Back
Legal

Sisk & Son Ltd v Carmel Building Services Ltd (in administration)

Building contract – Interim payment – Arbitration – Claimant contractor entering into sub-contract with defendant incorporating JCT Conditions of sub-contract – Defendant entering administration – Claimant terminating sub-contract – Defendant claiming sums due to it from claimant – Adjudicator making award in favour of defendant – Claimant appealing – Whether arbitrator erring in burden of proof – Whether arbitrator erring in rejecting claimant’s primary claim – Whether defendant being entitled to statutory interest – Appeal dismissed

The claimant contractor was engaged to construct a nine-storey reinforced concrete frame mixed-use building at 41-51 Bolsover Street, London for the creation of forty apartments, together with a new Outpatients Department for the Royal National Orthopaedic Hospital. By a sub-contract, the defendant company entered into an agreement with the claimant to carry out the supply and installation of mechanical and electrical services on the project. The contract expressly incorporated the JCT Conditions of Sub-Contract SBCSub/C2005 Rev 1 2007. Clause 7.7.4 of the conditions set out provisions in the event of the defendant’s employment being terminated. Clause 4.10.5 dealt with amounts due under interim payments. Clause 15.9 provided for the payment of interest of the claimant failed “properly to pay the amount, or any part of it, due to the sub-contractor … by the final date for its payment”. Payment of such interest was to be treated as a debt due to the defendant by the claimant.

The defendant submitted an application for interim payment to the claimant but entered administration and ceased work under the sub-contract. The claimant terminated the sub-contract pursuant to clause 7.5.1 of the JCT Conditions. The defendant subsequently gave notice of arbitration in respect of the sums due to it. The claimant’s position was that, on a proper operation of clause 7.7.4, no sum was due to the defendant. The defendant asked for statutory interest in accordance with the Debts Act (Interest) 1988. Having determined what was due to the claimant under clause 7.7.4 by way of set-off, the arbitrator awarded the defendant £975,965.48, together with VAT, compensation for late payment (in the sum of £100) and interest on the late payment in the sum of £359,329.10. He held that clause 15.9 provided an optional regime for the payment of interest which was not an adequate remedy as defined by the Late Payment of Commercial Debts (Interest) Act 1998, and so had to be declared void. Accordingly, there was no contractual remedy for late payment and the provisions of the 1998 Act were implemented.

Start your free trial today

Your trusted daily source of commercial real estate news and analysis. Register now for unlimited digital access throughout April.

Including:

  • Breaking news, interviews and market updates
  • Expert legal commentary, market trends and case law
  • In-depth reports and expert analysis

Up next…