr Hepker said that on this occasion the conversation was about s.73. Mr Hepker said the he said that Priory were going to make a s.73 application and that PLA should assist. Mr Hepker said that he did not discuss landscaping, and simply asked if everything was OK, or if everything had been done. His evidence was that he assumed that that included landscaping. Mr Hepker’s evidence is that Mr Padgett said that he could not be sure, he had not spoken to Mr Lavender, but that he thought that Mr Lavender had done everything. Mr Hepker’s evidence is that he assumed that everything was fine and that Mr Lavender had submitted a landscaping scheme and would help with the s.73 application.
117. It is PLA’s case that Mr Hepker invented the November telephone conversation with Mr Padgett. Mr Padgett gave evidence that he could not recall a conversation with Mr Hepker such as Mr Hepker describes.
118. Both
119. He was cross-examined upon the case of his client
120. The Instructions to Counsel drafted by Mr Hepker cover ten pages. The history is recited. Mr Hepker referred to the grant of planning permission on 25th February “subject to an extensive list of conditions”, and to the two reasons why it could not in practice be implemented: the boundary problem and the delay on the CTR. He referred to there being two potential purchasers, Priory and Bradstead. In relation to Priory Mr Hepker wrote:
“… Mr Smith has assembled a high powered team to hand the development, consisting of La Sande (NW) Ltd, planning and development experts, whose principal representative is a chartered surveyor called Bill Parkington, and Taylor Woodrow, the builders. This team has been in negotiation with Darlington Borough Council and with the various highways authorities with a view to substituting the food consent on the Land for a leisure consent in consideration of their contributing £4.3m to the CTR. They would ideally hope to start construction of the CTR in May 1997 and of the retail and leisure units in September 1997”.
121. I observe that there is no suggestion in the instructions that Mr Lavender was involved at that stage.
122. The instructions included documents listed in 100 descriptive paragraphs. The documents referred to above dated on and between
“(1) Principal Matter
1. What is the best way of keeping the planning consent of 25th February 1991 alive beyond 14th December 1996? (see in particular documents 57 to 64)
(2) Subsidiary Matters
…
5. Should a commencement of material development be made before 14th December 1996 (See the memo dated 22nd November 1996 from Bill Parkington to Brian Smith).
6. Since the two years run from the date of approved [sic] of the last of the reserved matters to be approved, and since details of landscaping have not been approved (or have they?), could it be argued that the two years have still not started to run? (Consider para 4 of the letter dated 11th October 1996 from M Hepker to Brian Smith; and the memo dated 22nd November 1996 from Bill Parkington to Brian Smith)”.
123.
124. The advice was given by counsel in conference, and a detailed note made by Mr Hepker. In that note it is recorded in relation to question 5 that there is a difficulty in that condition (iv) is a separate condition and there can be no development until a scheme of landscaping is approved. Nevertheless counsel advised the claimant to begin development (as defined by s.56). He referred to Whitley v Secretary of State for
“…the developer by commencing operations before obtaining approval would be taking risks. He would be taking a risk that he might not obtain approval and a risk that the authority could for example serve a stop notice or take other enforcement action. However, if the developer is prepared to take these risks then the purpose of the legislation is achieved by permitting the permission to be lawfully implemented irrespective of whether or not the approval is before the commencement of the operations.”
125. Next to question 5 Mr Hepker noted: “that does not run”.
126. On 6 December (a Friday), in the telephone conversation Mr Hepker asked Mr Lavender to check whether the s.73 application was on the agenda at
127. Mr Hepker gave evidence that in the conversation of 6 December he reported to Mr Lavender what counsel had advised, and that he had assumed that all conditions had been satisfied. Mr Hepker’s evidence is that Mr Lavender reassured him that that was not a problem, or that that was fine, or words to that effect. Mr Lavender’s evidence is that nothing of the kind was mentioned. If counsel had assumed that all conditions had been satisfied, that fact is not apparent from Mr Hepker’s note of the conference.
128. On
129. Apart from one communication irrelevant to the matters I have to decide, the next communication between
“Matters arising from time to time … in dealing with planning position regarding development site at Lingfield Estate, including attendance on site when excavating of proposed roadway took place and liaising with prospective purchasers of site”.
130. I have no hesitation in preferring the evidence of Mr Lavender and Mr Padgett and in rejecting the evidence of Mr Hepker where it conflicts with theirs.
131.
132. The documents that I have summarised above demonstrate that there was before and in October some discussion between Mr Parkington and Darlington, and some of the statements made by
133. It is not necessary for me to find why no instruction was given by
134. I also note that the suggestion that Mr Hepker had given instructions to Mr Lavender on
135. I find that Mr Hepker gave no instructions to Mr Lavender to submit a scheme of landscaping on or after 11th October 1996, and that absent such instructions, Mr Lavender owed no duty to the claimant to do so. I am fortified in this conclusion by my findings as to the events that occurred subsequently. I find that Mr Lavender was a careful, conscientious and efficient in the performance of his services to the claimant. That had been the view of each of Mr Cartwright and Mr Martin Smith in the period in which they had dealings with him. It remained the position, in my judgment.
Events after 1996
136. The next communication between Mr Lavender and Mr Hepker was a year later, in a letter Mr Lavender wrote on
137. There was no further contact between
138. The doubts about whether the works done in December 1996 would satisfy s.56 continued in the minds of Priory and La Sande for some years. But La Sande in due course formed the view that matters had changed. On 9th April 2001 Mr Hepker responded to a call from Mr Lutton with a fax confirming his, Mr Hepker’s, view that there appeared to be “some substance to Bill Parkington’s suggestion that a commencement of material development may have taken place before expiry of the relevant … period”. Referring to the work done in December 1996, he wrote that
“it was undertaken pursuant to memos and correspondence from inter alia Bill Parkington to Brian Smith in November 1996 warning him that the 3 year period was about to elapse. I too was aware of the fact and had been in touch with both Brian Smith and John Lavender to arrange the work”.
139. On 19th April 2001 Mr Elkins sent a letter to Mr Hepker on behalf of La Sande. Mr Elkins had been a project manager with Taylor Woodrow, and had represented that firm in providing assistance to La Sande, when the two companies were jointly interested in developing the claimant’s land in partnership with Priory. In April 2000 Mr Elkins ceased working for Taylor Woodrow and commenced working for La Sande as a consultant.
140. Mr Elkins wrote that he had been asked by Brian Smith to provide a précis of the situation regarding the planning consent. He stated that in early 1997 it was considered that although works had been carried out they were not considered sufficient to be material steps as required by s.56, and that some conditions which should have been satisfied prior to the start of the works had not been fully satisfied. But he referred to recent case law on s.56 which may put a different interpretation upon the works that had been done. La Sande instructed their planning consultants, RPS Chapman Warren, to investigate the matter and they were proposing to seek counsel’s opinion.
141. On 20th April 2001 RPS Chapman Warren wrote to Mr Elkins. On the question whether the conditions had been satisfied, they raised only two queries, namely whether conditions (xii) and (xiii) had been satisfied. On the s.56 point they referred to the recent case of Riordan v Secretary of State for the Environment ([2000] JPL 594 decided on 2nd December 1999). They also raised the question whether the fact that Mr Petch’s car showroom had been built on part of the site in the meantime might satisfy s.56. In Riordan David Vaughan QC sitting as a Deputy High Court Judge had considered a number of cases decided in 1997 and subsequently, and decided that in order to satisfy s.56 an objective test was to be applied, and it was not necessary that there should have been any subjective intention to complete the works.
142. On
143. In May 2001 RPS Chapman Warren prepared a very detailed document for counsel to advise as to whether the 1991 planning permission was still extant, and in particular whether the conditions of the outline approval had been complied with (or if not whether that mattered), whether there was a material start, and whether the implementation of the car showroom had kept the planning permission alive.
144. On
145. On
146. On
147. The point made in relation to the statement is twofold. Mr Hepker relied upon it in support of his contentions in the Declaration Proceedings, as appears from the judgment of Mitting J. And in the light of that judgment, and of the fact that no scheme of landscaping was in fact submitted, it is the claimant’s case that the statement is a lie and that it covered up the true situation. It is said that this is relevant both to Mr Lavender’s credibility, and to the issue of limitation.
148. For his part Mr Lavender said that he felt intimidated by the threat of professional negligence proceedings that was then made to him, that he understood that Mr Hepker wanted a statement for the purpose of any legal case with Darlington and for his dealings with La Sande, but that at the same time he was not prepared to lie and state that applications to satisfy the conditions precedent had been obtained when they had not been. He stated that he tried to find a form of words which might have been of some assistance to Mr Hepker, but not at the expense of the truth. He recognised that the statement of 27th July 2001 was incomplete in that it did not state expressly that there remained outstanding conditions precedent, but he said that to his mind the statement was not incorrect, and he assumed that others would read it carefully and work out what it did not say. He believed when he wrote it that it was accurate so far as it went and that it was lawful.
149. The evidence is conflicting as to the meeting of 10th July 2001. For the claimant the evidence was given by
150. Mr Lavender stated that at the meeting Mr Hepker wanted him to state that the conditions precedent had been fulfilled, and he simply responded by saying that he had done all that he had been asked. He said that his response was clearly not what Mr Hepker had wanted him to say, and he was threatened with the present proceedings.
151. On 5th November 2001
152. On
153. On
154. On 24th April 2002
155. On 15th May 2002 the claimant’s then planning consultant, David Collins FRICS, expressed the view that it was not difficult to arrive at a value for the site at £20m, if the planning permission was still valid. Much now turned on the question whether it was valid. I was informed that on 10th June 2002 Standard Life proposed a purchase of the site, conditional on confirmation of the planning consent of 1991, at a price of about £18m.
156. In June 2002 Mr Hepker attended a meeting with
157.
158. On 27th August 2002, following a further meeting with Darlington,
159. In September 2002, following a further meeting with the claimant,
160. In October 2002
161. On 28th November 2002 these proceedings were commenced.
162. On 12th January 2004
“2.1 The purpose of the Agreement is to provide HE with a success fee in return for his using his best endeavours to assist [the claimant] with the Declaration Proceedings and the Negligence Proceedings.
2.2 The success fee shall be payable if either (contingency A) there is a Consent Date [defined as the date on which there is a binding declaration or acknowledgement by Darlington that the planning permission is valid] or (contingency B) there is no Consent Date but [the claimant] succeeds in the Negligence Proceedings in being awarded and actually receiving damages in excess of £1,250,000…
2.4 The amount of the success fee in respect of contingency A shall be 4% of the Receipts if there is a Consent Date on or before 15th February 2004, 3.5% if there is a Consent Date on or before 31st March 2004; 3% if there is a Consent Date on or before 15th May 2004, and 2.5% if there is a Consent Date thereafter.
2.5 The amount of the success fee in respect of contingency B shall be 2.5% of the damages received by [the claimant] provided that the amount of the damages received is in excess of £1,250,000.
2.6 … it is acknowledged that there is no contractual arrangement or agreement between [the claimant] or any other Lingfield company and La Sande (Holdings) Ltd or Mr John Lutton.
2.7 All moneys paid by La Sande (Holdings) Ltd to Lester Aldridge in respect of legal fees regarding the Declaration Proceedings incurred at any time after 28th February 2002 shall be reimbursed to HE by [the claimant] on the signing of this agreement. HE hereby agrees to procure that no further payments of legal fees shall be made to Lester Aldridge unless and until the bills rendered by Lester Aldridge to La Sande (Holdings) Ltd have been scrutinised by both HE and [the claimant] using their best endeavours to reduce the amount payable to Lester Aldridge to the lowest amount which is reasonably justifiable. Provided that this is done and the amount to be paid to Lester Aldridge is agreed by HE and [the claimant], or imposed by a court of competent jurisdiction, such further payments of legal fees shall be borne by [the claimant]”.
163. On 10th December 2004 Mitting J handed down his judgment.
164. Again I have no hesitation in preferring the evidence of Mr Lavender to that of Mr Hepker and Mr Elkins, where there is a conflict. In fact there is little conflict on the important issues as to what was said at the meeting of 10th July 2001. Mr Lavender did feel intimidated by the threat of these proceedings, and with good reason. That is not to say that Mr Hepker or anyone else made any other threats to Mr Lavender. They did not.
165. During the proceedings Mr Evans-Tovey asked for a ruling that the evidence of Mr Elkins was inadmissible by reason of the agreement set out above. He referred to a number of authorities, including SPE International Ltd v Professional Preparation Contractors (UK) Ltd [2002] EWHC 881 (Ch). I stated that I would consider that matter in my judgment, after I had heard the evidence. In the event I do not need to make a ruling and will not do so. The effect of the agreement is to cast serious doubt upon the weight to be attached to the evidence of Mr Elkins. That is all that I need say in the circumstances of this case.
Limitation
166. In the light of the findings that I have made, no question of concealment on the part of Mr Lavender arises. So I do not need to consider the Limitation Act 1980 s.32, which the claimant invokes. Nor do I need to consider s.14A of that Act. Mr Hepker was aware from the memo dated 22nd November 1996 (which he saw before 5th December 1996) that
167. I shall deal briefly with the question whether damage had been suffered before 28th November 1996. In my judgment significant damage had been suffered before that date, and so the claim is time barred.
168. As noted above, the experts in land valuation agreed, and the parties accept, that the planning permission added value to the site, and the added value would have significantly reduced if not disappeared, once it was appreciated that the permission could not be saved, or was likely to be lost.
169. It follows that the question is not whether with great effort and good fortune a scheme of landscaping could have been submitted (or submitted and approved) by 14th December 1996. The question is whether by
170. In the event I find that the planning permission was not doomed to be lost until some time after 1996. Even on 14th December 1996 there were the possibilities that the s.73 application might be granted and, as Lord Woolf LJ contemplated in Whitley, that
171. I heard evidence from Mr Tweedale for the claimant and Mr Perry. I have no hesitation in preferring the evidence of Mr Perry that three to four weeks would be a reasonable period for the preparation and submission of a scheme. That is not to say that it could not have been done in less time, but I find that compressing the period to the days between 28th November and 14th December involved such risks of failure that it was unlikely that the submission would have been successfully made in time.
172.
173. It is sufficient that I say that Mr Perry’s evidence is carefully structured, with each step required listed and he gave a time he estimates was required. Moreover, Mr Perry practised in an area which gave him knowledge of
174. No evidence was called as to how long it would have taken for approval to be granted. While it was not necessary, following Whitley, that approval be given before the deadline if the planning permission were to have a chance of remaining extant, the value of the site would, in my judgment, have been affected if the scheme were submitted so late that there would be insufficient time for approval before the deadline. That was the position as I find it to have been.
Damages
175. The issue of damages does not arise, but again I shall state briefly the reasons for the conclusions that I would have reached.
176. The expert for the claimant was Mr John Irwin Frics of Storey Sons & Parker. He served a twelve page report. The expert for PLA was Mr Peter Smith FRICS of GVA Lamb & Edge. Experts reports are not to be evaluated on their length, but in this instance the report of Mr Smith does reflect much greater investigation into the issues than Mr Irwin’s. Two opinions had in the past been given on the site by Mr Irwin’s former partner, Mr Battle, who also unhappily died a short while ago. In his report Mr Irwin referred to the advice of Mr Battle given in 1990 and 1995, but he showed considerable reluctance to disclose the reports. They were eventually disclosed after tenacious applications by the solicitors for PLA. I was left with the impression that Mr Irwin’s approach to this aspect of the case did not give the weight to his duty to the court that is to be expected.
177. Mr Smith arrived at his valuations of the land as follows. For the valuation without planning permission for retail use he used the comparison method utilising land values for business/industrial use because evidence exists of land transactions in the nearby vicinity. For a theoretical valuation of the retail park, he used the residual method as a scheme had been drawn up with relevant information, and he relied upon comparable evidence for rental values and yields. To arrive at the valuation for the land with the 1991 planning permission, he had regard to the value without planning permission for industrial use, and uplifted it to allow for the speculative value which would have been associated wit the planning permission and the theoretical value and he discounted it significantly because of factors present in December 1990.
178. Although technically the land was farmland in 1996, Mr Smith did not value it as such because at the time it was designated in the local plan as being for employment uses, and had an application been made in December 1996 for permission for employment use, he had no doubt that it would have been granted.
179. The comparisons that he made were of small areas of land which were the subject of transactions in September 1995 and December 1998. He considered that it would have been most unlikely that a developer would have purchased the whole site of 24 acres in one tranche, but given that he was required to value the whole site, he considered it right to apply a reduction of 15% to take account of the size. So his valuation of £700,000 for business use purposes was arrived at by taking 24 acres at £35,000 per acre less a discount of 15%.
180. Mr Irwin also took the rate for industrial land at £35,000 per acre, and considered that it had to be discounted. His conclusion was that an investor or property speculator would have taken the view that the road would eventually be constructed, and
“would have been prepared to offer a sum of around £240,000 for the 24 acre site with the prospect of perhaps giving some clawback or overage payment if the access was secured within a time limit of 10 or 15 years. The price would reflect an uplift from agricultural land values rather than a reduction from industrial land values”.
181. Mr Irwin did not mention agricultural land values in his report, introducing a figure of £3,000 per acre in his oral evidence. This reasoning in the report is sparse. There is no indication of what the value would have been, in his opinion, without a provision for clawback or overage payment, nor of the value of the clawback or overage payment. So to that extent it is not a valuation of the site at all, but only one step towards a valuation.
182. In the joint statement
183. I prefer the opinion of
Conclusion
184. The claim fails because