Back
Legal

Walter Lilly & Co Ltd v Mackay and another

JUDGMENT
Mr Justice Akenhead:

1.    This litigation raises extensive disputes which have arisen on a substantial new building project at 3, Boltons Place, London SW5. The project commenced in about 2004 and it is common ground that, when the Contractor, Walter Lilly & Company Limited (“WLC”), was appointed as main contractor, design work was nowhere near completed. It was clear and became clearer that the employer, DMW Developments Ltd (“DMW”), had very high expectations. However, little if any design had been completed prior to the involvement of WLC. There were substantial delays, much of which initially at least were not the responsibility of WLC, and as time went on DMW fell out seriously with its Architect. It can certainly be seen with hindsight, and could probably have been foreseen, that the project was “a disaster waiting to happen”. This certainly has proved to be the case.
2.    The case raises a number of issues which may be of interest to the construction industry and specialist legal practitioners and these include global claims and concurrent delays. In one sense, this litigation is very old-fashioned because it has involved a full-blooded conflict between the parties in which there seems to have been little, no or belated room for compromise, although the quantum experts have gone some way to reducing what is in issue. There remain in effect hundreds of issues between the parties, hence the length of this judgment. Different approaches are adopted by each party on delay analysis. No quarter was given on any of the primary matters in issue. Some very personal criticisms and complaints have been made by each party about one or more of the other side’s witnesses. There have been over 32,000 pages of documentation put before the Court (albeit with a significant amount of duplication and irrelevant material), there have been 9 factual witnesses and 8 experts and the trial hearing has lasted 16 days. The expert bundles themselves run to 33 in number, totalling some 11,000 pages. It seems that the parties have expended between about £9m and £10m by way of costs, which is obviously disproportionate to what is in dispute.
3.    I propose to divide this judgement into a number of sections:
A. General Chronology.
B. Assessment of Witnesses.
C. The Contract.
D. The Proceedings and the Pleadings
E. Analysis of Major Causes of Delays and Major Defects.
F. Extension of Time.
G. Quantum Delay.
H. Other Defects.
I. Other Quantum.
In the General Chronology which follows, I will not set out in detail the history relating to the Light Wall, the ABW, the Courtyard Sliding Doors, the lift, the Barrisol Ceilings, the Stingray Doors, Leather in the Library, snagging or plaster defects which will be dealt with in the Analysis of Major Causes of Delays and Major Defects.
General Chronology
4.    No, 3 Boltons Place, owned and occupied by Mr and Mrs Mackay, is one of three adjacent houses of similar design. DMW was a purpose designed vehicle for the acquisition of the land at what is now Nos. 1, 2 and 3 Boltons Place and was formed by three people, Mr Mackay, Mr Daniel and Mr West. The three houses were known during construction as Units or Plots A, B and C, of which C was to be Mr and Mrs Mackay’s. The houses are of reinforced concrete construction on piled foundations and the external walls are brick, although the ground floors are rendered in a faux rusticated manner. There are five floors, with a basement containing a below garden swimming pool set across a narrow courtyard, a ground floor and three other floors. The third floor is located behind a mansard style slate clad roof. Whilst each house was built to a similar shell and core, the interiors were fitted out to suit the requirements of the individual owners.
5.    The basement at No.3 comprises on the west side a large habitable space, designated as the Library where the extensive bookcases are covered in stitched leather. The Library windows, which largely comprise a large sliding door, look out onto a courtyard with a water feature, on the other side of which behind a similar sliding door is the swimming pool, on the western side of which are glass screens behind which there are changing rooms, a lavatory and shower. The very substantial sliding doors which lead out from the swimming pool and the Library are known as the Courtyard Sliding Doors. The glass screens on the western side of the pool comprise and incorporate a lighting feature which allows a flow of changing coloured light from top and bottom to be diffused through the whole of the screen; this is known as the Light Wall. In the basement there is also a cinema and below the external area immediately outside the front door is a garage accessed by a car lift. The ceilings of the swimming pool and the cinema comprise what is known as Barrisol ceilings which essentially are a stretch light coloured fabric which conceals a substantial bank of lights which also change colour and are supposed to be diffused evenly through the ceiling downwards. There are also a wine cellar, guest toilet facilities, a kitchen, laundry and staff quarters. There is a secondary staircase to the ground floor. The ground floor comprises a large entry hall, to the west a large family room and to the east the drawing room in addition to which there are guest cloakrooms; the doors to these two rooms were known as the Stingray doors and were very substantial metal lookalike doors. The first floor contains the master bedroom suite, including bathroom and dressing rooms as well as two studies, referred to as His Study and Her Study. On the second floor there are two substantial bedrooms for each of the Mackays’ children, each having a bedroom with en-suite bathroom and a study. The third floor comprises a guest suite on the east side and a gymnasium on the west side. Rising up and down from the ground floor is a reasonably capacious circular staircase in the middle of which there is a lift which runs all the way up the house. Much of the flooring is of American Black Walnut (“ABW”); ABW was also used for much of the cupboard joinery as well as for the skirtings.
6.    Mr and Mrs Mackay assembled initially the following design and professional team:
Architect:            Barrett Lloyd Davis Associates (“BLDA”)
Interior Designer:    Initially Fox Linton and later Janine Stone Interior and Architectural Design (“JSI”)
Structural Engineer:    Cameron Taylor Bedford
Services Consultants:    Chapman Bathurst Partnership (“CBP”)
Lighting Consultants:    Equation Lighting (“Equation”)
Quantity Surveyor:     Gardiner & Theobald (“G&T”)
Project Manager:        Second London Wall (“SLW”)
Fit-out Manager:        Rider Levett Bucknall (“RLB”).
BLDA was re-placed as architect by Navigant Consulting in about March 2008, which was itself placed by a Mr Mulhearn in about March 2009. A firm called Malishev Wilson Engineers was retained in late 2004 by DMW or possibly BLDA on DMW’s behalf to design the lift shaft.
7.    Planning permission had been obtained in 1999 and was subject to a condition that work had to start within 5 years (by 15 June 2004). The first permission was for the demolition of the existing Earls Court telephone exchange which had stood on the site for many years and the second was for the construction of three dwelling houses with basements and attached garages with access from Boltons Place. There was therefore some pressure on all concerned to get the job started within that timescale.
8.    In early 2001 Mr Mackay became aware that BT was proposing to sell the site and he teamed up with two friends, Paul Daniel and Stephen West, to purchase the site for £13.2 million on the basis that each would have one of the three units, A, B and C, Unit C being for Mr and Mrs Mackay. In 2004 the three of them set up DMW as the corporate vehicle through which the development would be carried out. Initially, DMW used the original architects who had helped secure the planning permission. G&T were retained in 2003 as were SLW, CBP and BLDA. In mid-2004, the Mackays retained Fox Linton as the interior designers, in particular Anthony Bevacqua, known as “Bev”. It was only later, in February 2005 that the Mackays retained Equation as the lighting consultants. In 2006, RLB was retained to provide a range of quantity surveying, building survey and project management services to manage directly employed artists and tradesmen.
9.    Mr and Mrs Mackay wanted to create what they call their “dream home” for themselves and their two children. Mrs Mackay spent a very large amount of time in researching in particular the interior design and fit out. She collected images from magazines such as “House and Garden”. They decided on the overall concept which was to be “modern, stylish, with great attention to detail, luxurious with the highest quality of finish with smart, shiny dark glossy floors, luxurious bathrooms, beautiful lighting and elegant perfect finishes”, as Mrs Mackay said in her witness statement.
10.    Separate contractors having been engaged to carry out the demolition work to remove the telephone exchange building, four contractors, including WLC, were invited to tender for the main building works. WLC was to describe itself as having particular and extensive experience of working on high-quality residential and new build projects. On 26 March 2004, WLC submitted its tender in the sum of £15,476,970.99 for construction of all three plots. It referred to there being limited information and how difficult it was to conclude an actual programme; although the stated completion period was 78 weeks, WLC’s experience suggested 80 to 90 weeks, notwithstanding the enclosed programmes showing a 78 week period and some 23 work packages. The Executive Summary stated that it would provide “a dedicated specialist team, which has extensive experience of working on high-quality residential projects including new build” and that it had a “strong track record of working on schemes which require design input from the contractor as well as the ability to work with design teams.” There was a detailed breakdown of the preliminaries to be provided at a total cost of £1,438,500.62. There is no hint or suggestion at the time from DMW’s design team that this was an inadequate allowance. Indeed if anything it was somewhat higher than G&T had estimated.
11.    The tender was further negotiated and reductions totalling some £105,000 were negotiated, leaving a net quoted price of £15,372,962.83; this negotiation was thought necessary (as Mr Mackay confirmed in his witness statement) because WLC’s pricing of preliminary costs and profit overheads was slightly over the budget which G&T had set (this also being confirmed in a Project Meeting minute of 20 April 2004). On this basis, WLC’s tender was accepted in that amount; it had been confirmed that the overhead and profit percentage was set at 4.5%. The Date of Possession was to be 12 July 2004 and the Date for Completion was 23 January 2006. There were graded liquidated damages rates (£2,150 for each of the first seven days of culpable delay, £2,850 per the next 18 days, £4,300 to the next 44 days and £6,400 per day thereafter). The actual formal Memorandum of Agreement was signed on and dated 28 May 2004.
12.    A Sub-Contract Protocol (incorporated in the Contract) was drawn up 10 May 2004 which was to establish procedures by which sub-contractors were to be retained by WLC to prepare a proposed schedule and scope of trade tender packages, to identify an initial list of suitable tendering sub-contractors, prepare a pricing documents for all packages, to prepare with G&T quantities for the “key works packages”, prepare and issue tender enquiry documentation, to arrange and undertake a commercial and contractual appraisal of the preferred tender in conjunction with G&T and to request an instruction to enter into a subcontract order and following receipt of an instruction to place an order with the subcontractor identified in the instruction.
13.    There is no doubt that at this stage a very large number of design decisions had not been taken up by the Mackays and their professional team and the design, such as it was, was in many respects at best at an incipient stage. Apart from the preliminary cost items, all the actual building works were the subject matter of provisional sums and the Contract specification and drawings were largely outline with little or no detail. Over one year later on 19 August 2005, BLDA was to write to G&T saying that: “The distance between client aspirations and cost has never been so far apart”. This highlighted what was to be a continuing problem, namely considerable delays in securing design decisions so that WLC and its sub-contractors could progress the Works with reasonable expedition.
14.    The first major element of the works to be instructed was the piling and it was made clear to WLC that it was to be responsible for the design. This was confirmed at a project meeting on 4 May 2004. WLC negotiated with several piling contractors and on 28 June 2004 recommended that the piling package was awarded to Stent Foundations. BLDA issued an instruction (AI001) on 30 June 2004 for WLC to issue a letter of intent to Stent authorising limited works up to a value of £10,000, which in effect WLC did a few days later. The reason for the Architect’s reticence was that the demolition works being carried out by H Smith Engineers Ltd were delayed. Although it was not until 17 August 2004 that BLDA instructed WLC to enter into a formal sub-contract with Stent Foundations (in the sum of £736,976.06 by AI007)), a further instruction the following day deferred the start of the works until 31 August 2004 due to demolition delays. Indeed, WLC was itself instructed by the Architect (AI008) to carry out certain further demolition work of underground concrete and brick work. The works started on 30 August 2004. By 10 September 2004, WLC was reporting that the contract was in delay by some four months. Some delay and disruption was caused by the presence on site of trees subject to tree preservation orders and over the following few months permission was secured for the felling of such trees.
15.    On 22 July 2004, WLC produced its procurement programme which was at least partly based on their tender programme which in relation to each package indicated dates by which WLC wished to receive “design tender information”.
16.    Over the following months of 2004, piling work proceeded and WLC also invited tenders from various groups of sub-contractors for the mechanical and air conditioning services and the brickwork and blockwork. On 18 November 2004 BLDA instructed WLC to enter into a contract with Keltbray Ltd to carry out superstructure concrete works. By early 2005, WLC had given notifications under Clause 25 of delays caused by tree removal problems, additional piling works and the late instruction of Keltbray.
17.    Over the latter part of 2004, there had been discussions about the need for the single contract relating to all three houses to be split out into three separate contracts. For instance in late July 2004, G&T communicated with WLC about splitting the overall contract sum into three separate sums. On 9 August 2004, Mr Corless of WLC provided a breakdown of the preliminaries for each house. There was concern on the part of WLC that the three houses were constructed as three legally separate contracts because the level of preliminaries could only be maintained provided that all works were and continued to be run in tandem. This led to a Deed of Variation dated 23 December 2004 whereby WLC was engaged by DMW to carry out building works for each of the three units effectively by way of three separate contracts. For Unit C, the Contract Sum was £5,281,974 with the same Possession and Completion Dates as before and the same contractual conditions.
18.    On 23 December 2004, BLDA issued an instruction (AI032) to WLC to enter into a contract with Doppler Lifts for the supply, installation and maintenance for the car and passenger lifts. In consequence of this, WLC did place a contract with Doppler, the terms of which required it to pay a substantial deposit to Doppler. This gives rise to one of the final account claims.
19.    At this time, the formal agreement between DMW and BLDA was entered into pursuant to which BLDA was to be the “Design Leader”, “Lead Consultant” and Contract Administrator.
20.    By the end of 2004, apart from the design of the piling and principal structural and external envelope works, the design for much of the remainder of the work was substantially incomplete. This was acknowledged in part by the Architect who confirmed at a meeting on the 16 November 2004 that the “Clients’ design decision deadlines [on] the current programme is [sic] are problematic”. There is little or no evidence that the Mackays were ever clearly advised by their professional team of the critical need for the design to be decided upon sooner rather than later. Major aspects of the interior design were not resolved until 2006, well after the original contractual date for completion. In this context, and given that it was open to DMW to designate within the confines of the contract that WLC design substantial elements of the Works, WLC wrote on several occasions in 2005 to BLDA seeking instructions and clarification as to what if anything else (other than the piling) it was to design. For instance on 21 March 2005, WLC wrote to BLDA in the following terms:
“Within the preliminaries section A13-Description of Work, of the contract documents, there is a list of trades that ‘may be designed by the Contractor’. In our Tender submission we excluded any Professional Indemnity Insurance or any designer/coordinator input associated with Contractor Designed works.
We have published our understanding of the current CDP requirements and have reported our preference that Employer’s Requirements be developed for inclusion in tender packages…
We therefore enclose herewith our updated list of the current state of CDP packages on this project. We would be grateful if you could check the status and advise us whether any further packages need to be added. We would also be grateful if you could indicate when Employers Requirements for the noted trades/ packages will be available.
This will help us to identify the design implications and responsibilities, in order that we can include a sufficient level of PI cover and also assess the required level of design and coordination the mobilisation at the appropriate stage of the procurement process. Clearly, the cost of the PI cover and any resources required to facilitate design management and coordination will need to be assessed and incorporated within the comparisons to each relevant package. It is therefore important that an exhaustive list of all Contractor Designed Works is identified at the earliest opportunity in order that PQS can be notified of any additional costs”.
The attached list identified the packages then envisaged with many of the items indicating no design responsibility but some such as the courtyard sliding doors to be subject to “full design – Subject to [Sub-Contract]”. This was followed by similar letters dated 13 May 2005 and 10 August 2005 which also elicited no substantive response. There is no evidence that BLDA ever raised this important issue with their clients. That DMW’s Design Team were aware of the need to formalise arrangements about who was to be responsible for design is clear from such correspondence as is available to the Court relating to the piling in relation to which Mr Elliott of G&T e-mailed Mr McMorrow of WLC on 11 November 2004 confirming that “a set of documents can be gathered to pass back to the Clients’ solicitors” going on to say that “this will be necessary for all of those packages so that design responsibility is passed down to Water Lilly”.
21.    Notifications of delay under Clause 25 of the Contract Conditions continued to be made by WLC. There were such notifications on 5 January 2005 (Keltbray late instructions), 12 January 2005 (piling changes), 4 February 2005 (late instructions for pre-cast concrete features work, eventually leading to Sterling Services being retained) and 23 February 2005 (additional drainage works and late drainage instructions). It was only on 18 February 2005 (AI045C) that BLDA instructed WLC to enter into a contract with Bansal Building for the fair face brick and block work, following a series of cost reduction exercises.
22.    There were regular meetings between WLC and the professional team. These included procurement meetings. General specifications for General Glazing (10 May 2005), Purpose Made Joinery (12 May 2005), Structural Glass Assemblies (31 May 2005) and Glazed Lift Enclosure (2 June 2005) were issued to WLC.  In May 2005, WLC invited a company called Firmans to provide and fix the two Courtyard Sliding doors, an order following in September 2005. However, this had been preceded by extensive contact directly between BLDA and Firmans (as evidenced by example by a letter dated 7 January 2005 from BLDA to Firman discussing various design options and decisions, to which WLC was not a party. Firman indeed provided quotations direct to BLDA which continued to liaise with Firman about design as recorded in procurement meetings in April and May 2005). On 23 June 2005, Adams Joinery Ltd quoted for the supply and installation of joinery in a number of rooms (five bathrooms, two dressing rooms and two WCs); the scope of their work was to be extended substantially by later quotations and re-quotations. BLDA did not instruct WLC to place an order for this work until 3 October 2005 (AI166C). This led to an extension of time notification by WLC on 7 October 2005.
23.    WLC wrote to BLDA on 21 July 2005 to the effect that it was incumbent on the Architect in issuing instructions for provisional sums, usually on the basis of a tender process involving sub-contractors and suppliers, to identify the likely impact of such instructions on the contractual Completion Date and if appropriate to adjust that Completion Date and to award any related loss and expense. A schedule was attached which showed agreed changes to the original programme occasioned by provisional sum instructions. It also placed on record “that the flow of information continues to lag behind dates agreed in both the Procurement and Information Required Schedules” and emphasised that it was “critical to adjust the programme in a timely manner to ensure that the employer is aware of the current forecast completion date as well as any adjustments to the Contract Arising from the architect’s instructions…”. This elicited no response.
24.    By August 2005 there were numerous items of information and instruction awaited from BLDA. This was noted at the procurement meetings as well as in correspondence. For instance on 2 and 16 August 2005, numerous work packages were listed that should have been secured and in respect of which tender information was still awaited, all of which was to be actioned by BLDA. It is not wholly clear why BLDA was so far behind with the provision of information and instructions but there is no suggestion that it was in any way the fault or responsibility of WLC. One of the reasons however undoubtedly was that the clients’ wishes were not capable of being accommodated within the budget which they had set and a substantial amount of work had to be done to try to accommodate both. Certainly there were substantial tensions between Mr Mackay and the professional team; for instance he wrote to G&T on 16 November 2005 complaining that they were:
“…so wrong in terms of your numbers, budgets and procurements and I think you owe me an answer to my question and to least have the good grace to start doing something about this other than trying to make me look like I’m an idiot. That I may be but only in the context of employing you to look after the costs plans on the job”.
These tensions highlighted the fact that many tenders had come in over budget, as reported in a number of meetings in 2004 and 2005.
25.    By September 2005, the Mackays and various members of the professional team had begun to research and investigate the efficacy of the Light Wall. For instance in May 2005, Equation had produced for Mr Mackay some sketch drawings representing the first outline design and in June 2005 he attended a meeting with Bev at Equation’s offices to discuss the Light Wall at which he was shown fibre-optic lights being applied to the edge of a plastic sheet that he was told was called Prismex. On 27 September 2005, Firman was invited to tender for the other elements of the glass cubicles for the swimming pool area. It was only in November 2005 that Mr Mackay saw a small mock-up of the Light Wall and instructed the team to proceed. It was only on 2 February 2006 that BLDA instructed WLC to place an order with Firman for the Light Wall, although WLC’s tender report of 24 November 2005 had said that a 23 week period was required by Firman from the sub-contract being let to it. It was also over this period that there were discussions (not involving WLC) about the Barrisol ceilings and the lighting arrangement above them, albeit that in early October 2005 WLC did receive an estimate for the supply and installation of the Barrisol sheeting in the swimming pool area.
26.    It was also in 2005 that Mr and Mrs Mackay at least provisionally selected the American Black Walnut wood to form the flooring and veneer for much of the joinery in Unit C, in particular in relation to the cupboards and the skirtings. By February 2006, the Mackays had chosen a Danish Oil finish for the ABW. Further visits were being arranged in March 2006 however to organise “another veneer selection process” as referred to in an e-mail dated 7 March 2006 from Adams Joinery. This occurred when Mrs Mackay visited the workshop of a company called Reliance Veneers, who were to be the suppliers to Adams Joinery which was to be the sub-contractor; Mr Hawks of Adams Joinery attended but WLC did not. This meeting was not to select ABW as such, because that decision had already been made, but to pick an actual piece of ABW from which the veneer would be sliced.
27.    At the end of September 2005, delay of some 17 weeks was being reported. Notwithstanding this, SLW reported to Mr Mackay that there was goodwill on the part of WLC, albeit it acknowledged that there had been substantial delays caused by late and un-coordinated information from the design team which was “a direct consequence of placing a main contract with [WLC] to secure planning consent for the scheme in early 2004 and at the time with incomplete design information”.
28.    An issue had arisen between the parties as to where the risk lay in relation to delay attributable to the issuing of provisional sum instructions with WLC arguing that, as the provisional sums were undefined, all programme risk was with DMW; thus, if a sub-contractor whose engagement was instructed by way of a provisional sum instruction failed to finish within the time otherwise reasonably allocated by WLC to such work WLC was entitled to an extension for overall delay caused by this as the delay would have arisen simply as a result of compliance with the instruction in question. DMW’s lawyers advised it that this was wrong as did BLDA. SLW appear to have disagreed with this for reasons set out in its letter to Mr Mackay of 5 October 2005; their view was that the problems and delays on the job could be traced back to the letting of the Contract at a time when there was incomplete design information. It advised that the design must be frozen to prevent any further extensions of time. It explained that it was trying to manage the “dynamic process” of design, information provision and construction but it was “difficult”.
29.    On 8 and 28 November 2005, WLC submitted further extension of time notifications (electrical information and joinery). A total extension of time of over 19 weeks was indicated, with much of the later delay said to be attributable to the non-receipt of instructions for the commencement of joinery production by Adams Joinery.
30.    By late November 2005, it had begun to be clear that the Mackays wanted the bookshelves in the Library covered with leather with decorative stitching. The BLDA “Elemental Description Schedule” dated 16 November 2005 indicates that the finish and material would have to be confirmed. On 24 November 2005, WLC submitted revised loss and expense assessments in relation to a number of their earlier extension of time claims.
31.    By January 2006, the delays had worsened. On 6 January 2006, WLC reported in its Progress Report that an extension of time of 27 weeks and three days was requested, recording only that an extension of time of four weeks had been awarded. It was noted that the mechanical and electrical services subcontractor, Norstead, was significantly behind programme with the electrical works as a result of late and incomplete information from the design team whilst the procurement of finishing trades remained seriously behind programme. On 2 February 2006, BLDA issued the Plastering Specification, which was in 2007 to give rise to disputes about the required standards for plastering. On the same date, it also issued an instruction (AI 208C) to WLC in relation to the Light Wall in a sum just below £100,000. A whole series of further Architect’s instructions followed within a few days relating to additional and altered work for Adams Joinery. 
32.    By early January 2006, Mr Mackay was considering omitting a substantial amount of the finishing and external works from DMW’s contract with WLC. On 7 January 2006, BLDA sought instructions from him to that effect.
33.    Clearly tensions were rising within DMW. There was a dispute between Mr West and Mr Mackay about the costs of moving the electricity sub-station from Unit A to Unit C. Mr Mackay referred to Mrs West as “avaricious and jealous” and as needing a “f***ing good slapping”. The very clear inference from this and what had gone before is that Mr Mackay believed that he was spending far too much on the construction works and that he had been misled about likely costs. In an e-mail exchange on 28 February 2006, Mr Mackay said that the project “has turned into a fiasco where we all look like complete idiots unable to listen to or act on reason”. By 16 April 2006, Mr Mackay was telling his architect and quantity surveyor that “a lot of people are late on this project due to no fault of mine and…the costs are being passed on to me with no regard to my approval or interests”; G&T were appearing “to just act as a high-priced mail box in this whole affair” and their performance was “at best pitiful”.
34.    By 3 March 2006, WLC was reporting that, although 20 weeks extension of time had been awarded, over 27 weeks overall delay had occurred for which an extension of time should be granted. Delayed procurement of finishing trades issues, the late resolution of the sub-station issue, late changes and alterations to installed work, late details relating to the Light Wall and late finalisation of the veneer were highlighted as the more recent primary problems. In late March and early April 2006, further extension of time notifications were dispatched by WLC to BLDA relating to additional works for joinery and to problems relating to the moving of the sub-station and additional work relating to pre-cast concrete features. By late April 2006, a total extension of time of 33 weeks with costs was being requested. By June 2006, the parties were anticipating completion of the Works on 28 November 2006, with over 36 weeks reported delay. At a site meeting held on 8 June 2006, it was recognised by DMW’s Design Team “that coordinated design information remains to be given to [WLC] and significant numbers of queries generated by [WLC] remain to be answered…”. By the end of June 2006 WLC was reporting an extension of time of 36 weeks and 2 days, that Adams Joinery was running five weeks late due to late instructions and information and that they were awaiting instructions to proceed with the leather finishes, including to the Library. There had been a quote which included the leather but it was thought to be too costly and Adams was asked to quote for savings to be made.
35.    As is common ground, G&T produced regular cost reports. Their May 2006 report identified an increase in the budget of £300 per square foot to £570 per square foot. The cost had been estimated originally at just over £5.5 million but by May 2006 it was estimated at just above £9.375 million. The principal changes from the early days were listed with costings explaining various increases.
36.    BLDA wrote to DMW’s solicitors on 21 June 2006 identifying that 19 weeks and four days extension of time had been granted but that further extensions would probably be due.
37.    Some insight is given as to the perceptions on the DMW side in an attendance note of a meeting attended by its solicitors, Manches, on 29 June 2006:
“The view of [BLDA] was that the main causes of delay to date were late instructions and design information…the splitting of packages into a smaller packages, poor coordination of services, the lifts and the substation. [WLC] were also claiming time and money due to there being only one staircase, but two was included in the original specification, which resulted in delay and disruption to the works owing to congestion.
[BLDA] also said that another problem was that [WLC] would not take on any design liability and this was causing delay…The building contract was checked and it set out a number of packages that may be [Contractor Designed Portion] packages. CF [of BLDA] said that he thought a list of such packages had been agreed early on…JA said that no work had been procured as a CPD package. [BLDA] confirmed that the mechanical and electrical services were fully designed by Chapman Bathurst.
…It was also noted that [WLC] had not been acting aggressively in respect of their claim and that generally [WLC] are keen to avoid disputes; that was one of the reasons they were selected for this contract.”
The correspondence overall supports the general truth of these observations. Very few of the extension of time notifications were challenged by BLDA, albeit BLDA did occasionally do so (such as on 1 June 2006 in relation to ceiling details). At this stage, the causes of delay were primarily the late provision of instructions and information to WLC and poor coordination by DMW’s Design Team. There had been little or no complaint that WLC was responsible for any of the overall delay. Documentary evidence and indeed the evidence of WLC, which I accept, confirms that virtually no work (the piling package being an exception) had been procured by the Design Team as a Contractor Designed Portion package. What was not correct was the note that WLC was not prepared to take on any design liability. There had been a number of letters written by it unequivocally seeking clarification and instructions as to what design responsibility it should take on; those letters had been studiously ignored principally by BLDA and G&T for no obviously good reason other than they believed that the imposition of design responsibility on WLC carried with it an additional financial burden for DMW. It is clear that there was and continued to be serious ill feeling between DMW and the Design Team about the escalating costs of the project.
38.    On 21 July 2006, WLC submitted an extension of time notification in relation to the Stingray doors on the basis that the timing of architect’s instruction for it would mean that the doors could not be completed until 11 December 2006. WLC’s progress report of 24 July 2006 identified that 45 weeks and four days extension of time had been requested, although at this stage only 20 weeks extension had been granted. Delays associated with the Light Wall were noted as one of the current delaying factors. Within several weeks, a further extension of time of seven weeks was granted. On 22 August 2006, BLDA reported to Mr Mackay that WLC was predicting contract completion at mid-February 2007, this date being “generated by the late delivery of bespoke ironmongery, the long lead in time for some door finishes and testing and commissioning”. Following further extension of time notifications in July and August 2006, including one on 25 August 2006 relating to delays in relation to decisions on leather selection, WLC reported on 15 September 2006 that a total extension of 51 weeks was being requested with significant delays being recorded against pool areas generally, lifts, stairs, roof lights, doors and frames, courtyards generally and external works.
39.    The Barrisol ceilings in the pool and cinema areas began to emerge as a problem in September 2006 when BLDA reported to Mr Mackay that Barrisol would not start work until 50% of sums due to them were paid. The Architect’s instruction for this had been given on 24 August 2006 (AI347C), although the quotation to which the instruction relates was dated 7 October 2005. A problem arose in relation to Adams Joinery who required a 50% deposit before the placing of orders for the leather and fabric which had been apparently finally decided upon several weeks before.
40.    By late September 2006 the lift shaft had been installed and BLDA raised with WLC concerns about the overall quality of the lift shaft installation in a letter dated 28 September 2006 to WLC. A certain amount of remedial work was done to overcome at least a number of these concerns.
41.    By October 2006, Mr Mackay had become disillusioned with, principally, BLDA and G&T; cost had risen enormously and there was at least a year’s delay; he referred in an email dated 27 November 2006 to his Design Team to a doubling of the budget. He retained well known claims consultants, Knowles, by an agreement dated 19 October 2006 to provide nominally “contractual and adjudication advice”. This retainer was initially kept secret from BLDA and WLC, albeit that it was no longer secret by early 2007. Knowles’ personnel attended a site visit on 18 October 2006. It is clear at this time that Mr Daniel believed that the main person at Knowles, Mr Rainsberry, was “very aggressive and thinks we should go after contractor now…through attack rather than negotiation”; he liked his approach and said that “all contractors are dishonest so let’s nail the bastards!”. Mr Mackay evolved a strategy from about this time to pressurise the Design Team and WLC. Knowles was initially asked to carry out a critical path delay analysis for all three houses. One of the primary purposes of involving Knowles was or certainly became watching over BLDA and G&T and influencing them as to how they should do their jobs on this project. This was an aggressive move against them. One facet of this was that BLDA was disentitled from issuing instructions without the approval of DMW or Mr Mackay. Another primary purpose became the development of a strategy to ensure that no further extensions of time were granted to WLC and that financial constraints were imposed. This strategy began to develop at least from about early November 2006 when Messrs Mackay, West and Daniel met at a Client Meeting on 1 November 2006 and mutually agreed that a completion date should be established with no further extensions of time to be granted past this date and that liquidated damages were imposed on WLC thereafter. In the case of Mr Mackay, this involved an increasing determination that a large amount of work should be omitted from the Unit C Contract to be performed by artists, tradesmen and others directly retained by him or possibly DMW, with WLC being left with such remaining works in respect of which, he anticipated, WLC would be in culpable delay or other difficulties. The motive for this by inference was to land WLC with a substantial liquidated damages burden. RLB was appointed as the project manager to superintend the work to be done outside the construction contracts. It is also the case that Mr Mackay as from this time began to be highly critical of the quality of WLC’s work, for instance in relation to the plastering and the lift.
42.    By 10 November 2006, WLC was reporting that 35 weeks and two days extension of time had been granted but that a total extension of 51 weeks was being sought. Problems with delayed instructions from BLDA relating to the precise scope of external works had been experienced, WLC indicated by e-mail on 10 November 2006 that it would commence such works in good faith and raise a written confirmation of verbal instruction in respect thereof. Although WLC was hoping that the Unit C work could be completed by the end of February 2007, problems with the Light Wall continued throughout November and December 2006, which included breakages of glass due to inadequate structural strength as well as uneven light distribution (scalloping) within the Light Wall. Further extension of time notifications were issued by WLC, including one on 14 December 2006 relating to the Light Wall and another on 11 January 2007 relating to problems associated with the external works.
43.    By the end of 2006, although much of the procurement had been finalised, much of the finishing works were substantially incomplete. An example was that the extensive leather work in the Library in the basement had still not been finalised, either in terms of the type of leather or the stitching which was to be used. The Light Wall was undergoing substantial problems which were to continue throughout 2007 and into 2008. Both WLC and SLW believed that  the Light Wall would not be complete by the end of February 2007. By 19 January 2007, WLC was reporting that, although an extension of time of 47 weeks and 4 days (up to 2 February 2007) had just been granted by BLDA, various works including the Light Wall and the Leather in the Library along with a number of items of work which remained to be instructed remained to be completed. Subject to the items listed, WLC was reporting that works would be complete by the end of January 2007. An extension of 58 weeks was claimed. By 6 February 2007, WLC was reporting that final snagging to Unit C could commence as soon as possible, albeit with the Light Wall and Leather in the Library being still outstanding. At a client meeting on 26 January 2007 with BLDA and SLW, Mr Mackay accused BLDA of being complicit in the extensions of time granted on the basis that they masked BLDA’s delays in issuing information. It was said at this meeting that WLC was predicting that work would be completed by the end of January except for a number of items. There was talk about WLC providing a schedule of areas ready for snagging and it was resolved that the snagging process would be carried out by a senior architect and team from BLDA. On 29 January 2007, BLDA, clearly under pressure from its client, wrote no less than 15 letters to WLC. On 2 February 2007, BLDA issued instructions to WLC to omit almost all the hard landscaping in relation to Plot C, as well as various other works and items such as the supply of door ironmongery.
44.    On 2 February 2007, BLDA issued what turned out to be its last extension of time, extending time for Plot C until 16 February 2007; this final extension related to the delayed installation of the three gas supplies for each of the plots with work being finished by the statutory undertaker only on 17 January 2007.
45.    On 2 February 2007, BLDA certified Practical Completion in respect of Unit A.
46.    At a site meeting on 6 February 2007, WLC reported that everything which it had “programmed to be completed by the end of January is largely complete” although there were still items outstanding. BLDA and Mr Joyce of WLC had discussed snagging to Plot C and agreed that “it must commence as soon as possible”. Mr Joyce said that it would have to take place “elementally because there are unfinished and late items in most rooms”. The Leather in the Library was identified as a potential problem area because WLC and Adams Joinery were “waiting for confirmation on the leather stitching”; Adams Joinery had presented 10 samples of stitching and Bev (not in attendance) was expected to confirm a sample later that day. This was said to be “urgent as it affects installation of the Library joinery, the door and the large panels of the Lower Hall” with Mr Joyce stating that “none of the Library joinery can be fixed because it is dependent on the upper sections being covered in leather first and these are in abeyance until the leather stitching has been agreed”. Mr Mackay sent three pages of comments on these minutes, although he had not been in attendance; he said amongst other things that when he and his wife visited the site on 10 February 2007 “the house was a complete mess” and “nowhere near complete”; he identified that the “plasterwork in every area is defective for a job of this quality and “price”.”
47.    On 8 February 2007, Mr Joyce wrote to BLDA saying that WLC wished “to offer Plot C as being practically complete on 16th February and would request that we arrange an inspection for Monday 19th February…”. He wished to “undertake an elemental snagging process to expedite the completion process and confirmed that this will commence, in conjunction with you, in the week commencing 12th February 2007”.
48.    On 9 February 2007, Mr Mackay wrote an e-mail complaining that there was no point snagging because he felt that every room in the house contained defective plastering which as he saw it on walls was not flat and the corners and angles were not straight. He had complained about this to some extent also in late November 2006. This gave rise to an extensive exchange over the following few months about the extent to which, if at all, WLC was liable for this. This is addressed in the plastering section of this judgment.
49.    On 16 February 2007, WLC reported that a 60 week extension of time had been claimed for and that there continued to be significant delays in the pool areas generally, the lifts, doors and frames, library shelving and joinery, courtyards and external works. Mr Mackay e-mailed BLDA on the same day saying that he was not prepared to allow it to certify Practical Completion “if there are any patent defects or incomplete works outstanding”. Problems continued with the Light Wall and WLC was told to stop work on the pool screens pending further design development; this was recorded in a letter dated 19 February 2007 from WLC to BLDA and confirmed at a site meeting held on 20 February 2007. On 19 February 2007, Mr Joyce identified this problem as likely to impact on the completion date.
50.    On 18 February 2007, Mrs Mackay e-mailed BLDA with a long list of complaints, including the need for “ballet bars” in the gym, the quality of the finish in the children’s bathrooms being “a disgrace” and “the baths” being  “disproportionately small and narrow, seemingly without reason and OF PLASTIC!” The Site was said to be “a complete mess again” and another disaster was “the specially designed lift”.
51.    On 23 February 2007, BLDA wrote to WLC saying that they were preparing a schedule of outstanding items which would need completion before a Practical Completion certificate could be issued and that “other Works have not been completed by the Completion Date of 16th February 2007”. It sought various particulars previously requested to allow it to review previous decisions and other Relevant Events for the purposes of extensions of time. BLDA did produce a preliminary snagging list on that date.
52.    On 26 February 2007, WLC e-mailed BLDA to the effect that in relation to the leather work, primarily in the Library, Adams Joinery would need between 17 to 19 weeks from receipt of a 50% deposit to procure and install such work. Adams Joinery’s prices were provided. On the same date, Mr Mackay indicated that he intended to withhold liquidated damages in effect as from 16 February 2007. As at 28 February 2007, BLDA had certified that the works had a gross value of £8,542,457.
53.    In summary and by the end of February 2007, extensions of time had been granted up to 16 February 2007. Whilst large parts of the Works were substantially completed, the main relevant areas of work which remained to be completed were the Light Wall in the swimming pool area, the Barrisol ceilings and the lighting arrangements above them, the Library shelving (primarily concerned with the associated leather work), the courtyard works, snagging for final handover, remedial works to plastering and resolution of outstanding complaints in relation to the lift. These will be addressed in detail separately hereafter.
54.    From late February 2007, Mr and Mrs Mackay and the Design Team instituted what became known as “client walk around” meetings, usually but not always attended by WLC representatives. Prior to this time, liaison between the Design Team and the Mackays was much more on an ad hoc basis.
55.    That Knowles was playing an active and determinative role on behalf of Mr Mackay is clear from a letter which it wrote to WLC on 7 March 2007 making it clear that DMW would withhold some £550,000 in relation to what was said to be defective work; this primarily related to allegedly defective plaster, defective lift shaft, defective ceiling and the Light Wall. It is unclear what, if any, analysis Knowles had undertaken in relation to responsibility for these alleged defects. The involvement of Knowles caused some administrative confusion and in consequence WLC liaised with BLDA on Knowles’s letter (for instance on 15 March 2007) but also delivered a detailed riposte to it on 30 March 2007. Knowles was to write direct to WLC on a number of occasions, for instance on 29 March 2007 again in relation to alleged defects.  The introduction of Knowles was certainly to raise the temperature and did little to engender any feelings of trust and co-operation between employer and contractor. On 7 March 2007 also BLDA sent a list of what was said to be unacceptable areas of plaster throughout the building based on a “preliminary spot survey of walls”.
56.    There still remained doubt as to whether the leather work in the Library was or was not going to be omitted and Mr McMorrow of WLC e-mailed Mr Cane of G&T on 7 March 2007 asking whether the work was “to be in contract or out of contract”, emphasising that it would take until July for this work to be completed. This e-mail was passed onto Mr Mackay who e-mailed back later that evening saying that the work was “in the contract – you’re all very late – so I would get on with it if I were you!!!!! Be advised everything stays in the contract where WL are late”. This highlights part of what Mr Mackay’s strategy was becoming: it included the desire not to omit from the scope of WLC’s work all those items of work which Mr Mackay, rightly or wrongly, regarded as the fault, risk or responsibility of WLC; the advantage, doubtless as he saw it, was that he would be able to extract the substantial liquidated damages agreed upon within the Contract. In mid-March 2007, Mr Mackay seriously considered that in the light of the reported defects on the lift and lift shaft a new lift shaft should be put in. WLC was on 20 March 2007 to estimate that this would take between six and nine months. He was however being told by BLDA (for instance at a meeting held on 7 March 2007) that the plastering was generally in accordance with the specification.
57.    On or after 16 March 2007, by memo (wrongly dated 14 February 2007), BLDA reported on various “defects” in the lift which included suggested problems with the verticality, alignment, distortion of glazing, sealant, scratches and other defects. Throughout March 2007, Adams Joinery was applying the agreed type of oil (Danish Oil) to the joinery, such as cupboards and skirtings, starting at the third floor and moving down. Some of the lift defects were being addressed by WLC and its sub-contractor in March 2007, including the mastic and the scratches to the glass.
58.    At a meeting held on 14 March 2007, Mr Lloyd Davis of BLDA expressed the view that he had properly examined the plasterwork using a straight edge. In broad terms, the dispute between the parties relating to the plasterwork was one of degree, with WLC accepting that there were some areas of plaster which were out of specification and Mr Mackay saying that virtually all the plasterwork was defective; the argument revolved around what the contractual specification called for. The Federation of Plastering and Drywall Contractors was called in and reported in the third week of March that the standard achieved was “of a commercially acceptable standard”. In the result extensive remedial works were done over the next two or three months which satisfied WLC and BLDA but not Mr Mackay.
59.    For reasons which are unclear, DMW withheld payments due to BLDA and in consequence throughout most of March 2007 BLDA largely suspended its work on the project. It was only in late March 2007 that Mr Mackay procured payment to BLDA with the result that shortly thereafter BLDA did resume operations. By early April 2007, DMW was retaining over half a million pounds for alleged defects and delays. This withholding was initiated by Knowles.
60.    In April 2007 WLC submitted a detailed request for extension of time in relation to variations and late receipt of instructions in relation to external works. This suggested that there had been and would be an overall delay of some 71 weeks and that the earliest contract completion date in consequence would be 20 July 2007. Also on 18 April 2007, WLC submitted to BLDA a further extension of time notification relating to the Light Wall which continued to give rise to problems including at this time removal of the glass units from site for further work on them to be done at the factory.
61.    It was in the latter half of April 2007, as protective coverings began to be removed, that a problem was beginning to be perceived to exist in the ABW. It was referred to at a walk around meeting on 23 April 2007. Problems with the lift were being addressed by this stage with both glazed panels having been replaced and scratches having been polished out. The leather for the Library remained unresolved and there were technical difficulties identified in this achieving a finish and look which the Mackays wanted. The Stingray doors remained unresolved and no order had yet been placed for the door panels and the ironmongery for the doors, to be supplied by DMW, had not yet been supplied.
62.    The position in relation to the lift was that, whilst there were a variety of items which remained in dispute, WLC remedied many of the other things complained about. Notwithstanding this, DMW retained over £130,000 in relation to the lift. 
63.    From about May 2007, if not earlier, the artists and tradesmen directly employed by Mr and Mrs Mackay began to come to site. While there is no evidence that this caused particular problems in that year, by 2008 there were substantial numbers of such people at the site.
64.    The problems associated with leather and stitching approval and selection were not resolved until towards the end of May 2007 and Adams Joinery’s programme from approval would bring about completion in early September 2007. Problems were also emerging in the swimming pool and cinema ceiling areas to be covered by the Barrisol fabric; what was feared by Equation was that the lighting would not be sufficiently diffused. These problems were referred to in e-mails and, for instance, at the client walk around meeting of 6 June 2007. At that meeting Mr Mackay reported that the complaint about the verticality of the lift shaft was effectively unfounded because it was as the minutes said, “found to be within tolerance”.
65.    The main problem with the ABW began to emerge in late June 2007 when Mrs Mackay recorded in an e-mail to BLDA on 25 June 2007 that “walnut veneer cupboards in my study…have gone very yellow toned over the last few weeks”. To this, Ms Hammond BLDA replied on the same day that the “veneer will change in colour as it ages and is exposed to light.” Staining was suggested and she suggested that Mrs Mackay should “see the colour change in the hardwood in my parents’ house thanks to the Australian sun!” Tensions were rising with Mrs Mackay replying that she was not “particularly interested in your parents’ experience” and complaining that it was for the clients to spot problems.
66.    At the walk around meetings in July 2007 attended by the clients, BLDA, WLC, Bev and Equation, problems with the Light Wall, the Barrisol ceilings (and the related lighting) the lift and the ABW were highlighted. The Mackays complained that they had not been warned that the colour of walnut would change in daylight. There was a debate at around this time between Knowles and WLC about the need for programmes. These had been provided over the first 30 months of the project and Knowles had complained about the absence of programmes. WLC wrote on 5 July 2007 saying that the circumstances were such that it was impossible properly to programme the works and forecast the completion of the works; the letter suggested that there were still significant outstanding information and instructions and that the activities and progress of directly employed artists and tradesmen was making it difficult to progress and complete. The debate continued in a somewhat abortive fashion.
67.    By this time the relationship between Mr Mackay and BLDA was close to breaking point with Mr Mackay blaming his architects for defective designs, acting unprofessionally, blaming the client for “everything” and delay. Complaints were made that minutes prepared by BLDA were a work of “fiction” and that their behaviour in relation to issues and defects was “nothing short of scandalous”. Knowles wrote on 23 July 2007 on instructions from Mr Mackay to BLDA instructing them not to issue instructions to WLC without Knowles’ “written consent to the issue of each and every Instruction”. Mr Mackay does not appear to have been advised that this was not justified under the construction contract and that, if implemented, could well result in yet further delays in the issue of instructions and information to WLC; this was copied to WLC who wrote on 26 July 2007 to Knowles complaining that this was not only invalid but also a repudiatory breach by DMW; WLC complained that “the reality of the situation is that the Architect has ceased to be an effective Architect in this regard and has been replaced by Knowles in all but name”. By the end of July 2007 Mr Mackay had imposed a design freeze in relation to the work in the bathrooms. This reflected the fact that BLDA was at the very least severely constrained not only by the increasingly personal and hostile criticism offered but also by the close involvement of Knowles in the running of this project.
68.    By this stage an adjudication had been commenced by WLC against DMW in relation to the sum of about £200,000 being withheld from certificates for the lift, some finishes and the Light Wall. Knowles was retained in that context by Mr Mackay and WLC had brought in its own claim consultants, Brewer. The adjudicator issued his decision on 30 July 2007 finding that, although there were some defects in the lift, only £30,000 was a reasonable withholding (as opposed to the £148,000 actually retained), that there was no justification for deducting anything in relation to the Light Wall and that only £5,000 could be withheld in respect of the finishes. It could justly be said that WLC was the substantial “winner”. However, the adjudication in so far as it related to the lift led to a negotiation between WLC and DMW whereby WLC undertook to carry out an over-cladding solution in effect to cover up elements which were not acceptable to the Mackays. This resulted in a proposal made by WLC on 13 September 2007 whereby WLC offered to carry out work and waive any right for extension or delay related costs attributable to over-cladding work. This was accepted by DMW and the work was primarily done in October 2007. 
69.    So far as ABW was concerned, in August 2007 Mr Mackay was planning to withhold money from the next payment, in effect blaming WLC for what was said in an e-mail dated 10 August 2007 from RLB to BLDA to be “an unacceptable level of variation between the flooring and finished joinery” and “the overall colour of the joinery is not the matt, dark finish expected and a rather orange/ginger tint”. As is clear from its reply, BLDA did not consider that WLC was to blame as the colour change was inevitable and mostly attributable to the use of an oil rather than a lacquer finish. In early September BLDA instructed WLC to stain a door in the guest bedroom to see if the Mackays would accept it. The story relating to the ABW continued through various meetings in September and October 2007 and there is no issue that WLC and Adams Joinery stained virtually all the  veneered ABW throughout the building; this caused great consternation with the Mackays. However, WLC took the stance that it had done what the Mackays had asked and notwithstanding their complaints and concerns it was not prepared to replace the veneered wood or re-stain it or otherwise treat it again.
70.    The leather work to the Library started in the third week in August 2007 and was to run over the following few weeks. There were continuing problems mostly with the lighting above the Barrisol ceilings, with Architect’s Instructions being issued in July and August and into October 2007 making alterations to the lighting and lighting patterns.
71.    By mid September 2007, the relationship between Mr Mackay and BLDA got even worse. Mr Mackay accusing them of “working full-time for” WLC, dissembling and being “truly a disgrace to your profession” (in an e-mail dated 13 September 2007). On 19 September 2007, he accused Mr Davis of BLDA of being “the most unprofessional person” he had met, that he was a charlatan and liar and that his head was “so far on the chopping block that it is holding on by a thread”. Part of these complaints related to minutes or notes of meetings prepared by BLDA which Mr Mackay believed were inaccurate, either positively or by way of omission. He was therefore particularly alive to those concerns. These types of complaint continued over the following few months. At a walk around meeting on 31 October 2007, Mr Mackay referred to Mr Davis as a “f***ing Pussy” and said that he “wakes up in the morning wanting to kill him”. At a similar meeting a week later he called Mr Davis to his face a “f*****g little twat” and said that “when this is finished (the building) I am not going to rest until I have taken you out and I have got the money to be able to do it”. In an e-mail dated 19 November 2007 Mr Mackay wrote to Mr Davis saying: “…you lie, you cheat, you cut corners, you dissemble – frankly you would try the patience of God…You have wrecked what should have been an amazing experience by your conduct – we are nearly at the stage where I can sue you and frankly I can’t wait!!!” During a conversation with Mr Davis on 18 December 2007, Mr Mackay said to him that he was “a joke”, his “e-mails are full of lies” and that he was going to “take you out. When your PI cover is used up I’m going to go for you individually. I have a QC just waiting to go. I spent £750,000 on Knowles…” There were constant references to BLDA in general and Mr Davis in particular representing the contractor’s interests over his, for instance in an e-mail dated 10 November 2007.
72.    By the end of September 2007, the “strategy” to deal with the project was being honed by Knowles, undoubtedly with the knowledge and approval of amongst others Mr Mackay. Knowles wrote to DMW on 27 September 2007 in relation to Unit C:
“We would like to create a situation whereby direct work is not delaying [Practical Completion] – i.e. PC is solely delayed by WL’s works. WL works can be omitted to achieve this if possible.”
The problems relating to the ABW and the Light Wall were identified as being attributable to design breaches by BLDA and the problems with the Barrisol ceiling as being caused by design breaches by Equation. Knowles advised that it would be “prudent to dismiss BLDA on or about 26 October”. Part of the strategy included Mr Mackay sending a Knowles drafted letter instructing G&T to issue no further recommendations for Interim Certificates, as was confirmed by G&T in its letter to WLC, albeit copied to a number of other parties. G&T clearly felt very embarrassed and apologised to WLC as recorded in a WLC e-mail of 2 October 2007.  This course of action was persisted in notwithstanding BLDA’s correct advice for instance on 19 October 2007 to Mr Mackay that it was inappropriate and a breach of contract. Further aggressive interference in the administration of contract was the direction from Knowles to G&T (Mr Whidborne) that Adams Joinery should not have any preliminary costs on variations ordered after the extended date for completion; this was confirmed in an internal G&T e-mail dated 25 October 2007; although Mr Whidborne thought that this was wrong and bizarre, he followed this direction. Knowles representatives told Mr Mackay that BLDA was the worst architect whom they had ever come across (as later referred to in an email of about 4 February 2008).
73.    On 28 September 2007, BLDA issued its Practical Completion certificate in relation to Unit B.
74.    Further problems continued with the Light Wall throughout September and October 2007 and, for instance, on 5 October 2007 WLC issued an extension notification to BLDA.
75.    By November 2007, the complaints about the ABW as stained were continuing and WLC secured a report from the respected TRADA organisation about the ABW which in effect did not criticise what Adams Joinery and WLC had done. BLDA clearly considered that the ABW was in accordance with the contract, for instance as it said in its letter to Knowles of 24 December 2007.
76.    By the end of November 2007, BLDA produced a preliminary list of outstanding items of work, of which major items were the ABW issues, the Stingray door panels, the Light Wall and the Barrisol ceilings. There were some further complaints about the plasterwork and in early December 2007 WLC was addressing these.
77.    By late January 2008, WLC was identifying to BLDA amongst other things that the Barrisol ceilings and related lighting were causing delay. The Light Wall continued to give rise to problems with the lighting effects not being acceptable to Mr and Mrs Mackay.
78.    By early February 2008 if not before, Mr Mackay was beginning to fall out with Knowles. There were unpaid bills outstanding to Knowles but Mr Mackay sensed that Knowles was suspending work pending payment. In an e-mail dated 2 February 2008 to them, he made it clear that he did not like these tactics. He felt that he had spent over £800,000 on Knowles and that this “should have been enough for the fee for the whole action – WE have not really even started!!!” Knowles’ services were to be dispensed with by Mr Mackay within several months. As indicated in an e-mail dated 22 January 2008 to Mr West and Mr Daniel, Mr Mackay referred to Knowles in highly derogatory terms and as not providing value for money; Mr Mackay later (on 12 February 2008) referred to Mr Tomlinson as a “f*****g w****r”. It is also clear that Mr Mackay did not like some of the advice which he was receiving from Knowles to the effect that DMW would have some liability to WLC for delay; this is referred to in passing in Mr Rainsberry’s e-mail of 4 February 2008 to Mr Mackay. Meanwhile, adjudication had been initiated by DMW in relation to the ABW and the well-known adjudicator Mr Tony Bingham was appointed. On 21 May 2008 in a very short decision Mr Bingham decided that WLC was in breach of contract in the supply of the original ABW; he had not been asked to consider the question of the staining.
79.    It is clear that by about February 2008 the works were substantially completed with certain exceptions. These included the Light Wall, snagging (namely final putting right or completing of minor items) and the outstanding ABW dispute. On 21 February 2008, WLC wrote to BLDA saying that, once the Light Wall work and some floor finishing were done by 29 February 2008, it considered that the Works would be practically complete. So far as the ABW issue was concerned, WLC reminded BLDA in effect that the latter had accepted the quality of the veneers in terms of material used and of workmanship and therefore this should not delay the certification of Practical Completion. Knowles wrote back on 22 February 2008 threatening the withholding of sums for the ABW and for the Light Wall. Mr Mackay wrote to BLDA advising it not to award practical completion.
80.    By mid March 2008, DMW had begun the process of terminating the employment of BLDA. As appears from an e-mail dated 4 February 2008 from Mr Rainsberry of Knowles, a primary explanation at least for the timing of this termination was a very real fear on the part of Mr Mackay that BLDA was about to issue a further extension of time to WLC. It was also Mr Rainsberry’s view that BLDA was not in repudiatory breach of its contract and that therefore the contract could not be terminated summarily.  On 28 February 2008 the first warning shot in this process was fired by DMW with a long list of complaints being listed. BLDA’s response of 13 March 2008 was to deny all the allegations and complain about Mr Mackay’s frequent interference with the administration of the project. Later that day, the employment was terminated and within about three weeks a new architect, Navigant Consulting, had been brought in. Unsurprisingly, it took a not inconsiderable time for the new architects to find out what the job was about and they were, through no fault of theirs, not in a position readily to address requests for extensions of time and the like with any promptness. However, Mr Priestley of Navigant very quickly took the view that the ABW workmanship was unacceptable as he confirmed to DMW’s solicitor in an e-mail dated 16 April 2008. He was also in May 2008 to form the view that the problems with the Light Wall were defects for which WLC was responsible.
81.    By April 2008, the final major problem was emerging and this related to the Courtyard Sliding doors which were found to be catching and difficult to open. Investigations were done which involved Firman but ultimately WLC and Firmans took the view that neither was to blame for the problem. WLC did call in experts on the topic. WLC attributed responsibility to the design for which it said it had no liability. Navigant called on WLC to put the problem right on 22 May 2008.
82.    On 23 May 2008, WLC wrote to Navigant giving a brief overview of the current issues. It identified the Barrisol ceilings and lighting, the Stingray doors, the Light Wall, the Leather in the Library and the ABW, various lighting issues in the ground floor cloakrooms and directly employed artists and tradesmen as the primary causes of delays since February 2007.
83.    On 27 May 2008 following Mr Bingham’s adjudication decision on the subject, Navigant instructed WLC to put right the supposed ABW defects failing which DMW could employ others to do so. In the result, WLC did not do any further work on the ABW and so it was that Mr and Mrs Mackay employed a separate company, Interior Joinery, effectively to remove much of the existing stain and to stain it again with an equally or probably darker stain than had been done by Adams Joinery in September and October 2007.
84.    There is no real issue that during this period between the beginning of the year and about August 2008 there was a substantial presence at the site of artists and tradesmen employed directly by DMW or Mr Mackay and there was snagging to do on the part of WLC which to a substantial degree was increased by the need to put right work which had been damaged or affected by their work. WLC complained about this in letters dated 1 and 2 July 2008 to Navigant. There were also issues as between WLC and Navigant as to whether Navigant was cooperating effectively and promptly in the exercise of snagging.
85.    By the end of June 2008, WLC complained to Navigant that their extension of time applications had not been answered to a large extent promptly or at all. They referred to the fact that they had issued 234 extension of time notifications of which 196 remained unanswered.
86.    On 8 July 2008, Navigant warned WLC that it had seven days to put right the alleged defects in the Courtyard Sliding doors failing which DMW could employ and pay others to do the requisite work. On 10 July 2008 WLC wrote to Navigant effectively challenging any suggestion that the works were defective and enclosing a report which they had commissioned from the Building Research Establishment which suggested that the problem was one of Architect’s design. It asserted that this problem should not hold up the issue of the Practical Completion Certificate.
87.    Mr Mackay was not helping to keep the temperature down and there was an exchange of e-mails in July 2008 between him and Mr Howie of WLC who he had taken against. Whilst Mr Howie’s limited responses were polite and restrained, Mr Mackay’s remarks included:
“…you have three major defects notices outstanding…
Guess what when I have forgotten about you in a years time enjoying my £100 million home or sailing on one of my 40 meter yachts – you’ll still be trying to wind up some other poor unsuspecting customer with your brand of mediocrity – a sad loser – gaining your kicks and being irritating. Suggest a new career as a traffic warden might be ideal at least it wouldn’t involve lying.
Ps I’m sure your brokers aren’t interested in this. Perhaps the press would be though…
Oh no, little guy like you – throws his weight around – big chip on your shoulder – you were definitely bullied at school!!!!
…or is it the fact that your little victorian 1800 sq ft cottage in pulborough can fit into my dining room…Or perhaps the fact when you bought it in 2003 the cost was the same as my defective veneer. I’ll bet you will lord it in the pub over those neighbours of yours in the cheap semi’s.
What is it that makes you so chippy little man.
Well whatever it is you’re costing your company of fortune. I reckon around £1.5 million so far. Sent a note to your bosses last night saying your way isn’t working and asking when they might fire you….
You’re such a loser. I’m going to enjoy finishing you off over the summer. But don’t worry you’ll be reading the contract I’ll be on the beach.
…Semis was talking about your neighbours over the road not you -sorry reading isn’t a strong point for you…
Sorry about the pub – you probably bored them into closing down too.
50 this year – midlife crisis as well – nearest to a Ferrari you’ll ever get is a toy one…
…What I find so difficult about you and WL is that you’re really in the crap. You don’t do anything about it apart from trying to jam me the whole time. I really want you all out of my life – it has been a sad chapter. I will not however allow you to continue to take the piss…
My middle name is relentless. I have the money and anger at this point to push on and make sure that you have to deliver or get punished for not delivering. I don’t want to have to fight for that, but trust me I will NEVER give up if you don’t start to change your attitude it will cost WL time and money – it may eventually cost you your job. Who knows. Never underestimate me.
So we can decide to have a change of attitude or we can continue like this I have three counsel’s opinions that tell me I’m in the right on the contract. Is this a risk you all want to carry on with. Over the summer I am away – unless we sorted out it will cost you another £120k in LAD’s. That will be nearly £1.5 million.”
88.    On 16 July 2008, Navigant emailed WLC to say that Practical Completion “should be granted from 7 July which implies from the very start of the day”. This was not to happen. At this stage in reality only the Light Wall and the Courtyard Sliding doors were holding matters up. On 17 July 2008 WLC wrote to Navigant referring to the fact that DMW had been installing soft furnishings, furniture and fixtures and fittings into the property and  suggesting that this was the clearest evidence that practical completion had in practice already occurred. Matters remained unresolved although Navigant told WLC that it was seeking instructions from its client whereby the contentious items could be omitted so as to enable Practical Completion to be issued.
89.    On 13 August 2008, Navigant issued the Certificate of Practical Completion albeit an accompanying note identified that the Light Wall, the ABW and the Courtyard Sliding Doors were removed from the Contract. There was a continuing debate in correspondence over these three items into which it is unnecessary to delve because they remained and remain unresolved. No remedial works were done to them apart from the Interior Joinery work in about June 2008. On 26 August 2008, G&T issued their Valuation No 40 which identified a gross sum due to WLC of £9,107,430.43. This was to form the basis of Interim Certificate No 38 issued on 17 September 2008; the product of this was that there was said to be a sum payable by WLC by reason of previous overpayments.
90.    Further claims for extensions of time were submitted and internally Navigant prepared a report reviewing those claims. It formed the view that some delays attracted extensions of time and others did not. However it was equivocal because Navigant was not sure whether WLC was responsible for the design of the Courtyard Sliding doors and whether the ABW adjudication decision could or would be successfully challenged; it identified a number of relevant events which were at the risk of DMW, including Barrisol and related lighting, Stingray doors and Leather. It did not seem to attach any importance to the Light Wall as a cause of delay.
91.    Part 8 proceedings were issued in the TCC (HT-08-328) which challenged Mr Bingham’s decision. Mr Justice Coulson decided that, if the only cause of the fading of the wood was natural light, then such condition on its own could not render WLC in breach of contract. There is no suggestion that this assertion is not effectively binding on the parties as there was no appeal.
92.    Navigant was obliged as Architect to review extensions of time within 12 weeks of 13 August 2008 but it did not do so.
93.    Over the following months going into 2009 and 2010, there were discussions about further snags and alleged defects and also extensive liaison and negotiation about the final accounting. Navigant’s services were dispensed with and a new architect, Mr Mulhearn became involved on behalf of DMW. Various claims or updating claims were submitted by sub-contractors to WLC; for instance in January 2010 Adams Joinery put in a substantial claim for loss, expense and damages in relation to delay and disruption.
94.    WLC issued the current proceedings on 31 March 2010 against DMW. When serving its Defence and Counterclaim, DMW brought in as Part 20 defendants BLDA, CBP, G&J Stone Ltd (the interior designer) and Equation Lighting effectively blaming them for many of the problems relied upon by WLC as having delayed or disrupted it or otherwise caused it loss. After extensive procedural outings before this Court, DMW settled their differences with those Third Parties. 
Assessment of Witnesses
95.    I will first consider WLC’s factual witnesses:
(a) Graham Corless: he is and was a director of WLC who gave evidence about initial tendering, contract negotiations, continuing high level discussions during the project and certain aspects of the loss claimed. I found him to be a decent, straightforward person and a reliable witness. He answered questions directly and to the point.
(b) Sean McMorrow: he was involved with this project from the start and has been involved in the collation of the WLC claims. I formed the view that he was decent, sensible and “on the ball”. He was well researched and was very straight in the giving of his answers. He seemed to be thoroughly reliable and I have no difficulty in finding him believable.
(c) John Joyce: he was the contract manageryed by WLC. Although occasionally unsettled by the cross-examination, mostly in relation to questions about matters about which he had no direct knowledge, he stood his ground and was consistent in the giving of his evidence. He seemed to be a wholly genuine person and came over as a conscientious man. Again, I found him to be wholly credible and reliable.
(d) John Howie: he was the director brought in to the job at the time (early 2007) when it had become irretrievably obvious that the project was going badly. He was essentially a trouble-shooter whose job it was to get the Works completed. He was not always conciliatory and (with some justification) mistrusted particularly Mr Mackay and his motivation. He did not get on well with the Mackays, although I strongly suspect that, by the time that he came on the scene the relationship between them and WLC was rocky at best. He was undoubtedly faced with unpleasant verbal abuse from Mr Mackay and I formed the view that, although he found it difficult, he retained a level of restraint and politeness which was not reciprocated. He was slightly combative under cross-examination and he was clear and emphatic in answering what was often stern cross-examination. He was well prepared and he came over as believable and, as a witness, reliable.
96.    In relation to the Defendants’ witnesses:
(a) Giles Mackay: he was the key factual witness for the Defendant and as much turns on the extent to which, on contested matters, I accept his evidence, I set out below my impressions:
(i) He qualified initially as a barrister in 1984 but never practised. Since then, he has become an extremely wealthy man, now worth, he said, over £100 million. The business, which he has set up by all accounts extremely successfully, is a focused well financed property investment company, run from offices in Chelsea Harbour. He is clearly an astute but very forceful man. He has been and is obviously very busy primarily at his business but he enjoys sailing, owning several substantial yachts; at various, possibly important stages, he had to leave the country to participate in sailing races or the like. I strongly formed the view that he is a person who is used to getting his own way.
(ii) It is clear that, although he had passed the bar finals and had run for some 20 years (before this development) his substantial property investment business, he had never experienced either building contracts or direct involvement in construction projects. He unsurprisingly believed that his consultants, and in particular his architects, should act only in his interests but he seems to have been unaware throughout most of the project at least that, by agreeing to the standard JCT contract terms, he was leaving with the Architect an independent function of certifying sums due and of awarding, when appropriate, extensions of time.
(iii) He is a person who, virtually, from the start of the project up to this litigation, considered and considers that it is appropriate to apply very substantial sums of money and whatever it takes to getting what he believes he wants. He has spent some £17 – £18 million so far on the construction and, he told me, over £6 million on the costs of this case. His introduction of Knowles, as claims consultant, at a total cost of some £900,000 for 17 to 18 months work, in effect mostly to keep an eye on the other consultants and to dictate to them how they should do their jobs is an example. Save for some of their work in connection with the adjudications, much of this expenditure was substantially wasted.
(iv) He was and became increasingly frustrated as the project stumbled into substantial delay, rising costs and confusion as to who was responsible for what. I find it difficult to determine comprehensively whether it was the original architects, or other consultants, who were, so to speak, to blame or whether they gave appropriate advice at relevant stages to their client which was not followed.
(v) Whatever the cause of his increasing frustration, his behaviour towards the Architects, some WLC employees and other consultants was not simply coarse (for which he apologised on a number of occasions when giving evidence); it was combative, bullying and aggressive and contributed very substantially to the problems on this project. He was particularly critical of the Architect’s meeting minutes and, although on occasions he did point out to them criticism of some of the minute taking (see for example emails dated 4 and 27 February, 8 March, 19 July and 25 September 2007), this was usually done in a very aggressive way; however, for some critical meeting minutes, he did not come back to the Architect.
(vi) I have formed the view that he is and has been for a long time angry. This seems to have started as 2006 went on and was originally directed primarily against the Architect. He has sued many of the parties involved in the development (the Architect, the Services Engineer, the lighting consultants and the interior designer); he has been sued by his second architect for fees, by Knowles and by several firms of solicitors for fees also. He has tried to wind up WLC (unsuccessfully in the summer of 2008), he sought through his solicitors in mid-2008 to suggest that WLC had “rigged” sub-contract tenders (an allegation not pursued in these proceedings), he has set up a website to attract additional complaints against WLC and to publicise complaints against WLC (“Beware of Walter Lilly”) and has sought to interfere with an acquisition by WLC’s parent company. Much of his anger has originated in his mounting frustration when matters did not go as he had hoped.
(vii) I found him to be an unsatisfactory witness. From my observations, I have formed the view that he has lost nearly all sense of objectivity in relation to this development and I consider that he simply does not understand why, given the amount of money which he has spent, the house is not perfect or exactly as he and his wife wanted. His attitude has almost become in the nature of a vendetta against WLC. Although I did not find him to be dishonest, he was at least careless with the truth in a number of respects. An example was his Third Witness Statement in which he stated that he believed that two representatives of Knowles were practising barristers or solicitors; he must have known on any account that they were not solicitors, practising or otherwise and, having taken the Bar exams himself, must have been conscious broadly of what was required to be a practising barrister; there was little if anything to suggest that they were practising barristers, albeit that they too, like him, had passed the Bar exams. Another example was his evidence in court that shortly before BLDA was dismissed he did not believe that BLDA would grant another extension of time to WLC; that was directly countered by contemporaneous documents which showed that he clearly had this in mind. His evidence that he could not remember issuing a direction to G&T not to issue further valuation recommendations was expressly countered by the documentary evidence with which he had personally been involved at the time.
(viii) Having initially directed his ire against BLDA, he turned his attention also to WLC. I found him a most unconvincing witness. His objectivity having gone, I think that he has now convinced himself of the truth of certain matters such as those relating to the ABW issues such that, although he believes that he is right, he is obviously not.
(b) Caroline Mackay: she is a person who clearly knew what she believed she wanted in relation to this development. She had carried out extensive research before and even during the project as to what was required for the house. She was guileless and stood up well to cross-examination. She was also upset in the latter 12 to 18 months of the project as defects and delays began to emerge. She was clearly particularly upset about the way in which the ABW was eventually left by WLC, as it was she who had chosen the particular wood and, as she saw it, its appearance changed from what in her mind’s eye it should have been. Until she told the Court at the end of her evidence that she had a law degree and had practised as a solicitor in two well-known London firms for some 8 years, it had not been wholly obvious that she was well qualified to deal with people and business affairs in a businesslike fashion. She was frank and I had no reason to doubt her honesty.
(c) Gavin Bartlett: he was an assistant project manager employed by RLB who were appointed to oversee the construction works which were omitted from the Contract between DMW and WLC. He was brought in to replace a Mr Bardsley who had been in charge of this operation prior to September 2007. Although he only worked on the project for 11 months and had no further contact until late 2011 for the purposes of giving a witness statement, he remembered what had happened at a key meeting in September 2007, the minutes of which he must have seen at the time but did not challenge; his memory was that, contrary to what the minutes said, no general instructions were given to WLC to stain cupboards and skirtings. I found him wholly unconvincing in this context not only because he did not challenge the minutes but because this work was not his area of responsibility and he would have had no reason to have any specific memory about it.
(d) David Cane: I formed the view that he was reasonably straightforward and open in the giving of his evidence. Some of his recollection was faded; for instance, he had forgotten that WLC had invited G&T to verify certain aspects of the quantum.
(e) Richard Whidborne: he took over from Mr Cane as the acting quantity surveyor for the project in about March 2007; he was effectively sub-contracted by G&T. His evidence was largely uncontroversial but for instance, he had forgotten (and with it was clearly a surprise even to him) that he had been directed by Knowles to do things which he did not agree with and which he almost at least accepted would have been unprofessional. I was not impressed with his memory.
97.    So far as the experts are concerned that my views are as follows.
98.    As for the delay experts, Mr Robinson and Dr Aldridge, I preferred Mr Robinson in almost every respect. He, broadly, logically and conventionally, adopted the approach of establishing critical delay by reference to the “logical sequence(s) of events which marked the longest path through the project”; Dr Aldridge accepted that this was generally the way to calculate delay (this being taken from Paragraph 9.1.9 of his January 2012 report). In the difficult circumstances facing both experts by reason of the absence of any usable contemporaneous programme from early 2007 onwards, Mr Robinson adopted a much more objective approach to his expert analysis whilst Dr Aldridge proceeded on a much more subjective approach (which he accepted at least in part). I amplify on this in the extension of time chapter in this judgment.
99.    Dr Aldridge’s report also in some respects almost reads simply as a suggestion to the Court that the Claimant has not proved its case; an example is the opening words: “Walter Lilly’s case does not stack up”; his report is littered with this type of remark that WLC has failed to prove or demonstrate this or that or to make out its case; it is not for an expert to suggest this type of thing. He proceeds on an obvious logical misapprehension that, if works are finished before Practical Completion, they cannot have delayed completion. His suggestion that plastering defects delays could realistically have contributed to the overall delay is simply unsustainable in circumstances in which there was ultimately a limited amount of remedial work actually done and the remedial work was substantially completed by April 2007. His adoption of an approach based on determining the most “significant” matters preventing practical completion led to him adopting in many respects a subjective approach as to what his client thought was significant. This approach was one which Mr Robinson had never seen used.  He frequently descended into the arena of disputed facts and liabilities in which he was not the relevant expert; an example was Paragraph 2.2.35 of his January 2012 report when he felt able to criticise “WLC’s unwillingness to accept that the colour variation (and the very poor quality of staining which had made matters worse) was an unacceptable defect requiring rectification”. Some parts of his report were based on conversations and information which were not in evidence and on occasion he had to accept that he was given information by Mr Mackay and by Navigant which was not contained or referred to in his report. He produced as Appendix D a “Weighted Significance Matrix” which was worthless and self-fulfilling when he on a largely subjective basis awarded weightings to the various possible causes of delay; this was taken through the project in 2007 and 2008 on a monthly basis and, unsurprisingly gave much higher weightings to the subjectively accepted factors (such as plastering defects) selected by him or his client as “significant”.
100.    As for the Architect Experts, I preferred the well researched, very open and pragmatic approach of Mr Zombory Moldovan, WLC’s expert. He was clear and positive throughout. Mr Josey is an experienced expert and was open, as one would expect, with the Court. He has, perhaps somewhat unfairly, been criticised by WLC’s Counsel for having been instrumental prior to the Defence and Counterclaim in drawing up detailed lists of defects; it was said that this was indiscriminate because it did not identify what defects were the fault of WLC. Whilst it is the case that initially very large quantities of defects and amounts were counterclaimed against in respect of defects (many of which were later dropped), I would not criticise Mr Josey for that; it would be up to those advising DMW, DMW and Mr Mackay himself to identify who had a contractual or legal responsibility for the defects. However, he did labour under the disadvantage that he had to accept that a large number of them could no longer be pursued against WLC, including some which he had himself supported. I would not criticise him but I found Mr Zombory Moldovan much more reliable.
101.    In relation to the quantum experts, both are experienced quantity surveyors with experience of litigation. I much preferred the approach of Mr Hunter which was pragmatic and down to earth. I was disappointed with Mr Pontin who, although an experienced expert, I felt was trying too hard to reduce the delay and other quantum heads to an insignificant level. Whether he felt, subconsciously, pressurised by Mr Mackay or not I can not say. But his arguments were reduced to scraping the barrel in some respects such as suggesting that WLC had not demonstrated any loss and expense attributable to Plot C alone; this was absurd because it must follow that, if there was as here delay (almost 30 months delay), some time and resources must have been incurred in consequence and that obviously has a cost. He endorsed a totally artificial calculation to demonstrate that WLC had recovered all its preliminaries costs on the three Units.
The Contract 
102.    The Agreement between DMW and WLC was contained in a memorandum dated 28 May 2004. It set out that the Conditions were to be those contained in the JCT Standard Form of Building Contract 1998 Edition Private Without Quantities, incorporating various specific amendments, as modified by the Contractors Designed Portion Supplement Without Quantities 1998 edition (revised November 2003), as amended by the Schedule of Amendments dated 26 May 2004 and the documents referred to therein. I will refer to these conditions as amended below. BLDA was named as the Architect and G&T was named as the Quantity Surveyor.
103.    I will initially review the Contract to consider to what extent WLC owed design responsibilities or otherwise how design responsibility might pass to WLC.
104.    The Recitals, as amended, are of some importance. The First Recital made it clear that DMW was desirous of having carried out “the construction of three dwelling houses with basements and parking facilities with a private service road with access from Bolton’s Place…”. The Second Recital defined what is to be the “Contractors Designed Portion” as:
“the work referred to in the First recital includes the construction of certain works as notified by the Employer to the Contractor in writing”
105.    The Third Schedule was in the following terms:
“The Employer has caused the following documents to be prepared, sharing and describing the work to be done:
the Contract Drawings numbered [sic] the drawings listed at Appendix A of the Architectural Specification (together with drawing number 0119 P300 Site Layout…and at Appendix A of the Structural Service Specification…
and the following documents:
1. The specification dated March 2004 reference 18100…
3. The Tender Submission by Walter Lilly & Company Limited dated March 2004 reference 04023 [subject to some exclusions and amendments]…
together hereinafter referred to as “the Specification/that Schedule of Work”
together with other documents showing or describing or otherwise stating the requirements of the Employer for the design and construction of the Contractor’s Designed Portion (hereinafter referred to as the ‘ Employer’s Requirements’)”
106.    Article 1 stated:
“For the consideration hereinafter mentioned the Contractor will upon and subject to the Contract Documents…carry out and complete the Works shown upon, described by or referred to in those Documents and for that purpose will complete such design of the Contractor’s Designed Portion… as may be necessary in accordance with the directions which the Architect…shall give for the integration of the design for the Contractor’s Designed Portion with the design for the Works as a whole subject to the provisions of clause 2.7.”
107.    Clause 2 of the Conditions contained the following terms:
“2.1.1 The Contractor shall upon and subject to the Conditions carry out and complete the Works in compliance with the Contract Documents.
2.1.2 For the purposes of so carrying out and completing the Works the Contractor shall, in accordance with the Contract Drawings and the Specification/Schedules of Works where and to the extent that the same are relevant, complete the design for the Contractor’s Designed Portion including the selection of any specifications for any kinds and standards of the materials and goods and workmanship to be used in the construction of that Portion so far as not described or stated in the Employer’s Requirements…, and the Contractor shall comply with the directions which the Architect…shall give for the integration of the design for the Contractor’s Designed Portion with the design for the Works as a whole, subject to the provisions of clause 2.8…
2.1.3 Where and to the extent that approval of the quality of materials or the standards of workmanship is a matter for the opinion of the Architect…such quality and standards shall be to the reasonable satisfaction of the Architect…”
2.7.1 Insofar as the design of the Contractor’s Designed Portion is comprised in the Contractor’s Proposals and in what the Contractor is to complete under clause 2.1.2 and in accordance with the Employer’s Requirements and the Conditions (including any further design which has to be carried out by the Contractor as a result of a Variation) the Contractor shall have in respect of any defect or insufficiency in such design the like liability to the Employer, whether under statute or otherwise, as would an architect or, as the case may be, other appropriate professional designer holding himself out of as competent to take on work for such design who, acting independently under a separate contract with the Employer, had supplied such design for or in connection with works to be carried out in completed by a building contractor not being the supplier of the design.
2.10 An extension of time shall not be given under clause 25.3, and clauses 26.1 and 28.2.2 shall not affect, where and to the extent that the cause of the progress of the Works having been delayed, affected or suspended is:
2.10.1 any error, divergence, omission or discrepancy in the Contractor’s Proposals…
2.10.2 failure by the Contractor to provide in due time necessary drawings, details, specifications, calculation or information concerning the Contractor’s Designed Portion as required by clause 2.6.2, or
2.10.3 the Architect…not having received in due time necessary drawings, details, specifications, calculations or information concerning the Contractor’s Designed Portion from the Contractor for which he specifically applied in writing…”
“Employer’s Requirements” were in the Supplementary Appendix “to be agreed”. These documents would spell out what the Employer required the Contractor to achieve through any design process which was to be assumed by the Contractor.
108.    Provision was made in Clause 4 whereby the Contractor was required to comply with instructions issued to it by the Architect. Clause 8.1 required all materials and goods broadly to be of the specified types and standards set out in the Specification and Schedules of Work. Clause 13.1 entitled the Architect to issue instructions requiring a Variation to the Works, being an “alteration to or modification of the Employer’s Requirements”. Clause 13.3.1 required the Architect to “issue instructions in regard to the expenditure of provisional sums included in the Specifications/Schedules of Work.” Clause 13.3.2 entitled the Architect to omit in whole or in part provisional sums for internal finishings, finishes generally, fittings and furnishings and landscaping. Clause 13.4 provided for the valuation of instructions requiring the expenditure of provisional sums either by way of an accepted “Price Statement” or under the provisions of Clause 13.5. That latter sub-clause would value such work as if it was a variation.
109.    In reality, all the substantive work set out in the Specification (that is, apart from the Preliminaries) was simply identified by way of provisional sums. Thus piling was simply identified as “Piling to Perimeter” and a provisional sum of £600,000 identified. “Finishes Generally” attracted a provisional sum of £1,545,000.
110.    Clause 19 addressed sub-contracting. Relevant provisions are:
“19.2.1 A person to whom the Contractor sub-lets any portion of the Works is in this Contract referred to as a ‘Domestic Sub-Contractor’.
19.2.2 The Contractor shall not without the written consent of the Architect (which consent shall not be unreasonably delayed or withheld) sub-let any portion of the Works. The Contractor shall remain wholly responsible for carrying out and completing the Works in all respects in accordance with clause 2.1 notwithstanding the sub-letting of any portion of the Works.
19.2.3 The Contractor shall not without the written consent of the Architect (which consent shall not be unreasonably delayed or withheld) sub-let the design for the Contractor’s Designed Portion of the Works. Where the Employer consents to any such sub-letting such consent shall not affect in any way the obligations of the Contractor under clause 2.7 or any other provision of this Contract.
19.4.2.4 In respect of the Works to be undertaken by the Domestic Sub-Contractor pursuant to the sub contract (“the Sub-Contract Works”), insofar as the design of the Sub-Contract Works has been or will be carried out by or on behalf of the Domestic Sub-Contractor, the Domestic Sub-Contractor has exercised and will continue to exercise the skill, care and diligence to be expected of a professionally qualified and competent designer who is experienced in carrying out such work of a similar scope, complexity, nature and size to the Sub-Contract Works.”
111.    The Specification, which was a Contract Document, set out in the Preliminaries Section 1 details of the site. Part A13 describes the work as comprising “the construction of three high specification private residencies comprising accommodation at basement and ground to the third floors including underground swimming pool and garage”. At E on page 1/5 the following is stated:
“The following works may be designed by the Contractor:
    Windows…
    Lifts…
    Piling…
    Basement Waterproofing
    Mechanical & Electrical”
This list did not include any finishings, joinery or glazing.
112.    The Specification also provided for what was called “Category B” work to be carried out by Domestic Sub-Contractors, these being “Firms selected by competition from a list of names compiled by the Architect and Contractor as described in Clause 19.3.2” of the Contract Conditions (page 1/12). Page 1/13 stated that for Category B work specific works were identified including the mechanical, electrical and public health services installation, along with the lifts installation, landscaping and swimming pool, pool equipment and plant. Page 1/17 required “shop drawings [to] be submitted to the Architect prior to the manufacture or execution of the work covered by the shop drawings.” Page 1/18R stated:
“Certain Sub-contractors as defined in the Contract will be required to provide design, coordination, fabrication, installation and or builders were drawings, design calculations, fixing details, specifications and other information as appropriate during the course of the Contract. Certain Sub-contractors will be required to obtain all local authority building control approvals and any other statutory approvals that may be necessary for their detailed design and works, and shall be responsible for the provision of all necessary information to enable such approval to be obtained in time to meet the programme. Those Sub-contractors to which this paragraph applies shall include (but shall not be limited to) those associated with the following words:
    1. Windows…
5. Lift…”
Nowhere was it specified or defined that there were to be Sub-Contractors to provide design or other related design work for the pool hall glazing, courtyard doors or joinery.
113.    Page 1/19 and following addressed in relation to the Contractor’s Designed Portion what general requirements there were for the submission of design and production information by the Contractor to the Architect for approvals.
114.    Appendix C to the specifications contained a slightly wider description of the Works. It referred to the planning permission granted in June 1999 and to the fact that an application would be made to vary the permission in a number of ways including that the swimming pools would be built under the rear gardens. Appendix D provided what was called the Structural Engineer’s First Stage Scheme Design Report, which broadly described in lists what was to be provided. The lift was described as a “glass lift car with indirect hydraulic action”. Many of the Contract Drawings were described as “Preliminary” comprising layout and general arrangement plans. There were two elevation drawings.
115.    WLC’s letter dated 29 March 2004 to G&T (incorporated into the contract) amongst other things stated:
“Although there are a number of elements of the works that may be let as  Contractor Design Portions, we have not included the costs of any Professional Indemnity Insurance or any designer/coordinator input that may be required, should all any of the stated elements be let in this way. As an indication with regard to PI cover, we usually add 0.75% to the value of any CDP package.”
116.    In the light of the contract terms, it is necessary to consider how and in what circumstances a design responsibility and liability can arise in relation to WLC as the Contractor. Normally, with this form of contract, as one of the expert architects confirmed, the areas of work which are to be part of the Contractor’s Designed Portion are specified in the contract documentation. That did not happen in this case. All that one had in the Specification was identification at page 1/5 of works which “may be designed by the Contractor”. Clearly the word “may” is not permissive in the sense that the Contractor could choose to design these works. The use of the word “may” is clearly intended to identify those works which can be the subject matter of selection by the Employer to be designed by the Contractor.
117.    The term “Contractor’s Designed Portion” is only defined in the Amended Second Recital and was specified as being “the construction of certain works as notified by the Employer to the Contractor in writing”. Thus, an element of work can only become part of the Contractor’s Designed Portion if and therefore presumably when DMW notifies WLC that this is to be the case. It is of interest and importance to note that it must be DMW which notifies and the Architect or the Quantity Surveyor are not as such given authority by the terms of the contract itself to notify; that is in contradistinction for instance to the Architect being given authority to issue instructions requiring Variations.
118.    The next point concerns whether the list at page 1/5 in the Specification limits what is to be designed by the Contractor. In my view, the contract is clear that the Specification identifies those works which may or can be notified by DMW pursuant to the definition in the Second Recital. The Contractor cannot be asked to design works outside the list at page 1/5. Although the wording at Page 1/18 is possibly or partly otiose, it is interesting that there is a reference to sub-contractors to which the paragraph relates “including” those associated with specified works.  Page 1/5 does not provide a list, so to speak, by way of example.
119.    Page 1/18 is at best confusing. The reality is that no “Sub-contractors” were “defined in the Contract”, at least by name. Elsewhere (at page 1/12R), Category A was to be work by “Domestic Sub-contractors” where the firms were “named in this Specification”; this Specification was, one assumes, a template used by the Architect or Quantity Surveyor and there are no firms “named” in it in this case. The 18 types of work are the first 18 of the 21 types of work refer to page 1/5. It could be said that the distinction is being made between the Contractor being asked to design as compared with certain Sub-Contractors being asked or required to design. Reading page 1/5 with page 1/18, the meaning becomes much clearer. If the Employer notifies the Contractor in writing that it requires any one of the 21 types of work set out at page 1/5 to be designed by the Contractor, Sub-Contractors are to be deployed to provide design services for any of the first 18 of those types.
120.    One must then move on to consider how, contractually, the notification by DMW is to be made. Obviously, it must be in writing and that could doubtless be by letter, e-mail, fax or even by a meeting minute. It is obvious also that the notification must be to WLC because it must know, commercially and practically, that it is to assume design responsibility. The wording of any notification does not have to be in any particular form but what must be required is that it must be sufficiently clear to be understood as a notification that design responsibility is to be assumed by WLC for the particular item of work within one of the 21 categories identified on page 1/5. It follows from this that, as a matter of contractual interpretation, some sort of constructive or inferential knowledge on the part of WLC that it might have a design responsibility for a given item of work does not in itself deem there to have been notification. One needs to look at whatever the notification is said to be and, primarily answer two questions: is this clearly a notification under the Second Recital and is it a notification to WLC?
121.    I do not consider that notification by the Architect, as Architect under the contract, is sufficient because there is nothing in the contract itself which suggests that the Architect is clothed with authority in that role to notify something which the parties have agreed will, if it happens at all, be done by DMW. It would be different if the Architect, with specially given authority, wrote words to the effect: “On behalf of the Employer, I hereby notify you are to have design responsibility for (for example) the CCTV work”.
122.    In commercial and practical terms, it is important in my judgement under this construction contract for the notification to be clear and unambiguous. The main reasons are that everybody involved in the project, particularly the Architect and other professional consultants as well as the Contractor, need to know who has the ultimate or any particular design responsibility for any given work. If the Contractor has it, then the Architect knows to call for design documentation for approval. If the Architect or other of the Employer’s professionals retains responsibility, the Contractor knows from whom to call for information. Either way, each can protect itself by securing appropriate warranties or other protection from, say, sub-contractors who are to be retained. Another not unimportant reason for clarity is that, given that all works were the subject matter of provisional sums, it is more than arguable that the Contractor would be entitled to some additional compensation for design coordination as well as for the cost of procuring appropriate professional indemnity insurance as called for in the tender letter of 28 March 2004.
123.    In determining whether a CDP notification  has been given, it may as a matter of fact be relevant to determine if a design brief or what can be identified as “Employer’s Requirements” have been provided by or on behalf of the Employer to the Contractor. If no such brief or document which can clearly be identified as “Employer’s Requirements” has been provided, depending on what else has been notified in writing to the Contractor, it may be that one cannot even by inference or interpretation determine that a CDP notification has been given.
124.    Because it features in the differing approaches to delay analysis adopted by the two programming experts, it is also necessary to review what the Contract Conditions require. Clause 23.1.1 provides that on the 12 July 2004 WLC was to be given possession of the site, proceed regularly and diligently with the Works and to have completed by the Completion Date, 23 January 2006. Clause 25 provides for the Completion Date to be extended if various Relevant Events occur which cause delay. These Relevant Events include compliance with Architect’s Variation instructions (Clause 25.4.5.1) and a failure by the Architect to provide instructions and information timeously (Clause 25.4.6.2). Relevant provisions of Clause 25 are as follows:
“25.2.1.1 If and whenever it becomes reasonably apparent that the progress of the Works is being or is likely to be delayed the Contractor shall forthwith give written notice to the Architect of the material circumstances including the cause or causes of the delay and identify in such notice any event which in his opinion is a Relevant Event…
25.2.2 In respect of each and every Relevant Event identified in the notice given in accordance with clause 25.2.1.1 the Contractor shall, if practicable in such notice, or otherwise in writing as soon as possible after such notice:
.2 .1 give particulars of the expected effects thereof; and
.2.2 estimate the extent, if any, of the expected delay in the completion of the Works beyond the Completion Date resulting therefrom whether or not concurrently with delay resulting from any other Relevant Event…
25.3.1 If, in the opinion of the Architect, upon receipt of any notice, particulars and estimate under clauses 25.2.1 [and] 25.2.2
.1.1 any of the events which are stated by the Contractor to be the cause of the delay is a Relevant Event and
.1.2 the completion of the Works is likely to be delayed thereby beyond the Completion Date
the Architect shall in writing to the Contractor give an extension of time by fixing such later date as the Completion Date as he then estimates to be fair and reasonable. The Architect shall, in fixing such new Completion Date, state:
.1.3 which other Relevant Events he has taken into account and…
and shall, if reasonably practicable having regard to the sufficiency of the aforesaid notice, particulars and estimate, fix such new Completion Date not later than 12 weeks from receipt of the notice and of reasonably sufficient particulars and estimate or, where the period between receipt thereof and the Completion Date is less than 12 weeks, not later than the Completion Date…
25.3.3 After the Completion Date, if this occurs before the date of Practical Completion, the Architect may, and not later than the expiry of 12 weeks after the date of Practical Completion shall, in writing to the Contractor either
.3.1 fix the  Completion Date later than that previously fixed if in his opinion the fixing of such later Completion Date is fair and reasonable having regard to any of the Relevant Events, whether upon reviewing a previous decision or otherwise and whether or not the Relevant Event has been specifically notified by the Contractor under clause 25.2.1.1…
25.3.4 Provided always that:
.4.1 the Contractor shall use constantly his best endeavours to prevent delay in the progress of the Works, howsoever caused, and to prevent the completion of the Works being delayed or further delayed beyond the Completion Date…”
125.    From these terms, one can draw the following conclusions material to this case:
(a) To secure an extension of time before Practical Completion, the Contractor has to give notice if the Works are being delayed or are likely to be delayed. This notice can relate therefore to actual delays being experienced or to future likely delays.
(b) The notice should be accompanied or be followed as soon as practicable by particulars of expected effects and an estimate of the expected delay.
(c) What is at least initially envisaged is that the Architect will carry out a prospective exercise; this is because the Contractor can give notice when progress is likely to be delayed and the Architect has to assess what the likely delay will be. This makes sense so that the parties and the Architect can plan for the rest of the job. Of course, notice can be given when the Works have actually been delayed but actual overall delay will not happen until after the original Date for Completion has passed. How the Architect does this prospective exercise of working out how much future delay will result from the Relevant Events in question is not prescribed but he or she will simply have to do the best that he or she can; this may well be assisted by programming exercises done by the Contractor.
(d) Once the notice, particulars and estimate under Clauses 25.2.1 and 25.2.2 are given, the Architect is required to grant the appropriate extension of time. This is not an optional exercise: the word “shall” is clearly and intended to be mandatory.
(e) No later than 12 weeks after Practical Completion, the Architect must carry out the final extension of time exercise, irrespective of whether notices and the particulars have been provided. This will necessarily be a retrospective exercise because Practical Completion will have passed and all the delays (whatever the causes) will have occurred. Again, the way in which this exercise is to be done is not defined.
126.    I will review other provisions in relation to other specific disputes later in this judgement.
The Proceedings and the Pleadings
127.    WLC’s Claim was issued on 31 March 2010 along with the original Particulars of Claim. It was initially a relatively compact pleading in which the claims included seeking an extension of time to Practical Completion, the return of deducted liquidated damages and sums wrongly deducted for alleged defects, loss and expense related to delay and the outstanding unpaid value of works. The extension of time claim was based on events surrounding the Light Wall, the Leather in the Library, the Stingray doors, the lighting and Barrisol ceilings, ABW, External Works and WC2 and WC3 lighting. The Particulars of Claim have been amended twice and been particularised by way of Voluntary Particulars and other Further Information. There were Annexes and Schedules attached which provided some further information about the delays and the money claims.
128.    DMW served its original Defence and Counterclaim in September 2010 although it has since been amended on four occasions. The basic pleading ran to 414 paragraphs and 140 pages along with detailed appendices. It is fair to say that there was a thorough response and a myriad of issues was raised. It claimed that there had been an overpayment in terms of the value of work, that no further extension of time was due, that substantial liquidated damages were due and that a sum approaching £2 million was due to defects and that WLC’s holding company was also liable under the terms of a guarantee.
129.    DMW also brought Part 20 claims against BLDA, CBP, JSI and Equation which pleaded most of the defects against one or more of them and asserted that the delays were caused by them, to a greater or lesser extent, to the extent that it was established that WLC was entitled to an extension of time. These third parties responded.
130.    There were a number of procedural outings to the Court, some of which were heavily contested, in particular those which related to the way in which WLC had particularised or proposed to particularise its case on delay and its linkage to the loss and expense claimed. The Court eventually decided that a Re-amendment to the Particulars of Claim was appropriate supported by extensive Voluntary Particulars (in the final form) and an extensive document called “Detailed Loss and Expense”.
131.    In mid-July 2011, DMW and the third parties settled their differences under an agreement by which they paid DMW some £1.8 million inclusive of costs. This at least was sensible given that the costs of six parties would have led to costs (even assessed on a standard basis) massively exceeding what was really in issue in the case.
132.    There is no need here particularly to analyse those pleadings because I address what remained of the pleaded issues in the body of this judgement.
Analysis of Major Causes of Delays and Major Defects
133.    Given the pleadings and the allegations and evidence put forward about alleged defects and causes of delay, it is sensible to analyse the facts and legal responsibilities in relation to the suggested problem areas, namely the ABW, the Courtyard Sliding Doors, the Light Wall, the Lift, the Barrisol Ceilings, Leather in the Library, snagging and plaster defects. An important area for consideration of the first six items is the contractual risk or responsibility for the design. I will not here consider the delay consequences of these problem areas but simply seek to make findings of fact and liability, which will or may impact on the delay analysis which follows.
ABW
134.    The wood for the flooring throughout much of Unit C and the veneered cupboards and skirtings was American Black Walnut, which was a personal selection and preference of Mr and Mrs Mackay. Although the quality of the flooring was also criticised in 2007 and 2008, no allegations in relation to the flooring have been pursued in these proceedings. The complaints relate to most of the veneered cupboards and skirtings. There are essentially two main issues relating to ABW. The first is whether or not WLC owed any duty to DMW to advise it or its architect about the risk that ABW does have a propensity to fade in natural light. The second issue revolves around whether or not in September 2007 Mr and Mrs Mackay effectively instructed WLC to stain all the veneer wood throughout the house and whether WLC should have advised or warned DMW or the Mackays that the staining or staining process would or could suppress the effect of the natural grain. Whilst the second issue is arguably the most important issue, the first issue is relevant because it was the fading and changing of colour of the veneered wood which ultimately led to whatever the decision was about staining. This first issue involves a consideration of whether or not (and to what extent) WLC and Adams in effect on its behalf had some sort of design or designer responsibility to advise about the risk of fading. DMW immediately runs into difficulty on this first issue because Mr Justice Coulson has already decided in the Part 8 proceedings ([2008] EWHC 3139 (TCC)) that the fading of the ABW cannot, in the absence of an identifiable breach, give rise to a liability on WLC. There is no express term of the Contract that the wood should not fade; if WLC is not in breach of contract as such for the wood fading, it is difficult to see that it had any obligation to advise about the risk of fading. That said, it is still necessary and helpful to review what happened and what the contractual risks and responsibilities were because DMW argues that there was a design obligation on WLC which would have encompassed an obligation in effect to warn.
135.    There was no express or expressed notification to WLC by DMW or anyone on its behalf that design responsibility should fall on WLC.
136.    At some stage in the first half of 2005, Mr and Mrs Mackay had selected ABW as the wood which they wanted for the flooring and for the joinery and skirtings. On 27 May 2005, WLC invited, amongst others, Adams Joinery, to quote in relation to the joinery for “the supply and fit out of” various rooms in Unit C; this was said to be Package No WP 284 and the attached Contract Tender Enquiry document provides only general requirements for tendering, albeit it envisages that working drawings would be provided by the sub-contractor and for “design development”. There is no evidence that this form of Enquiry was promulgated, required or otherwise called for specifically by DMW or anyone on its behalf. Adams Joinery quoted on 23 June 2005 (£410,275.93 for five bathrooms, two dressing rooms and two WCs) and on 8 July 2005 (£275,428.12 for the Cinema, Wine Store, Cloaks, Family Room, a WC, Library and Mrs Mackay’s study). These quotes were “for the supply and installation as per architect’s drawings”. There is no suggestion that the Architect’s drawings add anything which might suggest any design responsibility was being devolved through WLC to the selected joinery sub-contractor. There followed a period in which there were some discussions and negotiations on price, including as between G&T and Adams Joinery.
137.    On 3 October 2005, BLDA by its Instruction No. 166C instructed WLC to place its order with Adams Joinery in relation to these quotations and G&T’s attached summary sheet. That attached sheet identified a revised tender sum of £546,545.71 which identified negotiated reductions for preliminaries and a £17,000 reduction “on the basis that BLDA have finished design and there is little need for design development”.
138.    On 23 November 2005, WLC wrote to Adams Joinery saying that it was their intention to place orders with it “for the design development, supply, delivery and installation of the fit out works and selected joinery”. Over the following four or five months further quotations for additional rooms were sought from and provided by Adams Joinery; 20 October 2005 (three quotes, £139,133.48 for staff rooms, drawing room and two children’s bedrooms, £29,914.13 for Mr Mackay’s study and £35,409.24 for the master bedroom and guest suite), 7 November 2005 (three quotes, details not in the Court papers) and 2 December 2005 (one quote, not in papers). There is no suggestion that these further quotations quoted for anything other than the supply and installation of joinery in all the rooms which are the subject matter of the ABW complaints or that the Architect’s instructions, so to speak, accepting them, called for anything other than the “supply and installation” of the joinery in question.
139.    Ultimately, by way of an Order dated 13 January 2006 signed by WLC and Adams Joinery, a sub-contract was entered into nominally in relation to the works quoted for on 23 June 2005 and 8 July 2005 by Adams Joinery. The works were briefly described as “fit out” works and there was a Schedule of Documents forming the Sub-Contract Agreement. This Schedule however related to more than just the rooms and the areas described in those two quotations and reflected further architects instructions relating to the later quotations by which WLC was again instructed to place orders with Adams Joinery “for the supply and installation” of various items of joinery. There is nothing on the face of all the Architects Instructions which called for design work as such to be done either by WLC or by Adams Joinery in relation to the joinery. The total sum identified in the Schedule of Documents was £747,573.91. The “Subcontract Pre-Order Agreement”, said to have been incorporated identifies that the works extend not simply to joinery but also to other types of fit out including bathrooms and against Box 29, whilst “Full Design” was expressly excluded, “Development of Design”, “Co-ordination of Design” and “Co-ordination of Design with other trades” was required. This Sub-Contract must have been entered into shortly after 6 March 2006 because the last documents referred to in the Schedule of Documents is dated 6 March 2006.
140.    The relevant specification referred to in the Adams Joinery Sub-Contract was NBS Z10 which was an adapted National Building Specification for “Purpose made joinery” which had been issued albeit not formally, by instruction or letter, by BLDA to WLC. Relevant clauses were:
“102c DESIGN AND PRODUCTION RESPONSIBILITIES
The Subcontractor shall be responsible for the following:
Completing the design/detailing and provide complete fabrication/installation drawings, full sized rods/shop drawings as appropriate for approval by the Architect…
220a WOOD VENEERED BOARDS/PANELS…
Setting out: Veneer features is and grain pattern aligned regularly and symmetrically unless instructed otherwise…
Veneer edges: Tight butted and flush, with no gaps…”
141.    There is nothing in what passed between DMW and its consultants on the one hand and WLC on the other which expressly or even by implication suggests that design liability was being passed to WLC. The fact that WLC was seeking to impose on Adams Joinery some design responsibility, albeit limited to design development and the production of working drawings, does not in itself, logically, commercially or at all, give rise to any inference that WLC was being notified or required by DMW to assume a design responsibility as between DMW and WLC. No case in estoppel is pleaded by DMW in this context so, for instance, it is not being suggested that by way of some estoppel by convention the parties were proceeding on the basis that WLC had assumed a full or material design responsibility as between it and DMW.
142.    The Z10 specification relating to the completion of the design or detailing does not really assist DMW in this context. The basic design had in fact been done substantially by BLDA; this much is evident from the 39 BLDA drawings set out in the Schedule of Documents and also from the main Architect’s instruction which expressly referred to BLDA having finished the design and there being little need for “design development”. Even if, as between WLC and DMW there was some design obligation on WLC, it would be limited to “completing” the design; that must envisage that essential design decisions had already been taken and that those decisions were effectively immutable. There is no real suggestion that any obligation on the part of Adams Joinery to produce fabrication or working drawings carried with it a general design obligation or responsibility.
143.    Mr Zombory-Moldovan, the expert architect called by WLC, said in evidence that. fabrication and shop drawings are drawings that show the composite of how a design is to be made and how it is to be manufactured; a fabrication drawing is not simply the isolation of components of the installation for production in the factory or the workshop but it brings together all of those components and sets it them out on a composite drawing. From that drawing the manufacturer is then able to identify specific components, but can understand from its own shop or fabrication drawing how many specific components sit within the overall arrangement. I accept this evidence as logical.
144.    It was Mr and Mrs Mackay who selected ABW as the wood which they wanted for the veneered cupboards and skirtings. This occurred essentially in 2005 at a time when Adams Joinery had not finally been engaged contractually by WLC. The documentary evidence shows that the selection of a Danish Oil finish as opposed to a lacquer finish (save in a few areas) had been made by mid February 2006. On 16 February 2006, BLDA emailed Adams Joinery confirming this. Bev from DMW’s interior designers did not like the lacquer finish because it looked “cheap” and Mr and Mrs Mackay did not like the lacquer finish, as confirmed in Bev’s email dated 17 February 2006 to BLDA. This selection was made notwithstanding the clear recommendation of Mr Hawks of Adams Joinery that lacquer was better because it gave added durability; he repeated that advice in an e-mail to BLDA on 17 February 2006, expressing his great concern. This is important because it does not appear that at least those advising Mr and Mrs Mackay were placing any significant reliance on what Adams Joinery were saying about this. To the extent that they were relying on anyone, the Mackays were relying on the interior designer (Bev) and BLDA. Mrs Mackay gave evidence that she went to Reliance Veneers in March 2006 but this must have been simply to select the particular piece of ABW from which the veneer was to be taken. The basic decision about using ABW had been made already many months before because Adams and others had been asked to quote for the use of ABW. Adams did send various samples of ABW in March 2006 and, I find, it is likely that they did not have a sticker on the back which suggested that the veneer might fade in sun light.
145.    Later in 2006 going into early 2007, Adams Joinery supplied and installed the ABW veneered cupboards and skirtings but, unlike the floors which were protected with coverings to enable workmen to pass over, the veneered surfaces were not so protected. It should be appreciated that many of the windows are large and let in a substantial amount of natural light.
146.    In the General Chronology, I refer to some of the history as to the discovery of the perceived problem. This began to emerge mostly in June 2007 and, initially, there was complaint and concern that the Mackays had not been advised or warned that either wood generally fades or that ABW not only fades but also somewhat changes colour. Mrs Mackay thought that it was going yellow (although later she and her husband were to refer to it as orange). When she reported this to Sonya Hammond by e-mail on 25 June 2007, the latter’s response was that “the veneer will change in colour as it ages and is exposed to light”; she suggested that it would be possible to “stain it to any shade you find more agreeable if you prefer”. Mrs Mackay’s response later that evening was somewhat abrupt but she emphasised that she would have expected BLDA to “have spotted the problem anyway and asked for a solution on our behalf”. Again, this suggests that the reliance of the Mackays in this context was on their architect or possibly interior designer as opposed to WLC or Adams Joinery. The problem continued to be raised in the following walk around meetings. For instance at a meeting on 4 July 2007 Mr Davis of BLDA confirmed “that old timbers will change colour as they age and are exposed to day/sun light”; he said that it “was fortunate that the changing is occurring uniformly across the unit”.
147.    Apart from the colour problem (which was overwhelmingly the main one), as it was perceived by the Mackays to be, there were in places concerns that abutting pieces of skirting showed up as being too dark or non-matching at the joints. This particular problem was addressed by Adams by a polishing technique which significantly improved the look of the affected joints.
148.    As confirmed in a letter dated 4 September 2007 from BLDA to Mr Bardsley of RLB, BLDA instructed WLC to stain the door to the third floor Guest Suite to see whether the client would accept it with a view to staining the remainder of the ABW. This was done.
149.    At a walk-around meeting on 5 September 2007 attended by Mr Mackay but with no representative of WLC present, Mr Mackay complained that the ABW was becoming too orange in colour. There was reference to the fact that Adams had said recently that “the oil walnut will fade in daylight as it does not contain a UV inhibitor as lacquer can”; Adams was reported as saying that the fading problem was “a defect as the specifier should have been aware of this”; they could “re-oil the walnut veneers with the staining, back to the original colour however they will fade again”. It was confirmed that Adams was instructed to stain the door to the Guest Suite as a sample.
150.    A key meeting in this history is that of 19 September 2007 attended by (amongst others) Mr and Mrs Mackay, his assistant (Gemma Tate who was Mr Mackay’s PA), Mr Davis and Ms Hammond of BLDA, Messrs Joyce and Fairweather (of WLC), Bev, and Messrs Bardsley and Bartlett of RLB. The minute states:
“French polished sample Door to Guest Suite – The clients both agreed stained sample is now a much better colour, closer to the expected colour. KF stated that the French polishers used a coloured stain.
GM showed DLD a photo of the back of the walnut sample they approved in [the interior designer’s] offices. The photo showed a sample without a disclaimer label from Adams Joinery (AJ). DLD showed GM a typical Adams Joinery timber sample with their standard disclaimer sticker. This sticker states that the colour of the timber may fade in time. CM stated that even with this information it was not clear enough, they were never informed that the timber would change colour. She asked whether the colour would fade further. SH confirmed that it may fade and might need a re-application. JJ asked whether WL are to proceed with the French polishing works to all walnut veneers. GM said yes and asked about whether various shades of stain are available…”
151.    Mr Joyce and Mr Fairweather were in no doubt at the time and Mr Joyce was unequivocal in evidence that at this meeting Mr Mackay told them to apply stain for the remainder of the veneered wood throughout the house. On the same day, shortly after the meeting, Mr Fairweather e-mailed Adams Joinery in the following terms:
“The sample colour and finish to the guest entrance door has been accepted by the client.
We therefore need to address all the Walnut Danish oil finished joinery to match the sample.”
152.    The minutes of the meeting was circulated to all concerned including Mr and Mrs Mackay on 24 September 2007. They were never challenged. As indicated elsewhere in this judgement, meeting minutes were often challenged by, principally, Mr Mackay.
153.    The staining work throughout the house was done and largely completed over the next 2 to 3 weeks. On 10 October 2007, at another walk-around meeting, no complaint was made as such by Mr and Mrs Mackay that staining work was being done to the veneered surfaces throughout the house. What was minuted at Paragraph 3.07 was as follows:
“As a general note GM expressed strong concern regarding the staining works Adams are undertaking to the American Black Walnut; highlighting how there is significant colour variation from room to room and often the staining is very blotchy. The joints are also darker. GM considered that all these points make the timber unacceptable. WL confirm that the oil seal had not been applied. GM and CM confirm that the samples [sic] doors on the top floor were accepted. CM suggested that Adams makes a sample based on the acceptance which can be referred to within each room which would highlight the variation, and should assist with addressing the issue. JJ to arrange a meeting with French polisher foreman to resolve the issues.”
These minutes strongly suggest that Mr and Mrs Mackay were not objecting to the fact that the staining work was being done throughout the house but more to it being done in a way which was unacceptable. There is also a confirmation that the sample being observed was on the doors on the top floor.
154.    At the next walk-around meeting on 17 October 2007, the following was minuted:
“Adams were staining Her Study joinery at the time of the meeting. The four drawers in the centre had received the sealer oil. WL would like acceptance in terms of the oiled wood before proceeding further. CM confirmed acceptance of the drawers stating that they looked great. The staining of the wood generally was much improved also. Adams showed CM a sample that had been made and was reported to be based on the approved doors on the top floor. CM confirmed acceptance of the sample.”
155.    At another walk-around meeting on 31 October 2007 the following was recorded at paragraph 3.01 of the minutes:
“GM stated that they are not in acceptance any [sic] of the staining works and are anticipating an imminent arrival of report from Trada. GM reported dissatisfaction with variation between the staining which is noticeable within runs. In addition the shadow gaps are too dark relative to the rest of the wood, and the butt joints are too dark. GM reported that grain had been lost in the timber because of the excessive staining and it does not look like a American Black Walnut originally approved. RB [of WLC] reminded GM that WL has undertaken the staining work at GMs request. CF [of BLDA] referred to the previous meeting where CM approved the drawers to Her Study and other samples including the door on the top floor (C.D3.04) and the hand held sample. CM reported that they had subsequently become darker because the French polisher has gone over them again. GM stated that WL are trying to make the best of a bad situation by staining the wood, and are not aware of what is going to occur to the finish long term. GM expressed dissatisfaction with the staining and explained that it has resulted in something which is unacceptable.”
There were no challenges to these parts of the minutes of these October meetings.
156.    The TRADA report commissioned by WLC, dated November 2007 reported that the appearance of the un-stained veneer “was consistent with what we would expect to see in American Black Walnut. There were natural variations in the colour of timber across the grain from a rich dark brown to a lighter orange-brown”. The TRADA expert carried out a detailed inspection throughout the house; he was the view that the use of the Danish Oil was “unlikely to cause” the colour change. He was of the view that the “stain has provided a high quality uniform finish” albeit that “the result of the stained walnut does not match the specified walnut veneer”. He considered the specification in the context of the matching of skirting lengths; by reason of the staining he could not assess whether there were significant variations in the colour or shade of adjacent sections of the skirting boards.
157.    It is clear from documents, in particular those to and from Knowles as disclosed by DMW, that Mr and Mrs Mackay were having detailed advice about the ABW issue. For instance on 21 September 2007 they had a report from an expert at Knowles about the ABW. Interestingly, it is also clear that Knowles attributed all or much of the problem to BLDA, for instance in its letter dated 27 September 2007 to Mr West.
158.    By sometime in December 2007, Mr Mackay was seeking to have the whole of the ABW veneered wood replaced; that was called for in an e-mail from Mr Mackay on 10 December 2007. Mr Bates of WLC replied on 11 December 2007 saying that it had “correctly carried out veneered walnut joinery to the specification and AIs”; he believed that the “issue appears to lie with what aesthetic you perceived you would be getting as to what you have got”. He said that WLC, Adams, BLDA and TRADA all believed that WLC had complied with “the specification in full by installing quality natural materials to a high standard of workmanship”. This belief had been expressed by those four parties. However, Mr and Mrs Mackay clearly believed that the work was defective and, as Mr Mackay said at a meeting on 12 December 2007, either WLC accepted that or he would arrange for work to be undertaken and recover all costs from WLC.
159.    The position of the Mackays from about this time on (and as put forward by them in evidence) was that they did not authorise staining for the whole house at the meeting of 19 September 2007 but only a limited amount of staining within the Guest Suite and that the sample was not the third floor entrance door to it, as had been stained by Adams before that meeting. So far as my findings of fact are concerned, I am totally satisfied that Mr Mackay did positively instruct and ask WLC to stain all the veneer throughout the house and that the sample against which the staining, so to speak, to be measured, was to be that of the entrance door which had been stained by Adams before that meeting for that very purpose. My reasons are as follows:
(a) I found Mr Joyce to be a wholly believable witness generally but particularly on this topic.
(b) The minutes of the meeting are reasonably clear and records this.
(c) Within a very short time after the meeting (on the same morning), Mr Fairweather who was at the meeting was instructing Adams to stain throughout the house. With a client who was known to be difficult and before the minutes had come out, he must have been absolutely clear on what had been said. It is unrealistic to believe that he would have made it up.
(d) The minute was not challenged by either Mr or Mrs Mackay. Since the ABW was something which was close to their hearts, and because they had been concerned in the past about the accuracy of minutes, it is not credible that they did not challenge these minutes if they were inaccurate in this particular regard. BLDA never withdrew or revised the minute.
(e) The later minutes, particularly in October 2007, do not hint at any complaint that staining was being done throughout the house. Again, it is simply not credible that WLC had not been instructed to stain throughout the house. If there was any issue about that, I would have expected it to have been raised in these later October meetings or at the very least in some contemporaneous documents; this did not occur.
(f) Simply, I did not find the evidence particularly of Mr Mackay on this topic credible; he was extremely faltering under cross-examination on the topic, unsurprisingly in one sense because almost all of the contemporaneous documentation, unchallenged by him, undermined what he was saying. Although Mrs Mackay was in some respects a “better” witness than Mr Mackay, I found her evidence on this area of the case particularly unconvincing. It is interesting that on several copies of the October meeting minutes she wrote various notes qualifying what had been minuted. She also did not challenge the 19 September 2007 meeting minutes and her solicitor background would have warned her of the need to challenge the minutes on a topic such as this, close as it was to her heart, if the minute did not clearly recall what was said.
160.    What is clear to me is that Mr and Mrs Mackay were very disappointed in the summer of 2007 that the veneered wood had altered colour from that which they were expecting. BLDA had suggested that staining the wood might well get the wood to the colour which they wanted and with their knowledge and consent the main door to the Guest Suite was stained by Adams to be considered as an appropriate sample. Mr and Mrs Mackay saw that sample and, as the minute of 19 September 2007 indicates, liked what they saw and Mr Mackay expressly and clearly told WLC to go ahead and stain the veneer throughout the house. They found on reflection after the work was done that they did not like it because it took away, in their minds, some or all of the aesthetic qualities which they were looking for.
161.    Another very important factor is that the Mackays, when later in 2008 they instructed Interior Joinery to remove the old stain applied in September and October 2007, obviously approved an even darker stain throughout the house than that which was applied by WLC; this second staining operation has, to an even greater extent than before, covered the more natural look of the ABW. This supports the view that their state of mind back in September 2007 was that a dark stain was to be provided throughout the house because they repeated the mistake (if it was a mistake at all) some 8 months later. Whilst they now believe adamantly that the staining by WLC was a culpable mistake on its part, the mistake, if such it was, was that of the Mackays.
162.    It follows from what was said earlier that I do not consider that WLC had any design responsibility for the selection of ABW in this case. There was no material notification of them that the joinery in general or the selection of the ABW in particular was an aspect of the design which was to be devolved upon WLC. If there was no material design responsibility, there can in logic have been no obligation on the part of WLC via Adams or otherwise to advise the Mackays that the ABW might fade or change colour in time on exposure to natural light. As indicated above, I do not consider in any event that the Mackays were relying on WLC or even Adams for that; to the extent that they were relying on anyone, it was BLDA or Bev. The selection of the ABW and the Danish Oil occurred before there was a sub-contract in law between Adams Joinery and WLC. As rightly accepted by Mr Sears QC for DMW, if there was no overall design liability on the part of WLC in relation to ABW, there was no duty to warn either that it might fade or that if stained it would lose or suffer a reduction in whatever aesthetic quality appealed to the Mackays.
163.    It is suggested that there remain some other defects. One other complaint is that WLC ensured that the feature is an ingrained pattern allying to regulate and/or symmetrically with the result that there was a marked variation in the colour of the ABW from one part of the skirting to another. It is claimed that the ABW is defective because it is not “book matched” (the practice of matching two (or more) wood surfaces, so that two adjoining surfaces mirror each other in appearance, thus giving the impression of an opened book). However, I am satisfied that there was no design/specification requirement for the veneers to be book-matched. On the contrary, the requirement in the specification was for “features and grain pattern aligned regularly and symmetrically” which I am satisfied has been installed. It appeared to be common ground between the experts that what one must do in that situation is one’s “best” with the veneer selected, given that there will be some variations between adjoining bits of veneered surface. BLDA at the time saw what had been carried out and was satisfied that it was in accordance with the specification and amounted to good workmanship. Another point was relating to the filled fixing pin heads; the only relevant evidence on the point is that it was normal practice to face-pin vertical (mitred) joints with lost-head pins, face filled, which is what has been done correctly by WLC.
164.    These relatively minor points in any event have been “lost” or covered over by the re-staining exercise done by Interior Joinery in 2008 which was done as a matter of choice by the Mackays. Mr Zombory Moldovan was critical of the way this work was done in that it was patchy and in places gave a treacly appearance.
165.    An odd feature of DMW’s complaint relating to the ABW is the fact that for over four years since the problems which are now the subject matter of complaint were first raised Mr and Mrs Mackay have not had the work remedied. They are clearly an extremely wealthy couple to whom the cost of putting right (as they see it) of the defective veneer is relatively minor. Mr Mackay suggested that the only reason that they had not was because they did not want to destroy the evidence. That is not an obviously credible explanation because all that they would have had to do (as Mr Mackay must have known) would have been to notify interested parties that they were intending to replace the veneer and give them an opportunity to inspect, photograph and possibly take samples and then gone ahead and done the remedial works. They have lived, apparently happily, in the house since August 2008 with veneered surfaces which they give the impression are extremely upsetting to them. I have the strongest impression that this complaint although nominally worth a substantial six-figure sum in terms of damages as well as contributing, arguably, to critical delay, is and was always perceived, at least by Mr Mackay, as a makeweight complaint.
166.    If there had been any liability on WLC for the ABW, I would have fixed the potential level of damages recovery based on what Mr Zombory-Moldovan and Mr Hunter said in evidence. However, for reasons dealt with elsewhere, I would have allowed nothing by reason of the settlement which DMW reached with the other third parties to the proceedings.
Courtyard Sliding Doors
167.    The primary issue here relates to the extent to which, if at all, WLC was contractually responsible for the design of these large heavy doors. They were each to weigh almost a metric ton and were about 5 m long way and 3 m high.
168.    By November 2004, BLDA of its own initiative had approached Firman and secured a budget quotation for the Courtyard glazing for £128,700 per house. It is clear that from this time onwards BLDA played the major role in determining what the essential elements of the Courtyard Sliding doors should be. Much of this was done in direct consultation with Firman and without the involvement of WLC. For instance, BLDA wrote to Firman on 7 January 2005 referring to a meeting at which Firman had been left “to consider that two of the houses require a one way single sliding door”; BLDA sent a preliminary typical frame section and asked whether the door would be top hung or run on bottom rollers. At a Procurement Meeting between BLDA and WLC on 1 March 2005 BLDA was shown in the “Action” column for this area of work which was to “be a combination of timber and steel, yet to be designed”. Although the Courtyard Sliding doors (identified as Work Package 300) were on WLC’s list attached to their letter of 21 March 2005 to BLDA as potentially being one of the Contractor Design Portion packages (indicated as “Full Design-Subject to SC [sub-contract]”), BLDA confirmed at procurement meetings on 12 April and 3 May 2005 that it was developing the design with Firman.
169.    On 24 February 2005 WLC wrote to SLW with a list of packages in the procurement report which identified the Contractors Designed Portion “status as we understand them”, this being based on the contract preliminaries. Mr McMorrow in this letter said that he had requested BLDA to compile Employers Requirements for future tender package issues to avoid ambiguity. The attached list identified the Courtyard Sliding doors package as “Full Design- Subject to [Sub-Contract]”. WLC was to write again to BLDA on 21 March 2005 with the same list asking BLDA to “check the status” of this list. There was no response.
170.    In May 2005, BLDA issued its specification for “General glazing”, NBS L40, again adapted from the National Building Specification. It is certainly not clear from this document on its face that it was specifically intended to apply to these very substantial Courtyard Sliding doors because the General Scope at Paragraph 100a related materially only to “Window units” which were said to be “double glazed factory sealed units inserted into traditional hardwood/placement windows”. Paragraph 103 did talk about the supplier or installer being responsible for “completing the Design and Detailing of the Works and to provide complete fabrication/installation drawings, full-size rod/shop drawings as appropriate for approval by the Architect”. Much of the rest of this document relates to shower screens and the like.
171.    In late May 2005, it seems that BLDA issued a document entitled “NBS Specification for structural glass assemblies”, referenced NBS H13; there does not appear to have been any formal issue but it was described as “Issued for Tender” on its face. It specifically referred to “Structural Glass Assembly to Courtyard Areas” and to various drawings including 2315/617 and 618. These drawings drawn to a scale of 1:10 provide a substantial amount of detail not only by way of the dimensions. Iroko wood is identified as being required to form the substantial 200 by 80mm framework; the Notes identify that the doors are to be automated; there is specified “continuous galvanised mild steel PFC framework as support for fixed glazed units” and “sliding door track and drive system”. Paragraph 115b specifically refers to those drawings and provides further details such as the finish, the type of glass, the width of cavity, the type of top hung sliding track with bottom floor guide. Paragraph 211a headed “Design” stated:
“Complete the detailed design, in all respects, of the structural Glass assembly (including automated sliding doors) and in accordance with the preliminary design drawings and this specification.
Coordinate detailed design with that for all related work.
Provide complete fabrication drawings/installation drawings for approval.”
172.    Paragraph 760b is however headed “Sliding Doors to Courtyard Areas Are Included in Window Type Z”. This clearly does refer to the two large sliding doors because it also refers “to drawings 2315/617-618 for details.” The track system supplier was identified as Roltrac (with telephone number and e-mail address provided). Other specific detail was provided.
173.    Shortly thereafter, WLC was to invite Firman amongst others to tender for the “design supply and fix of the glazed screens to the courtyards”; it does not appear that this letter was copied to BLDA. So far as technical documents were concerned, the tenderers were sent three BLDA drawings, three location plans and the NBS L40 specification. The BLDA drawings were described as having a “Construction” status and were relatively detailed. It was known at this stage that in the Courtyard garden (that is between the Library and Swimming Pool Courtyard Sliding doors) there was to be some sort of water feature, although the detail was not known. At a site meeting on 28 June 2005 it was reported that this water feature was still to be designed. Firman submitted a hand written quotation on 29 June 2005 “to supply and fix”; Firman indicated that the doors were to be constructed of “Iroko” wood. This was discussed at a meeting between WLC and Firman on 5 July 2005 at which, for instance, the programme and required attendances were discussed. The meeting led to a revision of the price as set out in Firman’s fax letter dated 12 July 2005.
174.    WLC submitted to BLDA its tender report in relation to the four tenderers and recommended that a company called Haran should be awarded the sub-contract; Firman was the third tenderer. It seems that, because BLDA had had extensive contacts direct with it, Firman were asked to re-quote and its new price (on 17 August 2005) came in at about £1000 less than that of Haran. At a Procurement Meeting on 16 August 2005, BLDA expressly made it clear that they would prefer Firman to carry out this work. On 19 August 2005, BLDA issued its formal instruction (AI 145C) to WLC to place “an order with FA Firman for the fabrication, delivery and erection of the courtyards screens in the sum of £117,521.06.” Shortly before, on 10 August 2005, WLC had written to BLDA as follows:
“Further to previous requests, we would appreciate your clarification and definition of those packages that you will require to be undertaken as CDP.
We would also request that you separately identify those packages that are not CDP would require design and development and design coordination by Walter Lilly or their subcontractor(s).
We require your response urgently and by return in order that we can conclude information that has been requested by Gardiner & Theobald in respect of cost recovery”.
There was no response. Mr Joyce, whose evidence I accept, said there was no agreement on the part of WLC to accept responsibility for any discussions which Firman had with BLDA.
175.    Under cover of its letter dated 15 September 2005, WLC sent to Firman its order for Unit C, referenced 1305/SC/0079. The Brief Description of the works was “design, supply and fix the glazed screens to the courtyards to plot C…”. Under “Design”, Paragraph 29 of this order described the “Design Element” as “Development of Design”. The order was signed by both parties at some stage thereafter without amendment.
176.    Thereafter, Firman prepared various working or detailed drawings for approval by BLDA and over the following months there was an exchange of information between BLDA and Firman and BLDA’s requirements were incorporated in such drawings. For instance on 9 November 2005 BLDA on 6 of the drawings marked up in red various changes and in February 2006, Firman re-issued its Drawing P1136-921 as a Revision B identifying that it had been “modified to suit BLDA’s comments dated 30-01-06”. One of these specific requirements of BLDA was that the bead on the outside face of the glazing which was a diagonally sloping one was to be replaced by a square edged one.
177.    In the period between about October 2005 through to about June 2006, BLDA or DMW engaged a Mr Andrew Ewing to design the water feature over the Courtyard; concern was expressed for instance at a site meeting held on 21 March 2006 as to his contractual position. At an earlier stage, WLC had been instructed to engage him but that instruction was expressly withdrawn shortly thereafter. The water feature was designed and developed by BLDA and Mr Ewing without any input from WLC and it was installed by contractors directly employed by DMW or Mr and Mrs Mackay in the period after installation of the Courtyard Sliding doors.
178.    So far as can be ascertained the Courtyard Sliding doors were delivered and fitted by about the end of 2006 (with final cleaning and commissioning in late January 2007) and in broad terms it was not appreciated that there was any problem until early 2008. The Mackays of their own volition had the ceiling access to the track and drive system for the Courtyard Sliding door to the Library in effect filled in for aesthetic reasons. It was in or by April 2008 that it was appreciated by the new Architect that the doors were catching and difficult to open fully. Essentially, Navigant instructed WLC to remedy the problems; WLC took advice from the Building Research Establishment which reported in May and June 2008 and suggested that the use of timber, the weight of the doors and the introduction of a square as opposed to a sloping bead caused or contributed to the problems, and the there were “fundamental design issues”. WLC did not consider that it was responsible for the problems with these doors and did not comply with the Architect’s instruction; the work was omitted on the day of Practical Completion. The Mackays have not had the defects remedied.
179.    The Architectural experts have reached a substantial measure of agreement on this topic. They agree that the Library door can not be opened and the Pool door only with difficulty. The bottom framing member of the doors has deflected (some 10-12mm at its mid-point) causing it to bind on the floor mounted bottom guide pins or otherwise to bind on the floor surface. The brush ceiling strips on the underside of the doors have been adversely affected by these deflections. They agree that the use of a square as opposed to a display or sloping edge detail at the base of the glass is unsatisfactory. They also agree that this as well as the deflection of the framing members are design matters. They do not find that there is any material bad workmanship or the use of non-merchantable materials. They agree also that the location of the doors in a humid environment has been a contributory factor in the propensity of the timber to deflect.
180.    It is therefore necessary to consider to what extent, if at all, WLC assumed design obligations in respect of the Courtyard Sliding doors. There was no and certainly no clear notification by DMW to WLC that the latter was to assume the design responsibility for these doors. As a matter of fact, the key elements of the design, such as the deployment of a wooden (as opposed, say, to a metal) frame, were decided either by BLDA or by BLDA in consultation with Firman before the NBS H13 specification was issued by BLDA to WLC in late May 2005. That document itself as well as the BLDA drawings referred to in it shows that the key design decisions had been taken by BLDA. This specification was only informally issued by BLDA to WLC; it was not accompanied by an instruction on behalf of DMW in effect notifying WLC that it was to assume design responsibility as part of the Contractor Designed Portion in respect of the Courtyard Sliding doors. The Architect’s instruction in August 2005 requiring WLC to place the order with Firman in relation to these doors does not clearly identify that WLC was to assume design responsibility.
181.    The fact that Firman, which was one only of five asked to tender for the Courtyard Sliding doors, had provided some input in late 2004 or early 2005 by way of discussion and interaction with BLDA does not mean that the design as it had developed prior to the production of the specification in late May 2005 was not that of BLDA. As both experts accepted, architects often talk to potential suppliers, sub-contractors or specialist designers at a very early stage to help them develop their design for the particular item of work. BLDA was not to know that Firman would necessarily succeed in securing the eventual sub-contract and, indeed, Firman initially came third in the running. If BLDA wanted somehow to protect itself or indeed its client from any unsuitability or careless advice in what Firman may have proposed in those early initial discussions between the two of them, it could have tried to secure either some warranty from Firman or, even, required Firman to provide some sort of collateral warranty once it did secure the sub-contract.
182.    One therefore needs to consider whether the informal issue of the specification or the Architect’s instruction in August 2005 as a matter of interpretation or implication amounted to a notification by the Employer. In my judgment, it does not for the following reasons:
(a) There is no evidence that the Employer authorised, consciously, by implication or otherwise, BLDA to notify WLC that the CDP provisions should apply to the Courtyard Sliding doors. If anything, there is evidence that BLDA did not either seek or secure such authority, that evidence being the repeated attempts by WLC to obtain clarification from BLDA as to what were or were not to be treated as CDP packages. It is logical to assume that BLDA either raised the issue with DMW or did not raise it. If it raised the issue with DMW and secured approval for the Courtyard Sliding doors package to be treated as a CDP one, I infer that BLDA would have informed WLC; if it did not raise the issue, there is no reason why DMW would have thought that it was necessary to do anything about it.
(b) Certain it is that DMW itself did not notify WLC that the Courtyard Sliding doors package was to be treated as a CDP package.
(c) There was a strong disincentive to BLDA, G&T and DMW not to have notified WLC that the Courtyard Sliding doors and indeed the other packages were to be treated as CDP packages, which was the clear and indeed correct perception that DMW would have to pay additional monies to WLC for the privilege. These sums would have included allowances for additional PI cover as well as specific design co-ordination and design and supervision of the particular sub-contractors, in this case Firman. Throughout 2005, 2006 and indeed 2007, there was a serious pre-occupation on the part of BLDA, G&T and DMW to keep costs down if at all possible, with costs just for Unit C perceived almost to have doubled from the early budgets.
(d) The giving by BLDA of the specification to WLC at the end of May 2005 did not of itself amount to some sort of notification that the Courtyard Sliding doors or “Structural Glass Assembly” document was to be treated as a CDP notification. There is nothing on the face of the document telling WLC that this was to be the case: at best, the specification was simply to be used by WLC to secure tenders from potential sub-contractors.
(e) The specification on any account does not seek to transfer an overall design obligation onto the successful tendering sub-contractor. It requires only “completion” of the “detailed design” but this must be in accordance with BLDA’s design drawings and the specification itself. Thus, the sub-contractor can not for example choose to use a framing material other than wood and it cannot deviate from the detailed dimensions set out on those design drawings. There is a very real practical and engineering difference between completing the detailed design, which simply involves finishing off what has already been (at least in relation to the Courtyard Sliding doors) substantially designed by BLDA, and assuming a full design responsibility for everything associated with such doors. The completion of the detailed design essentially means providing such design detail as is not already contained within BLDA’s design drawings and the specification. BLDA was to retain overall control in any event by the approvals process, which in this case involved active decision taking such as in relation to the glazing beads.
(f) The requirement for a specialist supplier or sub-contractor to provide fabrication or installation drawings is not an overall design function. Such drawings are always taken to mean drawings which enable the supplier or sub-contractor to fabricate or install. An IKEA flat-pack for, say a cupboard (usually) contains an installation drawing which shows how the cupboard can be put together and then fixed to the wall. A fabrication drawing will show the people in the workshop or factory the individual components and for instance their dimensions and how to put the components together.
183.    Much reliance is placed by DMW on the sub-contractual arrangements as between WLC and Firman in that it is asserted that, as Firman was invited by WLC to quote and WLC’s order to Firman was for the “design” supply and fix of the sliding doors, WLC was acting as if it had been notified that it was to assume CDP responsibility for the sliding doors. Strictly speaking, it does not matter what arrangements were made as between WLC and Firman if, as is the case here, there had been no CDP notification to or assumption by WLC of overall design responsibilty. There is no plea of some sort of estoppel, for instance by convention. It is wholly comprehensible however that WLC might wish to protect its position just in case the CDP notification came later (which it did not). Only five weeks before the order to Firman, WLC had written to BLDA asking for clarification generally about what packages were to be subject to CDP status and there had been silence from BLDA about it. The reference to “design” in the invitation and the order is also comprehensible, in contractual terms, as being qualified and explained by the specification which simply calls upon Firman to “complete” the design and, thus, Firman was not being contractually required to design ab initio the sliding doors but, merely, to complete the detailed design in accordance with and subject to the constraints of BLDA’s design.
184.    There was and is no liability on the part of WLC in relation to the problems with the Courtyard Sliding doors. The experts are agreed that the problems were caused by and attributable to what are essentially design deficiencies. The primary deficiency was the use of very heavy wooden frames which deflected under load, in effect causing the doors to put such pressure and load on to the bottom guide channel arrangements that they cannot easily be moved by hand let alone by the motor drive arrangements. The use of the heavy wooden frames was the design decision of BLDA which was a requirement which WLC and Firman had to comply with. As there was no overall design responsibility on WLC in relation to the Courtyard Sliding doors, it is not in breach of contract with regard to the inability of the doors to move readily or at all.
185.    Another causative factor, although not a primary one, was the presence of the finally designed water feature in the Courtyard between the two sliding doors. Whilst it was always known that there would be a water feature, what was not known was the precise nature and dimensions of that feature. In the result, the whole of the Courtyard comprised a flooded or totally immersed courtyard (bar some stepping stone arrangements), with spraying water jets. BLDA’s drawings for the Courtyard Sliding doors do not actually show a water feature at all but instead indicate paving with edge drainage slots. As Mr Zombory-Moldovan has, rightly, said, the immediate presence of water permanently right beside the sliding doors, together with the water jets and splashing caused by them and heavy rain, has increased the amount of moisture. This, he said, also may well have been exacerbated by landscaping and balustrade works above and around the Courtyard (not on any account the responsibility of WLC) and high level works to the Courtyard facades above the sliding doors and Courtyard glazing. The decision by BLDA to replace the sloping glazing beads actually put forward sensibly by Firman with a square one actually led to more moisture being permitted to enter the wooden frames with the result that the bottom members will tend to have distorted more than might otherwise have been the case. As WLC had no overall design responsibility, it is not liable for the consequences, contributory only though they are, in relation to the enhanced level of moisture at or close to these sliding doors.
186.    The problems of lack of or restricted movement have been exacerbated by the lack of maintenance by the Mackays of the motors and mechanisms. Corrosion has been found on the top track of the pool sliding door and that suggests that there has literally been no maintenance of any sort for years. Mr and Mrs Mackay’s design decision to close off any access to the motor assembly for the Library sliding door means that no maintenance can in fact be carried out without creating a major hole in the ceiling of the Library.
187.    If I had decided that there was any liability on the part of WLC, I would have decided that the appropriate, reasonable and proportionate remedial works were limited to the re-use of the existing sliding doors with the doors being adjusted by using the existing adjustable hangers above them together with some minor related work as set out in Paragraphs 17.106 to 17.118 of Mr Zombory-Moldovan’s first report with which, essentially, Mr Josey agreed under cross-examination; Mr Josey accepted that taking out and replacing the doors would not be reasonable, albeit that this was the solution put forward by DMW initially. These adjustments would raise the doors by a sufficient number of millimetres so that in effect the doors would open and close without hindrance. The costs of the adjustment solution are essentially agreed at between £10,000 and £11,000, as opposed to the £95,276 claimed. The eventual settlement agreement between DMW and the third parties also precludes any additional recovery.
Light Wall
188.    The Light Wall is an illuminated glass screen of wall and door panels that extends the length of the Pool room. It is about 2.6m tall and 15m long. It separates the Pool room from the shower, changing and toilet cubicles behind. It was intended to have light beamed via lighting heads fed by fibre optic cables into its interior so that it provided a uniform glow of changing light. The pool screens and doors comprise a composite construction of an outer skin of 6mm thick sand-blasted and acid-etched, toughened glass, a 2mm air-space, a sheet of 3mm thick opal acrylic sheet, a 2mm air space, a 10mm thick sheet of “Prismex”, a 4mm air space, and an inner layer of 6mm thick sand-blasted/etched, toughened glass, and these components are bonded together at their perimeters by the use of a proprietary 2mm thick adhesive tape.  Prismex consists of a clear acrylic panel which has a ‘dot-matrix’ pattern screen printed onto its face.  When light is applied to the edge(s) of the Prismex panel the dot-matrix pattern diffuses light across its face, the evenness of which is dependent on the design of the lighting as well as on the detailed design arrangement of the panel.  Prismex is commonly used for signage, and for architectural features in retail and exhibition design applications. The experts are agreed that the Light Wall was a novel concept for a private house and one with which most builders would have been unfamiliar.
189.     I accept the evidence of Mr Zombory-Moldovan that the Light Wall was an ambitious, innovative and novel concept; this was broadly accepted by Mr Josey.  It is clear that the design as it developed was essentially a prototype; this had not been developed in advance of construction or of WLC being instructed to place the order for it with Firman. This is important because, whoever was responsible for the design, it was developed by a process of trial and error on site (which after four attempts still remained flawed). It is common ground that on any count WLC had no design responsibility for the lighting aspects of the Light Wall; Equation was responsible. The real issues here revolve around the extent, if any, of the design responsibility of WLC for the structure of the Light Wall.
190.    The Light Wall was not mentioned anywhere in the Contract between the parties, albeit that it was identified that there was to be a swimming pool in the basement. It was not mentioned as a separate package as late as March 2005 in WLC’s letter dated 21 March 2005 to BLDA which listed all the packages then known about. Mr Mackay came up with the idea having seen something similar in a restaurant. It is clear that WLC was unaware what was going to be called for in relation to the west end of the swimming pool area until August 2005. There was reference in an internal WLC e-mail dated 23 February 2005, an e-mail dated 24 February 2005 from WLC to SLW and a letter 21 March 2005 from WLC to BLDA against WP301 to a package being classified as ‘Full Design – Subject to SC’ but that package was then being described as “Glass Walkway” which was not apt to describe any Light Wall, which had clearly not in design concept terms begun to emerge at that earlier stage. Glazing was later to be referred to as WP301C.
191.    BLDA produced its Drawings 2353 C/800 and C/801A for the Light Wall on 31 August 2005 on which there was depicted a screen for showers and toilets. They cross-referred to an Elemental Description Schedule dated 31 August 2005 and these were all handed over to WLC shortly afterwards. The Schedule describes the Light wall as comprising:
“Glass screen wall made up of 12 mm white laminated glass, 20 mm void, 10 mm Prismex and 10 mm white laminated glass to rear, all sandwiched into concealed aluminium U-Channel, frameless with concealed fibre optic lighting to top and bottom of screen. Bottom and top U- channel to be drilled with 8mm holes at approximately 800 mm (sic) centres to line with Prismex glass to detail.”
It was to “incorporate “Fibre Optic lighting to Lighting consultants specification” and the “Finish” was to be “White Laminated glass”. It is clear that Prismex was specified or selected by Equation as appears from BLDA’s later e-mail dated 24 October 2007 to Equation.
192.    The Elemental Description Schedule also referred under the column “NBS Ref” against the Light Wall entry to “L40/250”. There is no paragraph 250 as such in the Specification L40, merely a number of paragraphs running from 250a to 250h, all of which appear under the general heading ‘Types of Glazing’. It is accepted that there is nothing in any of them which is obviously referable to the Light Wall. L40 contained at Paragraph 103 “Design and Production Responsibilities” which imposes a number of obligations on the supplier,  including:
“Completing the design and detailing of the works and to provide complete fabrication/installation drawings, full size rod/shop drawings as appropriate for approval by the Architect…
Obtain specialist calculations as part of the completion of the design/detailing, e.g. for submission to other parties and to ensure elements are fit for their purpose. Inform the Architect immediately of any non-conformity…
‘The supplier and/or installer, as appropriate, shall be required to verify the glass specification; including size, thickness, rebate size and edge cover, aspect ratio and mechanical strength in relation to supported edges to ensure fit for purpose…”
193.    It is the clearest inference that over the preceding weeks or possibly several months BLDA and Equation had had discussions between themselves and possibly with specialists to discuss the Light Wall and had reached decisions as to what was at least broadly required. It is likely that BLDA had directly involved Firman because there was later during the tender period direct contact about design and details between them. There is no suggestion that WLC was in any way involved in such investigations.
194.    On 15 September 2005, WLC invited tenderers to tender “for the supply and fit of the glazing” and it is clear that this invitation referred to the “Sub-Contract Tender Enquiry” for glazing which talked about the Sub-Contractor producing “working drawings and quotes to allow for all costs in regard to design development”; the attached “Subcontractor Enquiry Record” refers to various BLDA drawings including C/800 and 801A and to the L40 Specification.
195.    During the tender period there was extensive and direct contact between Firman and BLDA. For instance, on 28 September 2005 Firman sent direct to Diana Grobler of BLDA a proposed detail for discussion; she sent back more details by way of a section, telling Firman that “the top and bottom need to be drilled with holes to allow light to permeate the ‘Prismex’ when the door is in a closed position”. On 26 October 2005, Firman provided a budget price only for the rear glazed wall but said that it could not quote for the front screens as “the detail shown will not work”. It arranged a meeting with BLDA to discuss “an idea which could work”. Following that meeting, Firman submitted a quote on the basis of a sample submitted to BLDA consisting of “aluminium top and [bottom] rails…with [stainless] steel and milled out to allow the light through”. By its tender report dated 24 November 2005, the other tenderer (Haran) having declined to tender because the work was outside its area of specialisation, WLC recommended acceptance of Firman’s quote of 10 November 2005, which had been in very simple form referring briefly to “shower-changing room fixed screens, doors and DIV’s for the sum of £75,650” and “Rear glass wall to shower-changing rooms for the sum of £22,250”. The report referred to Firman having been “working on the design and [Value Engineering] options with BLDA”.
196.    The Elemental Description for the swimming pool was re-issued by BLDA to WLC on 6 January 2006; it still refers in the specification column to “L 40/250”. On 2 February 2006, BLDA issued its instruction AI208C to WLC to “place an order with…Firman for the supply and fitting of the fixed illuminated glazed screens, doors, division panels and rear glass wall to the shower/changing room within the pool area of Plot C”; this was to be “in line and in accordance with” Firman’s quotation effectively of 10 November 2005.
197.    That BLDA was exercising control over the design process relating to the Light Wall is clear from its letter to WLC of 16th February 2006:
“I discussed these screens with the interior designer yesterday and we are trying to arrange a meeting with Equation Lighting on site with Firmans. The earlier that Equation can make is 10 am on 22nd February so I have set it provisionally for their. Can you get Firmans to attend…
It is not clear at the moment how this screen can be supported, and still allow the fibre optics to be placed under the glass. We are looking at possible solutions now, as we are aware that the screening of the pool is imminent.”
198.    WLC’s sub-contract order with Firman was dated 2 March 2006 but it is not wholly clear when Firman accepted it. The order was for the “supply and fit (of) the fixed illuminated glass screens, doors, division panels and rear glass wall to the shower/changing room within the pool area of Plot C”. “WLC’s enquiry dated 15 September 2005 and associated documentation therein” was said to form part of the Order. The Sub-Contract Pre-Order Agreement at Item 29 of Section 3 records that Firman is to be contractually liable for the “development of design”. Item 40 however recorded that architects drawings were needed and that there was “not enough info to be able to start drawings”.
199.    On 8 March 2006, WLC wrote an important letter to BLDA about the design responsibility for the Light Wall:
“With reference to Architect’s Instruction 208C and the appointment of FA Firmans, they have provided a programme for the works…[that] would give a completion date of 1st September 2006. As this extends beyond the extension of time already granted, we require a further extension of time to cover his work.
We confirm that the Architect’s Instruction is for the supply and fitting of the screens, and we would wish to confirm for the avoidance of doubt, that neither Firmans nor Walter Lilly are responsible for the design element of this work…”
There was no reply of any sort to this letter, which suggests that BLDA agreed. That is confirmed by the Manches’ attendance note dated 29 June 2006 at which it was generally accepted “that no work had been procured as a CPD package” (see General Chronology). It is further confirmed by the BLDA handwritten comments on their copy of the letter, which states “scheme still being designed”.
200.    There was a substantial amount of direct contact between Firman (in particular Mr Anderson) and BLDA and Equation over the following months, with details, sketches and other information being exchanged between all three of them. Although often, if not invariably, WLC was copied in, it is clear that WLC was not intended by anyone to be one of the other participants to participate in the process. There is no doubt that Firman produced to and for BLDA a number of drawings and sketches in relation to the Light Wall for perusal, comments and approval by BLDA. There is no doubt that BLDA took an active part in this process and it is clear that Firman sought approvals from BLDA at all stages. An illustration of this is in Firman’s email of 16 June 2006 to BLDA:
“With reference to our drg’s P1136X-930 and 931, sent to you for approvals/comments…which were returned marked up with various comments…
Although these drg’s have been given ‘B’ status, not all of the issues/information had been resolved, some in fact may be impossible to achieve, for example the gap of 2 mm indicated to the top & bottom of the floors, this has already been pointed out several times verbally, doors cannot be loaded onto the floor springs with these tolerances, doors of this type of multiple construction cannot be manufactured within these tolerances, we would also very much doubt, from years of experience within the associated building trades, that the stone finished flooring to these areas can be laid to within 2 mm, bearing in mind this would still only achieve Zero tolerance if it were possible, we therefore feel this problem will need to be resolved by your fibre optic subcontractors, some of the other issues that need answering before we can fully amend our drg’s for construction, manufacture & installation or further approval are as follows:-
1) Confirmation of the RAL colour?
2) Door handles, full details required, these would not be able to be bonded to the edge of the doors as indicated?
3) Metal cover strips to taped edges to the Prismex, this needs to be checked out, if the tape is suitable to accept this idea, etc, not very practical?
4) Full details of the shower controls, that need to be housed in the S/S section that we are to provide, this information was requested verbally several weeks possibly months ago.
5) Finalising the actual fibre optic situation, adaptation etc?
All of the above may not be all of the issues, but are the main ones that come to mind immediately & must be resolved before we can finalise our drg’s & even think of putting into full manufacture, therefore feel that there is not any point in re-issuing our drg’s until we have all the facts resolved, in fact we need the drg’s returned as more a ‘C’ than a ‘B’ status…”
Without witness evidence from BLDA or Firman, it is difficult positively to find that any of the matters complained of by DMW either historically or in the Light Wall as it was left at Practical Completion was the “fault” of BLDA or Firman or both.
201.    BLDA and Equation certainly had the major role in controlling the lighting side of the design. There are numerous e-mails and other communications between it, Equation and a company called Universal Fibre Optics which was assisting in the design of the lighting. Firman played no part in this aspect of the matter but simply did what it was told in relation to accommodating the lighting and fibre optic designs and specifications. It is clear from e-mails in at November 2006 that Universal Fibre Optics identified a risk of what is called scalloping which is an irregular and non-diffuse dispersal of light. In an e-mail dated 13 November 2006 the firm advised BLDA that it would be difficult to avoid or reduce this problem.
202.    By November 2006, the design was sufficiently advanced to enable Firman to manufacture the screens and doors for the Light Wall. There followed over the following 14 months the provision of what the parties have called four “generations” of the Light Wall.
203.    Before considering the history of the First to Fourth Generations of the Light Wall, it will be helpful if I summarise my views as to whether and if so to what extent WLC assumed design responsibility as between it and DMW. I have formed the clearest view that it did not in any or any legally meaningful sense do so. My reasons are as follows:
(a) I repeat (mutatis mutandis) what I said in relation to the Courtyard Sliding doors on the comparable issue. Thus, there was no notification by DMW to WLC about CDP for the Light Wall.
(b) There can on any proper factual analysis be no reliance on WLC’s lists sent to BLDA in February and March 2005 about the status of the packages because at that stage the package which was to become the one under which the Light Wall was to be procured at that stage did not even relate to Light Wall but to a Glass Walkway; the Light Wall does not appear to have been considered then either by WLC or BLDA as something which was or was necessarily to be provided. That came later.
(c) The only oblique way in which it is argued by DMW that a notification of CDP status being transferred was made is on analysis by the reference in the Elemental Description Schedule dated 31 August 2005 issued by BLDA to “L40/250”. It is common ground that there is no part of Paragraph 250 of L40 which is of any material relevance. The argument therefore goes that, as a matter of proper construction of the Elemental Description Schedule, BLDA must have been referring to L40 generally and references to the completion of the detailed design by the sub-contractor. The Elemental Description Schedule was not issued as some sort of instruction or indeed, obviously or at all, as a CDP notification under the Contract. The fact that WLC sought to incorporate L40 in its sub-contract with Firman does not mean that the Elemental Description Schedule is to be treated as a CDP notification.
(d) The need for a clear CDP notification should not be considered to be satisfied if one has to try to scrabble around to find it in documents issued by BLDA, particularly without any evidence from BLDA as to what was intended, and in a document in particular which does not obviously identify the requirement that L40 was to apply as a whole. The Elemental Description is not an instruction, let alone a CDP notification; it is at best a document in which BLDA merely tried to describe the elements which it had in mind for the swimming pool area.
(e) The only real evidence of what BLDA intended is that it did not intend to provide any CDP notification in relation to the Light Wall. Its repeated and what must have been deliberate ignoring of a series of letters from WLC seeking clarification as to design responsibility both in relation to all known packages and specifically to the Light Wall points strongly by inference to BLDA taking a conscious decision not to provide any such notification. The positive knowledge that no such notifications had been made is in the Manches attendance note later in June 2006.
(f) The fact that as such Firman actually did actively participate in the development of the design both before and after AI208C was issued or even that WLC sub-contractually retained Firman to complete or develop the design does not infer or mean that there was an effective or indeed any CDP notification from DMW to WLC.  One must therefore not confuse Firman’s active participation in the design process with WLC’s contractual responsibility to DMW. That active participation is comprehensible simply as a direct and partial direct delegation by BLDA to Firman of a design responsibility which, in contractual terms, completely by-passed WLC.
204.    The First Generation Light Wall was installed in November 2006. There were a significant number of glass breakages. By their letter to WLC dated 16 November 2006, Firman said that:
“We write concerning the Prismex and glass composition for the above.
As you are aware, there have been several panels that have been broken while stored on site that have been subsequently removed…
These breakages however have brought to light a problem which we feel needs to be addressed and that is important from a safety point of view.
Currently the white laminated glass is only adhered to the Prismex by means of a high bond acrylic edged tape to the perimeter; therefore it is not physically laminated to the Prismex material. The glass has no structural strength, its interlayer being the only safety feature therefore acting independently and not as a single component.
In our effort to reach the desired aesthetic appearance this important criteria has been overlooked. We have therefore put a hold on the production of replacements for these panels. There are several options at the moment which we are investigating, one of these involves the direct laminating as mentioned above, and another is the possibility of changing the type of glass being used.…”
205.    The factual evidence suggests that the panels lacked structural strength and stability. This was clearly a design deficiency which was inherent in the design as developed as between Firman and BLDA and as approved by BLDA. There was no criticism by the Design Team of Firman. Indeed it was discussed at a Site Meeting on 28 November 2006 with a minute recording:
“JJ [Mr Joyce of WLC] advised that they are experiencing problems with these special glass sandwich panels forming the edge lit screen wall at the rear face of the pool area in Plot C. The glass was proving to be more fragile than expected and some units had broken while being handled the delivery to the site. JJ stated that Firmans were not ultimately responsible for the design of the glass sandwich – its design being mostly driven by the requirements of the lighting designer. He stated that there may have to be extra payment to cover the cost of developing the design further. A meeting has been arranged between BLDA/Firmans/WL on Thursday 11th to resolve this issue. BLDA may want the glass element of the design checked by Malishev Wilson when an alternative solution is available…”
Malishev Wilson were the designers retained by DMW to design the glass lift. These minutes were drafted by BLDA and there was no challenge to the assertion that Firman was not responsible ultimately for the design. Indeed, when on 14 December 2006 when WLC submitted to BLDA an extension notification in relation to the consequences of resolving the problems with breakages, BLDA did not respond in any way to the effect that the breakages problems were the fault of WLC.
206.    Mr Zombory-Moldovan suggested that the omission of top and bottom clamping sections, called for by BLDA in the previous exchanges between BLDA and Firman, might have had an effect on the fragility of the glass and that the inclusion of the clamping sections would have increased stiffness of the panels and therefore increased their structural integrity as a composite unit benefiting also from greater stiffness of its layers acting together. However, he also said that whether this “would have entirely prevented breakages” cannot now be known for certain. I am satisfied that his evidence on this is helpful and logical and it must follow that the provision of clamping top and bottom would have been bound to assist at least somewhat in the greater rigidity of the screen or door structure.
207.    Whatever the cause or causes of the breakages, it is clear that it was or they were attributable to design deficiencies; there is no suggestion of bad workmanship or badly manufactured materials. Essentially, the problem was that, as designed, the units were not buildable in that they could not be manhandled without breakages and that is essentially a design deficiency for which WLC is not responsible.
208.    The First Generation units had to be taken back to Firman’s workshops and the Second Generation re-designed and manufactured. The Second Generation Light Wall was installed in February 2007. It was an alternative composite panel design which employed sandblasted, toughened glass instead of the white laminated specification. Firman was actively involved in this design process, although it is clear that BLDA was actively involved in considering and approving what Firman put forward. The changes were in relation to the structure and composition of the wall itself. A 1.2 metre high sample was produced by Firman on about 11 January 2007 and approved by BLDA and Janine Stone (albeit not by Mr Mackay, who was not present at the inspection) on 12 January 2007. In reliance on that approval, WLC told Firman to go ahead with the manufacture of the Second Generation. The new Light Wall was then put into production on the basis of what had been approved.
209.    Once installed, the new Light Wall was found to lack the obscurity required by Mr and Mrs Mackay. In other words, it was not considered sufficiently opaque to obscure the showers, toilets and changing rooms which were located behind. The problem seems to have become apparent when some temporary  illumination was provided behind the Light Wall. The actual or perceived lack of obscurity or lack of opacity was, if anything, a fundamental design flaw.  The functions of the rooms behind had been known since the outset, and had long been identified on the Architect’s drawings for the area. Therefore, it was or should have been obvious that the screen would have to provide sufficient obscurity for the rooms behind.
210.    The degree of opacity required was in a very real sense however a matter for BLDA to decide. Obviously, if the Light Wall was completely transparent so that people within the changing or other rooms could be clearly seen, one would have no difficulty in attributing blame to the designer. However, there was sandblasting of the glass and there was the Prismex within the sandwich of the units which would inevitably have provided a degree of obscurity. The degree of obscurity was very much within the purview of BLDA as opposed to Firman.
211.    Bev suggested in an e-mail dated 12 February 2007 to BLDA that there had been talk of a 4mm opal or opaque sheet within the Light Wall panels. On 15 February 2006, BLDA told WLC to suspend work on-site on the Light Wall and on 19 February 2007 WLC wrote to BLDA asking for further instructions and an extension of time to cover the suspension. On 16 February 2006, there was a meeting between Equation and BRDA upon which Mr Leddra of Firman “stumbled” (as he put it in an email dated 17 February 2006 to WLC) on Mr Bourke of BLDA and two Equation representatives experimenting with different types of opal acrylic to achieve greater obscurity. At the site meeting on 20 February 2007, WLC repeated that they were awaiting instructions and were told that, although BLDA, Equation and Bev had agreed on the remedial actions, they were waiting for these to be approved by the clients. On 28 February 2007 at a meeting attended by the Mackays, BLDA, Equation and Bev, Mr Mackay indicated that the proposed opal perspex interlayer was not approved and Mr Lloyd Davis indicated that other interlayers of varying opacity would be tried out and offered for approval. There was also discussion about how the application of silk within the construction would spread the fibre-optic plumes of light. At a site meeting on 6 March 2007, Mr Lloyd Davis indicated that a report had been received from a company called Light Lab procured by Mr Mackay and he had responded to Mr Mackay. He indicated that there was still disagreement about opacity although a perspex had been selected; WLC asked in effect instructions to undertake works in this context and Mr Lloyd Davis would establish what the financial consequences would be. A full height sample would be required to review and approve and WLC would arrange this once instructed to do so.
212.    On 7 March and 4 April 2007 Knowles wrote to WLC saying that some £75,000 amongst other sums would be withheld against the next money certificates in relation to what was said today the “defective” glazed screen in the pool area. There was silence from BLDA as to whether WLC was in any way to blame.
213.    On or about 11 April 2007, WLC was told by BLDA that a particular perspex sample had been selected and the following day told Firman about this and asked it to produce a full height sample. The sample was provided and on or about 17 April 2007 approved by Mr Mackay. Firman was required to remove the glass screens and manufacture again. On 18 April 2006, WLC wrote:
“We have agreed to remove the glass units from site and return them to the factory to undertake additional works to the screens by introducing a Perspex interlayer [without a film] all in accordance with approved sample GS 412. There was a suggestion that these works should be undertaken on site and although this is possible for reasons of quality, availability of space and expediency they must be undertaken in their factory. We have however been asked, and have instructed Firmans accordingly, to undertake a full-size sample on site which will be available for inspection for 25 April 2007.”
The full size sample was installed on site on 25 April 2007 and on 26 April 2007. BLDA issued its AI441C instructing WLC/Firman to proceed with the rectification works to the pool screens. Although the AI was initially issued in accordance with Clause 8 of the Contract, it was subsequently re-issued (as AI455C) on 11 May 2007 under Clause 13 (as a variation) after complaint was made by WLC. This strongly suggests that BLDA did not believe that WLC was in any way to blame. Another instruction, AI452C, instructed the installation of stainless steel angles to cover holding the glass screens.
214.    A telling internal BLDA e-mail was written by Mr Bourke to Mr Lloyd Davis on 2 May 2007, which was prefaced with the words: “the whole thread of design responsibility is a complete mess”. He went on to say that the “Equation drawings were useless as construction drawings” and that “BLDA have had to shoulder almost all of the design coordination with picking up all of the detailed design that nobody else would touch”. He described what Firman had tendered for a “prototype”. He attributed blame (“joint and several liability”) to BLDA, Janine Stone and Equation for approving the less opaque sample. He referred to WLC as “retracting any design liability at every point” and that “something as novel and complex as this [was] bound to take a wrong turn somewhere”. He “fully admit[ted] [this] could probably have increased our exposure to liability…but I believe that it was the only way of moving the design forward to a stage where we have an overall design effect capable of satisfying the client”. He said that the “interjections by Bev et al have only served to completely stifle the design process”. He went on to say that Firman had a “strong case” for the suggested extra cost of about £29,000.
215.    Thereafter, work began on the Third Generation. By an email dated 26 May 2007, Firman informed WLC that they were “currently splitting and re-assembling the screens” which were “scheduled to be fitted during week commencing 11 June”. Reinstallation did indeed commence as planned on 11 June 2007. However, soon afterwards, on 22 June 2007, BLDA instructed WLC to stop the installation because there was still visible “scalloping” of the lights; this was a non-diffused effect rather than a general spread of light throughout the screen. BLDA asked Firman to experiment with a different tape and diffusion silk to see whether they could improve the spread of light; three Firman operatives would work on the experimentation. The period of experimentation took about 5 weeks. On 26 July 2007, Mr Mackay at a walk around meeting said that the outstanding works to the Light Wall were required to rectify a defect for which WLC was responsible. The minutes do not suggest that any of the design team voiced agreement. On 30 July 2007, BLDA issued a further AI490C instructing WLC to set the glazed screens 2 mm clear of the light source and to stick the silk strips to the bottom and top edges of the Prismex panels. The instruction also required that fascia panels were to be applied along the top and bottom of the entire glass screen in order to obscure the worst of the “flaring” (which is otherwise “scalloping”).
216.    All this work took until about 21 September 2007, although some of the time was taken up because Firman employees had by this stage holiday commitments in August. Meanwhile, there had been an adjudication decision in which the adjudicator, Mr Tate, decided on 30 July 2007 that DMW had had no justification for withholding moneys against certified sums in relation to the Light Wall. By 27 September 2007, Knowles who had been in the forefront of advising Mr Mackay that sums could and should be deducted from WLC’s certificates up to that point advised DMW that BLDA was in breach of contract in relation to the design of the Light Wall.
217.    At about this time, it became apparent that there were blemishes visible in the glass screens. In order to establish the cause of these suggested blemishes Firman returned one of the glazed screens to their off site facility in order that it could be disassembled and inspected.  This revealed only a limited number of blemishes on the front acid etches surface and these marks were able to be removed using a weak hydrofluoric acid solution.  There were, however, concerns that the Prismex itself had a number of scratches beyond what was considered to be acceptable tolerances.  Firman wrote to WLC on 16 October 2006 following a visit to a specialist fabricator of the Prismex and reported that it had “a dot matrix pattern screen printed onto the surfaces” and that “due to the very nature of this product it cannot be guaranteed to be free from defects and discrepancies”; this was contained in an extract from the selling specification. To the naked eye, it wrote, panels would be acceptable and in accordance with the specification but if one lit each and every individual panel only two or three out of 18 panels would be acceptable; another problem was noted to be the need to remove a low tack film from each side of the Prismex which could lead to handling marks. It is clear that there were also some scratches which were unavoidably caused during the two additional re-fabrication exercises involved in the Second and Third Generation work because the panels had to be disassembled and the Prismex removed and then re-placed within the assembly. Mr Zombory-Moldovan said that these scratches were effectively unavoidable even if the work in the workshop was done with reasonable care. I accept that evidence as logical.
218.    Firman suggested that the opal acrylic layer previously inserted should be reversed to sit on the side of the Prismex that was facing out towards the swimming pool in order to better obscure the blemishes evident.  This suggestion, however, was not accepted and new Prismex panels were subsequently manufactured and supplied to Firman for insertion into the glazed screens.  Following an instruction (AI455C) from BLDA, this required, once again, the glazed screens to be returned to Firman’s off site facility, disassembled and re-assembled with the new Prismex panel.  This followed Firman’s assembly of a single panel for inspection, testing and approval by BLDA and Equation. The re-manufactured (Fourth Generation) screens were then installed between mid-December 2007 and late January 2008.
219.    By 6 February 2008, colour variations were identified in these Fourth Generation fixed glazed screens and doors with some panels appearing darker than others. Mr Bourke of BLDA indicated in an internal e-mail of 28 January 2008 that it was the responsibility of Equation. There was an exchange of e-mails on 6 February 2008 between Mr Mackay and Mr Howie with the former accusing the latter of lying, perpetrating a scam and trying to get him to pay for his incompetence when Mr Howie had suggested that the problems were attributable to design problems. Mr Mackay ended up by saying that he was “catching up with your tactics and believe me I am a fearsome adversary when I want to be. In fact I want you out of my and my families’ [sic] life and the idea of curtailing this is very tempting but I am determined to not let you get away with it.”
220.    It is apparent that there were a number of possible factors which could have caused or contributed to this colour variation, including the amount and consistency of light passing into the glazed screens from the point-sources specified and the de-bonding of the adhesive edge tape between the Prismex and the glass layers of the composite glazed panel construction.  The Architectural Experts agree that the de-bonding occurs as a consequence of flexing of the panels and the action of the doors.
221.    On 5 March 2008 and shortly before they were dismissed by DMW, BLDA wrote to WLC highlighting the problems with the tape, the insufficient rigidity and the colour variation. WLC’s position was that it had complied with its contractual obligations and the various Architect’s instructions issued to them and that the problems were attributable to design deficiencies. WLC commissioned a specialist glazing consultant, Mr Colvin, to report which appeared on 1 April 2008.
222.    Following this, there was essentially a stalemate between the parties with WLC claiming that a substantial extension of time was due. The new Architect, Navigant, was of the view that the Light Wall was defective and instructed WLC to rectify. WLC was not prepared to do so as it considered that it was not liable. Correspondence went to and fro with no resolution. On 15 July 2008, Mr Howie of WLC had a meeting with Navigant at which the latter indicated that the Light Wall “would be taken out of contract”; it was agreed that the problems raised design issues. Mr Mackay however decided that, amongst other things, the Light Wall should not be omitted, that being communicated by Navigant’s letter dated 21 July 2008 to WLC. Notwithstanding this, it was omitted on 14 August 2008, since when no remedial work has been done.
223.    There are essentially four defects said still to exist in the Light Wall, that the Light Wall lacks rigidity and doors flex more than they should, that there is de-bonding of the adhesive tape between glass and acrylic layers, that certain cover plates are missing and that there is inadequate access to light fittings behind the glass cladding of the rear walls within the shower rooms. The Architectural experts agree that the first two are design matters. The fourth allegation is essentially also one of design. As for the absence of cover plates, it is likely that the WLC delivered such plates to site for installation but they were not installed; Mr Zombory-Moldovan has seen that two of them have been used on site elsewhere. It seems that the absence of the cover plates is likely to be an incomplete part of the work rather than a defect as such (and indeed is pleaded as such by DMW); the evidence suggests that the cover plates were not fitted pending an instruction from the Architect in relation to waterproofing of the floor spring boxes and mechanisms, which meant that the work could not be completed.
224.    I am satisfied that there was and is no liability on the part of WLC in relation to the defects which are said to exist. Insofar as they involve design deficiencies (as they mostly do), for the reasons given above, there was no relevant contractual design responsibility imposed on WLC. There is a complaint relating to the access to the lighting in the rear walls which is that WLC should have warned DMW about the potential problem; if however there was no design obligation, there was no duty to warn about a potential design deficiency; indeed I accept Mr Zombory-Moldavan’s evidence that a warning was not required in circumstances in which BLDA had made it clear that they wanted a smooth flush backlit glass across the entire wall face which access panels would have interrupted and in any event access could have been provided for what he terms long-life service elements by removing the relevant glass panel. In relation to the cover plates, DMW by its architect omitting the work relating to the Light Wall, has effectively omitted the obligation to complete and therefore WLC has no obligation to complete this work and was not in breach of contract prior to the omission because it was awaiting instructions from BLDA in relation to some necessary prior work which had to be done before the cover plates were fitted. This is in any event a very minor item.
225.    It also follows from the above that WLC was not to blame for any delays associated with the development through its Four Generations of the Light Wall. All the problems were associated with design deficiencies or with the need of BLDA and Equation to develop the design of this prototype development as it went along. That process involved trial and error and the errors, if they can be so classified, were in the design for which WLC had assumed no contractual responsibility to DMW. There is no liability for damages and, even if there was, DMW has been compensated for it under its Settlement Agreement with the third parties (see below).
The Lift
226.    Unlike the three preceding topics, the lift issues only relate to delay. Neither party contends that any delay began to affect overall progress until 2007. There is no real issue that WLC was responsible for the design which was designed by Malishev Wilson who were specialist engineers in relation to the lift shaft and by others for the lift itself , retained by SLW on behalf of DMW in November 2004.
227.    The lift shaft enclosure is a prominent architectural feature within the house. It runs up through the centre of the property from the basement to the third floor. The lift shaft was to comprise a self-supporting structure, detached from the main staircase that surrounded it on three sides. It was to be formed largely of glass and to house a glass lift. The quality of its design and construction was hoped to be commensurate with the high quality required of the house as a whole. The lift shaft is 1.7 m wide by 2.35 m deep and 20.32 m high. The specification required that the glass panels carry the vertical load of the enclosure, with the steel frame providing lateral stability.
228.    The Specification prepared by the Engineers required the contractor to provide fabrication drawings (shop drawings). The intention thus appeared to be that the engineers would prepare the design in full from which the specialist contractor was then required to prepare component part drawings so that they could be machined and prepared for assembly. The glass was to be glazed into the structural openings formed in the stainless steel using black silicone sealant manufactured by Tremco. The width of the glazing was about 8mm on each side. The frame supporting the glass was 50 x 50 x 3, so the width of the glazing channel was 44mm. The thickness of the glass was 28mm, leaving 8mm on either side for silicone sealant glazing compound. Much of the glass was simply silicone bonded into the main structural openings. The connections between framing members where of bolted construction. The main horizontal frame was a rectangular ring beam of flat steel 131 mm wide by 20 mm thick. It had welded corners and would have had to be lifted into position as a single component. The vertical components all came in prepared lengths that enabled them to be lifted and fixed individually. There were two joints at each corner (one between the lower vertical and the ring beam and one between the ring beam and the upper vertical).
229.    The lift shaft was substantially complete and handed over to the lift installer in about late June 2006, although there continued to be a number of issues relating to the quality of the work. Some issues were highlighted in BLDA’s letter dated 26 September to WLC such as the finishing of the shaft and metal work which was addressed by WLC and its sub-contractor and agreed to be satisfactory by BLDA. These issues however, broadly, seem to have been resolved before the end of 2006.
230.    By the end of 2006 DMW had retained Knowles and embarked upon its strategy of seeking to omit numerous items of work, to have Knowles control and oversee particularly BLDA and to pressurise WLC. It is clear that at about that time Mr Mackay believed that the lift provided, architecturally, was a “monstrosity”, as he was to write later in an e-mail dated 4 May 2007 from him to the other directors of DMW and Knowles; he had completely forgotten about this and when he gave evidence he gave contrary evidence. It is clear that he was very unhappy generally about the lift. The same can be said about Mrs Mackay who wrote in an e-mail dated 11 February 2007:
 “Another disaster is the specially designed lift. It is also poorly finished, with rubber showing through unevenly, the stainless steel edges have been filed down to get them to meet, rather ineptly, you can see the fabric of the building through the lift glass and right down the shaft of the unfinished bottom. How could these issues be dealt with?…”
231.    It was in February 2007 that further specific issues were raised following the completion of the lift itself and the removal of protective coverings on the lift. SLW wrote to Mr Bates of WLC on 21 February 2007 saying, amongst other things, “the quality of the stainless steel installation to the glass lift shaft, particularly in Plot C, is unsatisfactory”. Haran Glass, WLC’s subcontractor for the lift shaft, had gone into liquidation shortly after mid-February 2007 and various relatively minor defects were noted at a client meeting on 26 February 2007.
232.    On 1 March 2007, Malishev Wilson sent an email to WLC making further complaints about the lift shaft, saying;
“… In our specification we asked for bow in glass tolerances of + or – 2 mm. Some of the glass panels observed were not complying with this requirement. We believe that the bow is not due to the loading but fabrication or installation fault. Strictly speaking these panels should be replaced.
We have observed that some of the csk bolts were not done properly which may compromise the strength or rigidity of the steel frame especially under temporary conditions (when the glass panel is being replaced).…
Structural silicone application around the perimeter of the panels appears to be of low visual quality and is subject to Architect’s approval…”
233.    On 2 March 2007 BLDA wrote to WLC stating that during a site inspection on 27 February 2007 “it became apparent that there are certain defects to the glazed lift shaft”. As a result, BLDA indicated that the enclosed interim certificate had been adjusted to take into account this defect; the total amount which otherwise would have been allowed for the glazed lift shaft would have been £133,697.39. On 6 March 2007 a meeting was held to discuss snagging and outstanding works to all three properties The meeting was attended by BLDA, WLC, and G&T (amongst others); BLDA highlighted the following three main issues with the lift shaft, namely, grinding of joints (worse on the landings), poor quality of mastic with silvery lines caused by light “diffracting” and glass bowing. It was however reported that Mr Malishev considered that the shaft was generally fit for purpose and compliant with the specification. On 7 March 2007 Knowles wrote to WLC saying that the full value of the lift work, £133,697, would be withheld by DMW. This was clearly an aggressive move, which was probably unjustified given both that Mr Malishev considered that the lift was broadly compliant with the specification and that there had already been a reduction within the interim certificate for what BLDA and G&T believed was appropriate for the perceived lift defects.
234.    After 14 March 2007 BLDA issued a snagging report (wrongly dated 14 February 2007) which was sent by email to WLC on 19 March 2007.  Noted defects in the lift glass had been circled and the marks transcribed on to a series of site sketches of each panel which were attached to the report. Amongst other things, it was noted in the report that:
i)     A 2m straight edge laid against the side of the corner stainless steel box sections indicated that the corner RHS could be as much as 2-3 mm out of vertical;
ii)    There was misalignment of some junctions and the linishing (grinding/polishing) had led to a noticeable dip on some of the joints;
iii)    Several glass panels were found to have a “pronounced bow outwards”. BLDA recorded 4 mm of outwards bow as a difference of level compared to the adjacent RHS box section;
iv)    Large runs of the sealant on most of the panels were exhibiting silver streaking visible through the edge of the glass, indicating that the black sealant was not fully contacting the edges of the glass nor penetrating the V of the edge of the PVB interlayer. The result was that the edge of the panel was made to look uneven thereby detracting from the visual effect of the shaft;
v)    Scratches on the inside and outside of the glass panels; and
vi)    Loose screws and a problem with the bulkhead at the top of the lift shaft.
235.    At a meeting between Mr and Mrs Mackay, G&T and BLDA on 15 March 2007 Mr Lloyd Davis reported that WLC had been asked to put forward proposals to deal with the problems. WLC had instructed a subcontractor to improve the mastic joints and reported that the glass scratches could be polished out; WLC had suggested that a capping on the uprights might be a solution. Mr Mackay indicated that he had ordered a survey of the lift shaft for verticality and alignment.
236.    There was a progress meeting on 20 March 2007 at which WLC reported that the results of its survey would show that the lift shaft was built within vertical tolerance. WLC agreed that the silvering/refraction problems with the mastic sealant were unsightly and also agreed to polish out any non-compliant scratches on the outside surfaces of the glass.  WLC also stated that it was considering methods of covering the steel structure with capping. It was accepted that there was a bolted connection at the top of the shaft which was not satisfactory and that it would correct this. It was also reported that WLC had investigated and considered the mechanics of taking out the entire lift shaft and that this would take between 6 to 9 months. WLC would not accept liability for the cost or time involved with this. Mr Mackay was to comment by email dated 12 April 2007 that the capping proposal had some potential.
237.    By its letter dated 30 March 2007 to Knowles, WLC, addressing the substantial withholding of moneys by DMW, accepted that the mastic was not of the required standard and said that they were ‘taking measures to address this deficiency.’ It is also clear that WLC accepted responsibility for the scratches on the lift shaft and for the bowing of the glass. Essentially, WLC made clear that it considered that the withholding of the entirety of the G&T valuation for the glazed lift shaft, which assumed that it had no value whatsoever, was “clearly incorrect”.
238.    In March, April and May 2007, WLC arranged for its various subcontractors to carry out much of the remedial work. As reported at a walk around meeting on 23 April 2007, the bowed glazed panels had been replaced and the scratches on the outside of the lift shaft had been polished. The stainless steel trims had been inspected by BLDA and found to be acceptable as complying with the specification as had the joint couplers. There was an issue between the parties in relation to the mastic; although WLC accepted that the mastic exhibited a “mirroring effect” which was neither aesthetically pleasing nor accepted by the Mackays and that some of the mastic was of a poor standard, it believed that the silvering or mirroring effect was essentially an unavoidable design problem attributed at least in part to the impact of the use of glass.  This was recorded in a report dated April 2007 from WLC who had also brought in the Glass and Glazing Federation to report. The works which WLC accepted responsibility for were mostly put right in the first half of May 2007.
239.    The minutes of the Client Site Walk Around meeting on 23 April 2007 recorded (at Item 3.04) that:
“WLC confirmed that the bowed glazed panels have been replaced and that the scratches on the outside of the shaft had been polished. GM stated he is interested in pursuing the bronze capping option as now that the interior design of the house has progressed there is more bronze than stainless steel.…”
The reference to the “bronze capping option” was a reference to a proposal which WLC had made to over-clad the corners of the lift so as to conceal both the joints and also the mastic. WLC had commissioned further samples of over-cladding for the box sections so as to conceal the mastic joint. At that stage, WLC was seeking a formal instruction acknowledging the time and cost implications of executing the works and the proposal was not therefore pursued.
240.    On 10 May 2007 Knowles issued a further withholding notice and made the following comments in relation to the lift shaft:
“The glazing, alloy trims, joint couplers and mastic seals are defective. The glazed shaft has been valued by the QS at nil in the present Valuation and their recommendation for payment is nil, hence there are no monies withheld again in this notice but emphasise, for clarity, herein that the lift shaft is considered defective by your employer and no monies be paid to you in respect of this element.”
It is clear that, as DMW and BLDA knew even if not Knowles, much of these complaints had been attended to effectively by WLC. Another similar notice was served on 1 June 2007. On 6 June 2007, there was a Client Site Walk Around meeting at which Mr Mackay is reported to have said that “he had had the lift shaft surveyed for verticality and it was found to be within tolerance”. He said that he would accept bronze capping. WLC subsequently wrote to BLDA on 11 June 2007 stating that, in response to the notice of withholding, it “had carried out a detailed dimensional survey, which had proved that the Lift Enclosure was fully compliant with the Contract Specifications” and that the survey had been copied to BLDA by e-mail on 4 May 2007 but no response had been forthcoming. It must have become apparent by then if not before that the total replacement of the lift and lift shaft was simply not going to be required.
241.    BLDA replied on 14 June 2007 stating that that the issue of the verticality of the lift shaft appeared to have been resolved and suggested that “this matter has now blown up out of all proportion”.  However, there remained a number of areas in dispute, namely, the finish to the stainless steel joints/couplers was said to be unacceptable, the bowing to the glass panels had, it was said, not been satisfactorily resolved and BLDA remained of the view that the mastic was unsightly and that the fixing detail at the head of the lift shaft was unsatisfactory. WLC wrote back on 27 June 2007 substantially disagreeing. WLC’s site diaries record that its sub-contractor, Eagle Mastics, was carrying out some remedial works to the lift shaft between 11 June and 25 July 2007.
242.    BLDA wrote to DMW on 6 July 2007 indicating that scratches had been remedied, and that one of the two glass panels had been rectified. The problem with stainless steel joints could only be overcome by over-cladding. The silvering of the mastic was to be expected but it was patchy; re-masticing had improved the situation. WLC had procured a report from the Building Research Establishment dated 11 July 2007 which concluded that the appearance of the sealant at the glass edge was a consequence of the design.
243.    On 20 June 2007 WLC referred the dispute to adjudication. On 30 July 2007 the Adjudicator issued his decision. He decided that the value of the lift frame should have been included in the previous interim certificate as it was not defective. He found that scratches to the glass had been adequately addressed and any scratches existing on 1 June 2007 were minimal and insufficient to justify withholding of the value of the glazing. He found that the general finish and appearance of the alloy trims and joint couplers was not satisfactory as they were not fixed or cut in accordance with the lift shaft specification; he found that a deduction of £5,000 for this default was reasonable. The surface finish of the mastic joints was generally inconsistent and poor in places and the rear face of the mastic had not been recessed as detailed. Although he accepted the BRE report, he found that £25,000 represented a reasonable sum in relation to what he found was a defective application of the mastic. In total therefore, the adjudicator found that over £100,000 had been wrongfully withheld.
244.    WLC proceeded with some limited further mastic work to the lift shaft but by 5 September 2007, as evidenced by a Client Site Walk around meeting on that date, it was envisaged that WLC would submit a proposal for over cladding. At another such meeting on 12 September 2007 Mr Bates of WLC demonstrated some bronze cladding. On 13 September 2007, WLC made to Mr Mackay a without prejudice proposal with regard to over-cladding. It offered (for free) to over clad the lift enclosure vertical steel hollows with bronze cladding on the basis that neither DMW nor WLC made any claim for delay against the other. It was predicated upon the basis that “irrespective of the standard of finish achieved to the joints, you dislike the general appearance of the exposed mastic and steelwork”. Mr Mackay’s e-mailed response on the same day was the over cladding was in principle acceptable but he wished to preserve his right to liquidated damages.
245.    BLDA wrote to WLC on 18 September 2007 stating that the “major item preventing the issue of a Practical Completion certificate is the fact that the Lift Shaft has still not been built…in accordance with the Contract”. On 28 September 2007 Mr Mackay sent to Mr Bates a draft letter (drafted by Knowles) offering to resolve the matters in issue on the lift. On 2 October 2007, Mr Bates of WLC wrote to Mr Mackay offering that WLC would over-clad the stainless steel frame with bronze metal at its cost, expressly accepting that the works would be carried out in accordance with Clause 8.4.3 of the Contract (and no extension of time would therefore be sought by WLC for those Works). This was agreed to by Mr Mackay and the over-cladding work proceeded.
246.    WLC placed an order with Bassett and Findlay Ltd for this over cladding work on 3 October 2007, a quotation for which had been sought a few days before. As Mr Howie attested, the work commenced on 11 October 2007 and was finally completed on 21 November 2007; most of this was completed by the end of October 2007 but a damaged piece of over-cladding was re-fitted over several days leading up to 21 November 2007. On 26 November 2007, BLDA and Mr Mackay confirmed their acceptance of the over-cladding work.
247.    There was much evidence as to whether the over-cladding work prevented or restricted access to the first and third floors whilst it was going on. By October 2007, the only means of access to the upper floors was by way of the staircase that went around the lift shaft from the ground to the third floors. It is undoubtedly the case that the over-cladding work primarily between about 11 or 12 October and the end of that month did somewhat restrict access but it certainly did not prevent it. Mr Howie and Mr Joyce gave evidence to this effect; Mr Bartlett indicated that artists and tradesmen directly employed by the Mackays were working on the upper floors during this period. The clients and the Design Team were able to get access.
248.    It is strictly speaking unnecessary to decide whether or not WLC was liable for any of the defects which led to the need for the over-cladding. This is because WLC accepted at the time that it would carry out these works at its own costs and as if doing it pursuant to an instruction requiring remedial works under Clause 8.4.2 of the Contract Conditions, which necessarily implies that it was putting right something which was its responsibility; there was to be no extension of time, and indeed it is no part of WLC’s Case or evidence that it was in any way delayed by the need to do the over-cladding work. The agreement to do this simply arose from WLC’s wish to draw a line under the lift issues and, although a significant part of its reasoning was that the over-cladding work resolved aesthetic or design objections which Mr Mackay (for which WLC was not responsible), another part of its reasoning was that there remained some mastic and other workmanship issues which would be difficult to address.
249.    As for the deficiencies, such as mastic, glass scratches, bowing panels and bolt heads, I am satisfied that these were deficiencies in workmanship on the part of WLC and its sub-contractors. However, these were put right mainly in the period up to the adjudication decision and they did not take an enormous amount of time or resources to resolve. It is clear that Mr Mackay either allowed himself or Knowles to exaggerate the extent, impact and scope for the Lift defects but that is consistent with the adopted strategy. A particular and good example is the continued withholding from WLC of a sum representing the total value of the lift and lift shaft works which was not simply unjustified; it was aggressive and it must have been known to Mr Mackay certainly by the adjudication and probably well before that the chances of holding on to the whole of the retained sum was close to nil.
250.    I will address the impact of the lift on delay in the extension of time part of this judgment. 
Barrisol Ceilings
251.    The ceiling finishes to the Pool Hall and the Cinema in the Basement of Plot C incorporated illuminated ceilings which comprised two principal elements, the first of which is an elaborate lighting installation fixed within a recess to the structural soffit of the ground floor above; the intention was to provide diffused light which changed colour on a recurrent basis. The second element is the “Barrisol” ceiling which is fixed below the lighting installation.  A Barrisol ceiling is essentially a suspended ceiling system consisting of two basic components, a perimeter track and lightweight PVC membrane. The aluminium track is first installed to the line and shape that the finished ceiling will take.  Once the track is installed, lined and levelled, the PVC sheet (less than a millimetre thick) is then laid out and heated so that the PVC sheet becomes workable and able to be stretched.  Once the PVC sheet has been sufficiently heated it is then stretched and clipped into the perimeter track. The PVC sheet then cools and tightens into its final shape, tension and consistency. The PVC was about 50 m2 for the swimming pool area and somewhat less for the Cinema.
252.    There is no issue remaining as to whether there are any defects for which WLC remain responsible and no suggestion that WLC was responsible for the design either of the Barrisol ceiling itself or the lighting above it. Equation was responsible for the design of the lighting, which proved to be unsatisfactory or at least not acceptable to Mr and Mrs Mackay. To the extent that it features in the delays, it is only the work to the ceilings in 2007 going into January 2008 that is material.
253.    Because the Barrisol ceilings were regarded as “fine finishes” and susceptible to damage and dirt, it was agreed that this would be installed only after dirty works to the Pool Hall (such as the pool screens, mastic to the drainage channel and stone flooring which remained incomplete in February 2007) had been completed in order to prevent damage to the Barrisol ceiling.  Similarly, it was agreed that the Barrisol ceiling to the Cinema would be installed after the completion of DMW’s directly employed contractors (in particular Sound Ideas) had completed their works.
254.    The Barrisol ceiling to the Cinema was not in the event installed until 24 May 2007 following the completion of the dirty works in that room. Between the date of installation of this Barrisol ceiling to the Cinema and the Client Site Walk Around meeting on 6 June 2007, concern was expressed in relation to the lighting effect of this Barrisol ceiling in that dark lines appeared across the ceiling.  This was due to the configuration of the lights above the Barrisol ceiling.  The Barrisol Ceiling, as instructed, was removed on 20 June 2007 and the lighting re-designed to address the problem.
255.    This concern was also raised at the 6 June 2007 Client Site Walk Around meeting in relation to the gaps between the lighting installed for the Barrisol ceiling to the Pool Hall.  The gaps between the ends of the fluorescent strip lights resulted in dark areas (or lines) running perpendicularly to the direction of the lights. Equation asked WLC to have the Barrisol sub-contractor to hold up a sample so that they could test the lights before the ceiling was put in place. There were problems with Sound Ideas, a firm directly engaged by DMW to supply and install equipment in the ceilings and, as recorded in an e-mail dated 22 June 2007 from WLC to BLDA, it was proposed that Barrisol should not complete their installation until Sound Ideas had adjusted their equipment. This work by Sound Ideas took some time, until about 5 July 2007.
256.    On 9 July 2007, AI478 was issued requiring WLC to remove all lighting fittings and wiring to the cinema ceiling; this involved WLC having its electrical subcontractor, Norstead, do the work; this was changed again by BLDA on 11 July 2007 with changes of position of the light fittings. The Barrisol ceiling in the pool was installed on 20 July 2007. By 26 July 2007, there had been continuing experimentation by WLC with the lighting effects in the pool hall ceiling and there continued to be a striping and shadow effect which was not acceptable to the client. A similar problem in the cinema ceiling was also reported at the Client Site Walk Around meeting on 26 July 2007. On 27 July 2007, BLDA issued AI485C which instructed WLC to request Stretch Ceilings (the installers of the Barrisol Ceiling) to remove the Barrisol ceiling in the Pool Hall. The Barrisol ceiling in the Cinema had already been taken down on 20 June 2007 (pursuant to AIs 492C and 496C) and was reinstalled (although not for the final time) on 28 August 2007. A complaint was made about the Barrisol ceiling material, which was manufactured in certain widths and was therefore jointed at the seams, to the effect that the joints should have been centralised. However as WLC pointed out, in an e-mail to BLDA on 27 July 2007, there had to be joints and there had been no specification as to the position of the jointing; in effect this could not be a valid criticism.
257.    Alterations were required again to the lighting in both the cinema and the pool. In August 2007, BLDA issued variation instructions AIs 485, 486, 491 and 492 as well as those referred to below in relation to the Barrisol ceilings. RLB reported to Knowles on 6 August 2007 that Equation acknowledged this as “their fault” and had “offered to put it right at their cost”. Pursuant to this concession, Equation itself provided six additional fluorescent batons to be installed to the Cinema ceiling and for existing fittings to be relocated to replace six of the fittings. These fittings were still awaited on 15 August 2007. On 16 August 2007 AI498C instructed further lighting revisions to the Pool Hall ceiling. Equation spent the whole week commencing 13th August 2007 on the site seeking with various workmen to resolve shadowing in the pool hall ceiling.  AI513C on 20 September then instructed further changes to the Pool Hall ceiling, changing the lights to LED rather than fluorescent in order to achieve a “twilight” effect.
258.    At the Client Site Walk Around meeting or 5 September 2007, a programme for the additional works to the pool ceiling was identified as being a minimum of six weeks, followed by the need for the ceiling to be inspected before the Barrisol ceiling and was re-fixed. There was no suggestion that this programme was unreasonable. More changes to the lighting were instructed by AI513C dated 20 September 2007 based on a directive received by BLDA on 19 September and revisions to Equation’s design; work on the new free issue lighting had been suspended by Mr Mackay and Equation on 19 September 2007. Between 20 September and 4 October 2007 two types of sample lighting at either end of the swimming pool were installed. On 20 September 2007, WLC made it clear it could not complete the works in the cinema until the ceiling lighting was resolved.
259.    On 10 October 2007, Mr Mackay instructed further alterations to the lighting installation in the pool hall Barrisol ceiling, these being confirmed by WLC in writing on 15 October; a sample of these alterations were inspected on 22 October 2007 and approved by BLDA in AI 526C; this instruction required WLC’s sub-contractor to carry out additional and varied works to the pool hall ceiling using free issue LED lighting provided by Equation. On 7 November 2007, WLC was instructed by RLB in effect to permit the pool ceiling works to be done by a directly employed contractor but this was rescinded. The final work was finished on 26 November 2007 and, the following day, AI547C instructed WLC to prove the new lights by running them for 100 hours over a period of 1 week. This had been done by 5 December 2007. The Barrisol ceiling was fitted again.
260.    At a Client Site Walk Around meeting on 5 December 2007, it was reported that the pool Barrisol ceiling was damaged. At a similar meeting a week later, it was reported that Barrisol did not accept responsibility as all reasonable care was taken when it dismounted and reinstalled the ceiling; it would not place the ceiling without an instruction. AI551 was issued to this effect after the meeting. Barrisol’s position was justified on the basis that the ceiling material had been taken up and down on a number of occasions and it simply and unavoidably got somewhat stretched as a result and that Barrisol had acted with reasonable care. AI552C also issued after the site this meeting on 12 December) instructed Norstead to install the newly specified LED lights to the Cinema. This work was carried out between 8 and 28 January 2008. By about this time the ceilings in both the pool and the cinema so far had been completed, they were demonstrated to and accepted by DMW.
261.    I am satisfied that, whatever the impact on overall progress, the Barrisol ceiling and related electrical works above, in both cinema and pool hall, were materially delayed by late instructions and variations between July 2007 and the end of January 2008. This was mostly attributable to the need constantly to change and adjust the lighting and the lighting configurations; it was unnecessary to decide whose fault this was on DMW’s side but certainly the evidence strongly points to Equation to a large extent. There was never any real suggestion that WLC was responsible for the delays involved in securing completion of these two areas of work.
The Stingray Doors
262.    The Stingray doors were double doors which provided access from the Entrance Hall into the Drawing Room and the Kitchen/Family Room.  The height of the doors is approximately 3.6m. The terminology of ”stingray” doors was used to describe the texture and finish of the doors, which are intended to resemble the skin of a stingray. The stingray finish was to be achieved by first cutting to size 12mm MDF panels which are then faced with bronze cladding.  The bronze cladding was to be sent off site to a company based in Greenwich called Based Upon to be finished with the “stingray finish” which was applied off-site. The finished stingray panels were to be positioned into a brass trim frame fixed to the door blanks.  In order to form the MDF panels it was first necessary for the brass trims and other ironmongery (such as pull handles and ironmongery) to be applied to the door blanks for site measurements to be taken.  The MDF panels were then sent off site to be cut to size before having their stingray finish applied.
263.    There are two areas of issue relating to the Stingray doors, delays and defects. In relation to delays, WLC’s pleaded case is that firstly, following the installation of the Stingray frames and doors between November 2006 and January 2007, delays occurred to the forming of the MDF stingray finished face panels due to the late supply of free issue bronze angles on 13 July 2007 which formed the frames for the MDF stingray panels. Secondly, there was a delayed start between 13 July 2007 and 8 August 2007 of the initial cutting and temporary installation of the door face panels and the bronze angles until all the other components (including the leading edge angles and door handles) had been delivered to Adams, WLC’s sub-contractor. Thirdly, the initial cutting and installation of the door face panels, bronze angles and other components took 6 weeks between 8 August 2007 and 21 September 2007. Fourthly, the period for the off-site application of the Stingray finish to the MDF face panels took 6 weeks between 21 September 2007 and 29 October 2007.  Next, installation of the Stingray finished MDF face panels was delayed due to the late confirmation of an approval sample of the patinated leading edge angle and design of the doorstops between 29 October 2007 and 3 December 2007. The on-site installation of the stingray finished MDF face panels then took 2 weeks between 3 December 2007 and 18 December 2007. Finally, it is said that the installation of the door handles was prolonged following the completion of the stingray finished door panels due to the late supply to WLC of the free issue adhesive required to fix the door handles and back plates by 6 weeks between 18 December 2007 and 25 January 2008.
264.    In March 2006, JSI issued drawings showing the concept design of the doors and a schedule of finishes. A Tender Progress Meeting was held on 19 May 2006. The purpose was to deal with problems with the design and detailing of the doors, so as to allow Adams to fully price the package. In May and June 2006 BLDA provided WLC with tender information for the doors. On 2 June 2006 BLDA issued general layout and door detail drawings for construction. On 6 June 2006 BLDA asked WLC to provide a quote for the door package and the tender documents were sent to Adams, who on 22 June 2006 quoted for the supply and installation of the doors, frames and ironmongery. A 22 week programme from the order was identified by Adams, albeit not as part of its quotation, this being set out in WLC’s tender report; this programme left blank the installation of the ironmongery as “delivery details [are] awaited from Manufacturer”.
265.    On 14 July 2006 BLDA issued an instruction (AI308C) to WLC to place an order with Adams for the “supply and installation of” the doors, frames and ironmongery, including the Stingray doors.  On 19 July 2006, WLC issued a site instruction to Adams to supply and fit the doors, frames and ironmongery. On 21 July 2006, WLC wrote to BLDA with an extension of time notification in effect for the late issue of AI308C saying that the completion date for the Stingray doors based on the late receipt of the instruction was now 11 December 2006. The substance of this letter was never challenged by BLDA.
266.    There remained issues about outstanding information relating to the doors and ironmongery. This was confirmed, for instance at the site meeting held on 25 July 2006 when BLDA confirmed that outstanding elements would be clarified later that day. Throughout August 2006, DMW was deciding whether to arrange for the supply of the ironmongery itself and there was uncertainty as to what the ironmongery would be. This was referred to in WLC’s report for the site meeting on the 22 August 2006 (“Ironmongery to plot C joinery remains unresolved”); the report went on to say that Adams was waiting for approval of certain ironmongery details but that those items were on an extended delivery and that therefore doors would lag well behind the installation of other joinery. At the site meeting on 5 September 2006, it was reported without demur that WLC was “awaiting instruction regarding plot…C ironmongery. Hoffmans has issued spec to [BLDA and SLW]. BLDA to revise instruction.” Hoffmanns (or “HOF”) was to be the supplier. Ironmongery was again reported as something likely to affect progress in WLC’s report for the site meeting a fortnight later. At that meeting, it was minuted that the joinery ironmongery was still to be approved by JSI and the current plan was “for this ironmongery to be post fitted”.
267.    By the site meeting of 3 October 2006, it was confirmed that all door handles were to be omitted; it was at about this time that DMW decided that it would procure all the ironmongery for the Stingray doors. Somewhat later, probably by December 2006, it was resolved by DMW that it would issue such ironmongery to Adams, to fit to these doors. Mr Joyce said in evidence that Adams’ fabrication drawings were “only able to be issued on 16 November 2006” The reason given was “protracted design development and changes to the door panel sizes.” When asked about it in cross examination, Mr Joyce said that he thought the panel sizes changed in size and number but was unable to provide any further detail. When it was put to him that there was little or no documentation evidencing what he was suggesting, and that if it had been causing a significant problem one might have expected to see letters or emails making that known, he only said that “there was a lot going on at this time”. Certainly, there was uncertainty about ironmongery for the Stingray doors, not only as to whether Adams was to procure it but also as to what it was to be.
268.    For reasons within their control, DMW and its Design Team between them were unable to confirm what the specification for the door furniture and handles for these doors would be. As Mr Joyce said in his first Witness Statement (upon which in this respect he was not effectively challenged), WLC could not assemble the Stingray doors without the free issue materials; this was because the ironmongery back plates, bronze angles and brass division strips were required in order to work out the exact length and dimensions of the MDF panels before they could be individually cut and dry fitted before being sent off site for the finish to be applied. This was well understood by BLDA as is evidenced by its internal e-mail of 24 April 2007. The door frames and blanks for both doors were manufactured and installed by 24 January 2007.
269.    On 1 June 2007, WLC wrote to BLDA saying that WLC could not complete the Stingray doors for a number of reasons including:
“Drawing Room & Kitchen main doors client free issue bronze ironmongery and features are still awaited; delivery was expected 21st May. The Works production slot has been missed, and a new time reservation will need to be made but will be longer than that currently advised”.
This was not challenged but someone obviously chased up DMW’s suppliers because some of the ironmongery was delivered by courier on 8 June 2007. Eight of the angles supplied were too short and the bronze division strips were flat and twisted and not what was required by the drawings issued to Adams. The back plates were only delivered to site on 26 July 2007 and the correct brass angles on 16 August 2007. Some changes to the design and shape of the MDF finished panels were instructed by DMW through Janine Stone in July 2007. Whilst the Stingray doors had been designed by BLDA to open in one direction only, Mr Mackay made it clear in mid August that he wished to consider the doors opening both ways; it was only on 22 August 2007 that he indicated that he was prepared to accept the original design intention. Between mid-August and the third week in September 2007, Adams marked up and cut the MDF panels which were to be fixed adjacent to the back plates; these had to be fixed to the door blanks.
270.    The MDF panels were then sent to Based Upon in Greenwich to have the Stingray finish applied which was done by 29 November 2007. The next step was for the finished panels to be permanently installed. However this was delayed because BLDA failed to approve the sample of patination of the leading edge angles until 31 October 2007 and because it was decided by DMW’s design team that doorstops needed to be provided to prevent or limit friction damage to the edges of the hinges to the doors. WLC reported without demur at a Client Site Walk Around meeting on 7 November 2007 that the top panels to the Stingray doors could not be fixed until the door stops were in place. Bev reported that a design had been priced and that once client approval was obtained the manufacturing could commence; he was instructed to issue WLC with the relevant details.
271.    The detail for the door stops was sent to WLC on 15 November 2007 and finally resolved by JSI by 21 November 2007. However, the installation of the panels was still held up because the door stops to be delivered by others were not so delivered until 8 January 2008. However, the Stingray finished MDF panels installation took place between 3 and 18 December 2007. However, the door handles could not be installed because WLC was not issued with the necessary adhesive or the specification of fixing the free issue door handle plates or an elevation showing the door handle heights. This issue was raised at a meeting on 5 December 2007 but the adhesive tape was only finally issued to and received by WLC on 20 December 2007. The installation of the doors could only be completed by 25 January 2008 because the free issue through bolts for the door handles were only delivered finally in January 2008.
272.    I am satisfied that, whatever the impact on overall progress, the Stingray doors work was materially delayed by delayed delivery of free issue ironmongery, late instructions and variations between January 2007 and the end of January 2008. This was mostly attributable to the decision on the part of DMW to procure the ironmongery itself, delays by the Design Team to secure earlier delivery of the ironmongery than was achieved, delays in the provision of information, and changes being made or considered. Again, it is unnecessary to decide whose fault this was on DMW’s side but certainly the evidence strongly points to JSI and DMW’s ironmongery suppliers to a large extent. There was never any real suggestion that WLC was responsible for the delays involved in securing completion of these two doors.
273.    There is a complaint by DMW in its Counterclaim about the finish. The expert architects’ agreement is as follows
“14.1 The bronze finish to the stingray door handles and faceplates is poor and uneven. It is understood that this ironmongery was free issued by DMW to WLC.
14.2 The cause is unclear, but it appears to have occurred prior to Practical Completion.
14.3 The remedial works in relation to the doors will involve taking the doors down and sending down to a patinator/finisher to have the faceplates and handles made good …[and]to have the handles and faceplates removed and sent to a patinator for re-patination.”
A protective film was applied to the units during the works. When the film was removed, it was found that it had contaminated or damaged the bronzed finish of the ironmongery. An unsuccessful attempt was made to clean and re-finish the surface.
274.    DMW’s case in relation to the stingray doors is that parts of the ironmongery are missing (linking strips) and other parts are now loose, that ironmongery was not left clean or in the specified condition and that metal decor strips have come loose or are inadequately fixed. The sum claimed in respect of remedial works is £18,068.12.
275.    HAF was the supplier directly engaged by DMW; patination was required to the ironmongery but for reasons best known to itself HAF was not prepared to do this work at least on site and so it was that AI504C was issued to WLC by BLDA on 7 November 2007 for its sub-contractor, Bassett and Findley, to do this work; this was done a few days later. There was then discussion as to how the door handles and plates were to be affixed. There was a free issue to WLC by HAF of adhesive tape (“Millionaire’s tape”) on 20 December 2007 which was then used by Adams to fix the handles and faceplates. The adhesive when removed seems likely to have left marks on the ironmongery. It seems likely that WLC attempted to remove the marks.
276.    The amount claimed by DMW for this alleged defect is £18,068.12 but the quantum experts’ figures are that for DMW’s remedial work case (removal of doors from site for re-patination £10,060.20 (Mr Pontin)) and £9,355.50 (Mr Hunter) and on WLC’s remedial work case (remove the ironmongery alone for re-patination £3,390.96 (Mr Pontin) and £3,153.43 (Mr Hunter).
277.    DMW originally sought to raise allegations of design as well as workmanship issues against WLC in relation to the Stingray doors.  The former was dropped by amendment but some of the latter remains. The source of the protection tape for the ironmongery was HAF, DMW’s directly employed ironmongery supplier. 
278.    The relevant Specification Z10 which was issued to WLC states with regard to “adhesive generally” that the contractor was to “remove surplus adhesive using methods and materials recommended by the adhesive manufacturer and without damage to affected surfaces”.
279.    Mr Josey said that the tape left adhesive residues on the surface and the resulting attempts to remove them caused damage to the finish. He also said that WLC or Adams Joinery should have obtained and acted on manufacturer’s advice on rectification (which was to remove the plate and return it to the factory for rectification) rather than attempt rectification on-site. Mr and Mrs Mackay both noted in their witness statements that WLC engaged contract cleaners to remove marks left by the removal of the protective material to the bronzework. This cleaning fluid has damaged the finish to the bronzework itself.
280.    On balance, I consider that WLC did fail to exercise appropriate care in seeking to remove the adhesive from the bronze ironmongery, even though it was not its contractual fault that there were adhesive residues left. There is no reason to believe that the adhesive was not removable without damaging the patination. So far as the complaints that parts of the ironmongery are missing (linking strips) and other parts are now loose are concerned, this has simply not been proved. If ironmongery was missing, it must have been because either it was not supplied to WLC to fit or it has been taken off by others, there being no reason why WLC should have removed it. As for loose pieces, this was not noted in 2008 on snagging and it is not possible to say probably what or who caused them to be loose.
281.    As for quantum, I can not accept that the total removal of the doors is either necessary or reasonable. The ironmongery can be removed and taken off site for re-patination and then returned and re-fixed on site. There is little between the quantum experts on this and £3,250 is a fair allowance. However, for reasons dealt with elsewhere, I would have allowed nothing by reason of the settlement which DMW reached with the other third parties to the proceedings. In this particular case, DMW did allocate in the settlement £12,045.41 to the Stingray Doors problem. This by a large percentage exceeds what I would otherwise have awarded in any event.
Leather in the Library
282.    The importance of the issues relating to the Leather in the Library revolve around responsibility for the design of the leather and the extent to which WLC had responsibility for the speed or (or lack of speed) of the requisite sub-contractor, Adams Joinery, in producing samples which were acceptable to the Mackays.  There is a major issue as to whether it caused overall delay.
283.    The supply and installation of the Leather in the Library relates to the lining to the purpose made book shelving units.  The shelving units comprised a 60mm thick MDF construction and lined all around in leather with decorative stitching in order to form an architectural feature of the Library.  It is common ground that the leather lining had to be installed to the joinery components prior to their on-site installation and that until the leather lined joinery had been installed no other joinery could be installed to the Library.  In addition to the library shelves, further leather finishes were required in the Lower Hall lobby walls which were situated in the basement between the Library, the Cinema and the lift shaft.
284.    Mr Mackay stated in his witness statement that it was his idea to clad the library shelving in leather at a relatively early stage in December 2004; it is clear that Bev took a major role in seeking to organise this. He produced various sketches. He produced some photographs in June 2005 showing examples of the stitching detail which the Mackays were happy with and then organised a company called Anthony Vahimis to produce a sample. This sample was produced some time thereafter and again the Mackays were happy with this. There is no suggestion that either WLC or Adams Joinery were involved in any part of this process.
285.    The history relating to the eventual engagement of Adams Joinery (as set out in relation to the ABW issues above) applies in relation to the Leather for the Library, because this was ordered as a variation to its joinery work. On 27 May 2005 Adams Joinery amongst others was invited to quote initially for joinery work for a number of rooms which did not initially include the Library. On 17 May 2005 BLDA produced drawings for the Library No. 2353 C/816A and C/817A. On 7 June 2005 BLDA produced an Elemental Description Schedule for the Library (cross referred to drawings No. C/816 and 817). The section dealing with the joinery had an item (4.10) relating to the shelves which provided that the MDF shelves in the Library were to be “clad all around with decorative stitching to ID specification and to architect’s approval” but stated that the material was to be confirmed. It is not clear what the “ID” specification was although there was a National Building Specification reference to Z10 and M60/185. The drawings do not assist with the type of leather or stitching.
286.    Adams Joinery was also asked to quote for the Library and provided its quote for the supply and installation of joinery to various rooms including the Library. The quotation was qualified by Adams Joinery to the effect that it had not “allowed for the supply or upholstering the Leather… until further specification”. It was also qualified by Adams Joinery to the effect that “no allowance has been made for constructing full working samples”.
287.    It is common ground that AI16C by which BLDA instructed WLC to place an order with Adams Joinery excluded the supply of the Leather for the Library until further specification. This suggests that either BLDA was unaware that the Mackays had made up their mind about the Leather or that they had not yet finally made up their mind. Indeed when BLDA issued its next version of the Elemental Description Schedule the Leather was still to be confirmed.
288.    When WLC entered into its sub-contract with Adams in or about March 2006, the sub-contract did not include for the leather. However, Adams had requested that information about the leather specification be provided by 23 December 2005. It had been informed at least informally by 16 February 2006 that the leather type was to be “Spinneybeck-Lucente 1601”. It appears that no specification was provided. Mr Joyce gave unchallenged evidence that Adams requested more information relating to the leather specification. He also said that on 20 May 2006 Adams provided a large sample of the leather clad library units to JSI.
289.    Bev was in a state of confusion or ignorance as to whether Adams had initially priced the leather in the library. In an e-mail to the Mackays, he wrote:
“1. LIBRARY…re leather costs…DLD [BLDA] explained that the initial costs of the leather, had failed to take into account that the leather was on all internal sites. The subsequent amendment to suit the issued design details, resulted in a cost increase. It was agreed that to resolve this that [sic] the vertical shelf providers would be lacquered, finish to suit the agreed dark grey RAL colour”
2. LIBRARY… Adams are currently trying to source a cheaper leather, as a further attempt to reduce costs. JSD (Bev) will do the same. We have however a ‘liquid’ leather (man made) which is a good match to the leather, and will be considerably cheaper.”
290.    The reference to “leather costs” in the first numbered paragraph is probably to such costs as had been allowed in the budget and this explains why Adams was being asked to find a cheaper leather than the Spinneybeck-Lucente previously identified for which Adams Joinery had submitted  a price (not in the court papers). On 22 June 2006, BLDA reported on Adams Joinery “Variations of cost”, stating in relation to the library:
 “The ID asked for a sample of the library to be manufactured. Adams did this, it is now in Janine Stone’s offices, and they have charged for it. G&T should confirm that this price is correct.
After tender the library was redesigned by the ID omitting joinery, and extending the use of leather. Adams re-priced the whole room and the price of the joinery was reduced [from] £35k to £25k approximately.
The leather coverings, which now covered all the faces of shelves, carcass and backs but was stuck not stitched, were priced by Adams as an additional £46k. Adams had investigated cheaper leathers and should have budget prices this week.
Client and ID discussed reducing the amount of leather. Instructions awaited.”
ID is an acronym for Interior Designer.
291.    Matters had still not been resolved by the end of June 2006. WLC reported at the site meeting on 27 June 2006 that the changes to Unit C including “some long lead in items eg leather cladding” were delaying the construction programme and were on long procurement times. On the same day, Bev e-mailed BLDA with an idea for an alternative specification for the leather for the back panels of the shelving. BLDA forwarded this e-mail to Adams Joinery asking for a revised cost for the library area using this alternative material; this was not copied to WLC. Mr and Mrs Mackay were kept informed as to what was going on; for instance at a design meeting on 6 July 2006, BLDA reported to them that the leather was being re-priced and that alternative samples and prices were awaited from Adams Joinery.
292.    On 11 July 2006, Adams quoted for amongst other things Leather in the Library; the sum quoted was £43,632.20. It had sourced alternative leathers and it provided samples: “Avionappa Ivory and Parchment leathers would give a saving of £14,620.03. The Specially Dyed Sonia-Panna leather would give a saving of £4008.73”. A 50% deposit was required to place orders for the leather and fabric. This was passed on to BLDA on 12 July 2006. On 13 July 2006, BLDA asked Adams to “research the viability of the re-specification of the leather to the library to Sonia Panna, as tabled” at an impromptu meeting that day; BLDA was concerned about the impact on the programme as the leather would have to come from Italy.
293.    There was an exchange of e-mails between Adams Joinery, BLDA and Bev (with WLC not being copied in) on 19 and 20 July 2006. Bev had been talking to Adams Joinery about joints and stitching details for the Leather in the Library, saying that they would be issuing outstanding information later on 19 July 2006 but Adams Joinery was not sure what Bev meant. BLDA told Adams Joinery that “Bev requires any stitching detail around the edges of the shelving and is keen to see where the jointing is going to happen” and thought that he was “waiting for a detail/sample from” Adams Joinery whose response was that this had all been held up pending the order being placed for the “Library change of Leather”. BLDA e-mailed back to Adams Joinery on 20 July 2006 saying:
“We are still awaiting your comments on any impact the change of leather specifications may have on the programme. As you are aware from our meeting on the site, both the client and the Interior Designer working to use the alternative that you table for the library. However it was agreed that due to the fact that it would have to be specially dyed in Italy, Adams would investigate its viability.
Once this information has been received, we will hopefully be in a position to place the order for the leather. In the interim it would be useful to use this time to agree the aesthetic of the stitching and joining details.
Please can you confirm if this is acceptable and when we will receive this outstanding information?”
294.    BLDA issued an instruction (AI311C) on 18 July 2006 for numerous variations for Adams Joinery which had not been formally instructed; these did not include the Leather to the Library. It is clear that Adams Joinery was unwilling to spend time and resources researching the issues relating to the leather without clear instructions. At the site meeting of 25 July 2006, WLC repeated their concern about changes and the lack of instructions in relation to leather cladding as this was delaying the construction programme.
295.    On 9 August 2006, WLC sent to BLDA an extension of time notification based in part on the fact that it was still awaiting instructions regarding the supply and installation of Leather to the Library as well as the Lower Hall and lobby. The same point was emphasised in WLC’s progress report of the site meeting of 22 August 2006. BLDA never sought to challenge these assertions.
296.    It was only on 21 August 2006 that BLDA by e-mail identified to WLC (copied to Adams) that the Leather for the Library and lower hall was to be “Sonia Panna”. WLC confirmed this in writing that day and on the following day sent a site instruction to Adams Joinery in relation to this. On 25 August 2006, WLC reminded BLDA that Adams Joinery required a 50% deposit for the leather and fabric, albeit that WLC would pay for this out of advance payments; these payments were probably certified the following month. There was at this stage no information as to how the leather was to be applied; there had been talk of adhesive and stitching.
297.    WLC reported for the site meetings of 19 September and 17 October 2006 that, although there were substantial delay on the joinery, Adams Joinery was currently processing the leather goods. On 27 October 2006, Bev e-mailed BLDA asking for an update on the status of samples amongst other things for the “leather stitching for the library shelves”. Up to this stage, WLC and Adams had not been asked to provide any sample of the leather stitching but on 30 October 2006 BLDA passed on to Adams Joinery and WLC Bev’s e-mail. Bev indicated in an e-mail dated 8 November 2006 to Mrs Mackay that he was going to visit “the guys who are doing all the leather work next Wednesday to ensure that they have understood what it is we are after and to do a level of quality control” going on by asking: “Do you have any feedback on the sample of the shelf and it’s stitching I left on Monday”? It is not clear who “the guys” are; although it could be Adams Joinery or Courtney Contract Furnishers (“Courtney”), WLC’s report for the site meeting of 14 November 2006 identifies that a visit to “the upholsterer is planned for w/c 13 Nov”.
298.    The upholsterers were Courtney and they wrote probably following that meeting that their latest sample was the best answer to what was achievable using the specified materials. Courtney wrote to this effect to Adams on 22 November 2006 and adding:
 “Unfortunately, it would be almost impossible to have accurately sewn stitching lines on the horizontal surfaces of the shelves to mirror those on the vertical surfaces (as sample). Upholstery is not always an even thickness and certain parts of the hide are softer, therefore you get inconsistency of how much it may stretch, so with the number of datum lines involved it would be virtually impossible to keep those stitch lines straight and parallel.”
It then goes on to offer a further price for supplying and applying an interliner to wall shelves and back boards. It is a reasonable inference that any sample was provided to Bev and the reservations highlighted in this letter passed on to him. It is unclear if Mrs Mackay attended the meeting.
299.    WLC reported for the site meeting of 12 December 2006, following that meeting with Courtney, that a “revised sample for the library shelving incorporating padding is now ready for approval”. It is probable therefore that the different ideas, including providing padding between the latter and the MDF, were being considered.
300.    There was on 18 December 2006 an internal meeting between BLDA, Bev, SLW and RLB at which Bev raised “concerns regarding the quality of the leather stitching sample sent by Adams [to Bev] for their approval.” A subsequent meeting had been arranged for 5 January 2007 at BLDA’s offices to discuss stitching with Adams and Courtney. The following day Bev e-mailed Adams (copied to WLC) as follows:
“Apologies for the delay in getting back to you all…
As far as the sample is concerned I am afraid that the stitching that joins two pieces of the leather together on the vertical is still not acceptable.
Please refer to attached photo as it shows the leather tearing slightly at the stitch. I understand that this is a difficult detail but we must find a better way to achieve this. I am at pains to show this to Giles and Caroline as it is less than perfect.
There are also potential issues with what exactly is expected by Giles and this illustrates the quality that he is expecting. Note that via Caroline, Giles is expecting stitching details that are similar to the leather upholstered room within say an Aston Martin. I think that due to the budgetary constraints that this item at this level was never achievable, and is a discussion that will need to be had with Giles and Caroline when I present the sample”.
This followed a follow up e-mail on 18 December 2006 from Adams referring to another sample sent to site the previous week. The meeting planned for 5 January 2007 was postponed by several days.
301.    It was at this meeting or shortly thereafter that further thought was being given to changes to the shelf detail. This is referred to in Bev’s e-mail dated 15 January 2007 to BLDA, copied to Mr Mackay but not to WLC or Adams:
“Can you please give me an update or confirm that we are still on track to receive the revised leather shell sample with the following alterations by the end of this week.
1. Amended stitching to the leather joins.
2. Stitching removed off from face and replaced by line detail.
3. Implications of alterations”
This e-mail was passed on to Adams by BLDA. Mr Joyce said, and I accept, that the stitch detail was changed by Mr Mackay so that it would run horizontally across the joints instead of in line with the joints in the leather. Mr Hawks of Adams Joinery e-mailed BLDA on 17 January 2007 to say that he and Courtney was “not having much luck with producing the stitching detail”; he had even visited a car showroom without success and asked for a photo to be taken as to what was required so that they could understand the detail better.
302.    WLC reported to the site meeting of 23 January 2007 that the “library shelving is subject to development/specification/requirement.” This was not challenged by BLDA. On 23 January 2007, BLDA reported to Mr Mackay:
“Adams made a large sample of the leather clad library unit and delivered it directly to your Interior Designer on 20th May 2006.
There were discussions both about the design and quality until Adams arranged the visit to the upholsterers on 15th October 2006 to view what was thought to be the final agreed sample.
At this meeting the Interior Designer asked for the leather to be padded and the stitching to be straighter and more uniform.
Adams produced a second sample which was seen by the Interior Designer on 14 December. He was unhappy with the stitching.
On 10th January the Interior designer explained in detail what the client wanted with the upholsterer, Adams & BLDA (i.e. horizontally across the joints instead of in line with the joints).
At present, Adams are waiting for a photograph of the type of stitching required by the Interior Designer. They have sent their upholsterer to look at car seat stitching but need more guidance.”
303.    In its letter to BLDA of 1 February 2007, WLC wrote amongst other things that, whilst Adams Joinery had targeted to complete other work by the end of January 2007, areas that would not be complete included the Library where it had been agreed that the leather coverings should be left until completion of the clients’ final decorations.
304.    At the site meeting of 6 February 2007, the following was noted:
“The Library is waiting for confirmation on the leather stitching, [BLDA] reported that the meeting took place 5 February 2007 with [Bev] and…Adams. [Adams] presented 10 samples of stitching including hand stitching. [Bev] will confirm a sample with the client 6 Feb 2007. This is urgent as it affects installation of the Library joinery, the door and the large panels in the Lower Hall. [Mr Joyce] stated that none of the Library joinery can be fixed because it is dependent on the upper sections being covered in leather first and these are in abeyance until the leather stitching has been agreed.”
Mr Mackay was sent a copy of these minutes and said in relation to this note:
“We have been waiting for these stitching samples for months and months – why has it taken so long to arrive? We signed off this design in early summer 2006”.
These comments were eventually passed on to WLC on 27 February 2007 whose response was:
“Rejection of samples offered complying with the specification by reference to ‘Range Rover’ and ‘Aston Martin’ upholstery (see Interior Designer’s e-mails) is the case up to now. A further 10 samples of differing specification were offered, with pricing implications but no instructions yet received.”
305.    On 9 February 2007, WLC was still awaiting design decisions on leather stitching as confirmed in its e-mail of that date to Adams Joinery. WLC reported to the site meeting of 20 February 2007 that installation of leather work generally was delayed and was outstanding. It is absolutely clear that by 18 February 2007 no decision had been reached in relation to the stitching because on that date Adams Joinery was providing quotations to WLC for three alternative types of stitch (“small hand-stitched, zigzag and looped”). On that date WLC produced a list of outstanding works which in relation to all joinery in the library said that it was “awaiting instructions the leather stitching. 10 further samples offered 5th February”; it was explained that once the stitching was accepted a price and programme would have to be offered. Adams Joinery e-mailed WLC on 19 February 2007 that the leather work would take 17 to 19 weeks to complete “once we have the green light”. The costs and timetable were forwarded to BLDA on 24 February 2007.
306.    At a meeting between the Mackays and their design team on 2 March 2007 it was recorded that Mr Mackay would “call a separate meeting to discuss the Library shelving stitching” and would send BLDA “a picture of the effect desired”, it being recognised that the “stitching detail also affected the low wall panelling.” An explanation for the lack of urgency on the part of the Mackays is that some consideration was being given at least by Mr Mackay to omitting the Leather in the Library from WLC’s scope.
307.    On 8 March 2007, WLC wrote to BLDA stating that it still had “no instruction to date in respect of this leather”; they referred to the fact that the leather work would not be complete until 20 July 2007 if an instruction had been received by 2 March 2007; it said that this was a Relevant Event under Clause 25 of the Contract and requested an extension of time with costs. This date would need to be adjusted in the light of the actual instructed date. On 14 March 2007 Adams in relation to the Leather Stitching stated that preliminary costs based on a 23 week programme would be £41,330 and that the work if instructed by 19 March 2007 would be complete on 30 July 2007.
308.    A meeting between the Mackays, Bev and BLDA held on 19 March 2007 recorded elements of the agreement between them as to what should be required in relation to the leather. Thus, the faces of the shelves were to have a single machine stitch on long panels with black stitching, the junctions between the hides on long shelves should be minimal (stitched through on the back with a single crease and no thread showing) and that it should be “backed with a bumping” and that the lower panels should have no seams if possible. At a site meeting on 20 March 2007, Mr Joyce was told by BLDA that it was still discussing the leather stitching with Mr Mackay and Mr Joyce reiterated that an extension of time should be granted in relation to this item.
309.    On or about 20 April 2007, at BLDA’s request, Adams Joinery produced a further sample for approval. This sample was presented at the site meeting of 23 April 2007 which was attended by Mr Mackay. The minutes record that it was agreed “that the stitching was not acceptable as it was not straight” but BLDA “explained this is a difficult effect to achieve because the leather needs to be stitched first then stretched across the shelves across the bumping.” It was also recorded that “the leather is very soft so the parallel lines are easily distorted” although Mr Mackay stated “that he has seen examples of this done successfully”. It was agreed that a meeting should be organised with Courtney to discuss the technical solution. That meeting took place on 26 April 2007 attended by Courtney, Adams Joinery, WLC, BLDA and Bev; they looked at a sample which Mr Mackay had provided and there was agreement that it was not relevant; however having discussed the matter in some detail it was resolved that Courtney would produce one more sample. For instance, there was agreement that to avoid a raised seam effect the timber shelf underneath was to be grooved to take the double thickness of leather at joints. It was clear, as confirmed as a client site walk around meeting on 2 May 2007 decisions for the manufacture of leather panels to the Lower Hall were dependent on approval of the leather stitching.
310.    The further stitching sample was presented to Mr and Mrs Mackay at a client site walk around meeting on 16 May 2007. They confirmed that a sample with cream stitching was acceptable (it previously having been indicated that black stitching was more acceptable); the use of a thicker thread was to be looked into.
311.    On 22 May 2007, Adams Joinery indicated that its programme in the light of the approval would involve completion of the leather work by 3 September 2007. On 29 May 2007, WLC on a Question and Answer Sheet sought a decision as to whether the price for the leather to the Lower Hall Lobby (£9112.17) was accepted. Mr Mackay was reticent about accepting this.
312.    On 1 June 2007, Mr Joyce of WLC wrote to BLDA indicating that Adams Joinery would have difficulty in completing the leather work by reason of incomplete works from directly employed sub-contractors. It was recorded at the Client Site Walk Around Meeting of 6 June 2007 that Adams Joinery would complete the joinery in the Library by mid September 2007.
313.    On 19 June 2007 BLDA issued AI471C instructing leather works to the Lower Hall lobby. WLC instructed Adams accordingly on 22 June 2007 and it is clear that this was tied in with the Main Order to Adams Joinery. As confirmed by WLC’s Q&A Sheet No. 1677 the supply and installation of this additional work required a 14 week period, resulting in the leather to the Lower Hall lobby forecast to be complete by 25 September 2007. Following a 2 week period to complete any snagging work this would indicate an overall completion of the leather work to this area in early to mid October 2007.
314.    On 23 July 2007 AI 481C was issued requiring additional works in connection with an additional air duct to the Library fireplace; this had been presaged at the Walk Around Site meeting on 18 July 2007. Adams was instructed accordingly by WLC on 27 July 2007. The first delivery of leather joinery for the Library arrived on site on 15 August 2007. As a result of the additional AI 481C, WLC was anticipating completion of the leather joinery in the Library by the end of the first week in October 2007.
315.    Mr Joyce gave substantially unchallenged evidence that the leather work in the Library and the Lower Hall Lobby was in practice dealt with as one commission by Adams Joinery, which is not surprising given that the leather was the same, even if stitching was not required for the Lobby area. He also gave unchallenged evidence that the Leather work was delayed whilst a decision was made by the Design Team in relation to the number of panels to the sliding door between the Lobby and the dining area; these works were done between 4 and 18 September 2007. Work was further delayed as a result of the need to install a fresh air duct behind the Library joinery, this work was not completed until 6 September and affected the installation of the shelving. A further design change affecting joinery installation in the library was that instructed by AI510C on 4 September 2007 which resolved a design clash between a bulkhead and the higher level leather clad shelving. A further variation contained in AI508C received by WLC on 19 September 2007 required the installation of a frame to a ceiling ventilation grille which impacted upon the library shelving.
316.    WLC’s Site Diaries confirm that Adams Joinery was carrying out the works to the Leather Library shelving up until 26 October 2007 at which point this work seems to have been completed. Adams then completed the leather panelling to the Lower Hall Lobby.
317.    There was no complaint by BLDA that Adams Joinery was in any way culpably in delay in or about its performance of the Leather in the Library procurement or work. Indeed, from about April 2007 onwards, there was no complaint by the Mackays as such about delay on the part of Adams Joinery thereafter in relation to this work.
318.    One first needs to analyse whether WLC had any design responsibility transferred to it in relation to the Leather in the Library. For reasons already given in relation to ABW, there was no such CDP transfer to WLC; nothing in the history of events relating to the introduction of the Leather in the Library suggests any such transfer. WLC as between it and DMW had no such or any material design responsibility. Even if there was an obligation imposed on Adams by WLC to “complete the design/detailing” of this Leather, that would not create some sort of design responsibility as between WLC and DMW. In any event, the Leather work was excluded from the Adams Joinery quotation which WLC was instructed to accept and it only came back into the equation by way of a relatively informal variation arrangement; in relation to the Leather in the Library (as opposed to the Lower Hall Lobby), there was no formal Architect’s instruction, albeit there is no issue that WLC was asked to instruct Adams Joinery ultimately to do this work.
319.    I am wholly unconvinced that, even if WLC had an obligation to DMW to “complete the design/detailing” of the Leather in the Library, that would include deciding what leather to use or indeed what type of stitching to deploy. Those were essential elements of the design, which, once decided upon by the Mackays, Bev and BLDA, would remain to be completed.
320.    Because WLC had no or no material design responsibility for the Leather in the Library, any delay in the selection of the leather or the stitching regime was not the responsibility of WLC. Even if and to the extent that Adams or its upholsterer sub-contractor, Courtney, were involved in the process of selection, any delay or incompetence on their part in that process would not be the contractual fault of WLC. To the extent that BLDA and Bev decided to use Adams Joinery and Courtney to help them assist Mr and Mrs Mackay in their selection of leather and stitching, that was their choice.
321.    In any event, I am satisfied that in all probability neither WLC nor Adams Joinery nor Courtney delayed matters in relation to the Leather in the Library. They had no responsibility at all prior to March 2006 when the sub-contract between WLC and Adams Joinery was entered into. They had no responsibility indeed until about August 2006 when it could first legitimately be said that WLC was instructed, albeit informally, to go ahead with instructing Adams Joinery to proceed with the Leather in the Library.
322.    Even if there had been some responsibility earlier, I have formed the overwhelming impression that the delay was all on the side of the Design Team and in part on the Mackays themselves. Whilst it is true that Mr Mackay had indicated to Bev that he had approved in mid-2005 what Bev had shown him, there is no indication that this was passed on to Adams Joinery or indeed to WLC. Indeed, all the documents produced (such as the Elemental Descriptions) were telling WLC that the type and detail of the Leather was “to be confirmed”. There was no Interior Designer specification which identified the type of the leather or the type of stitching, at least which was produced to WLC. It is clear that going into 2006 the Design Team was worried about cost and tried to secure from Adams Joinery prices for other leathers. It was only in August 2006 that the Mackays and the Design Team indicated to WLC that they had selected what turned out to be the eventual type of leather to be used.
323.    There was no specification for the type of stitching initially and Bev appears to have taken it upon himself to talk to Courtney in November or December 2006 as to what might be appropriate. There was then essentially a development primarily by Bev, albeit occasionally consulting with the Mackays, of an understanding of what might be not only acceptable to the clients but also practicably achievable. In effect, Bev largely but to a lesser extent BLDA were working out what they (together with their clients) wanted. This included consideration of different types of stitching detail and the provision of padding under the leather. This process went on up until May 2007. DMW suggests that the delays up to May 2007 were largely attributable to the production by Adams Joinery or Courtney of “unacceptable” samples. Whilst it is true that most of the earlier samples were not accepted by Bev, BLDA or the Mackays, that does not mean that they were or were necessarily sub-standard. There was simply, in my judgement, an evolving design process by which the Design Team and the Mackays got to a point that what was eventually produced in May 2007 was acceptable to them, aesthetically and practically. The whole process was in any event confused by changes of mind on the part of the Mackays, not the least of which was the requirement that the stitching should be like that on leather seats in an Aston Martin or Range Rover car.
324.    Once the decision was made to go ahead with the selected leather and stitching in May 2007, I am satisfied that WLC and Adams Joinery proceeded with all due diligence in connection with the Leather in the Library. From May 2007 through to 26 October 2007, they went as expeditiously as was reasonably possible.
Plasterwork
325.    This issue relates primarily to plasterwork which was found to be defective mainly in about February 2007 and which was put right over the next 3 to 4 months. It is said by DMW that it was the need to put right such plasterwork which was the cause of delay initially during this period. This issue does not involve the consideration of design issues.
326.    It is common ground that two specifications issued to WLC by BLDA are applicable, K10 “Plasterboard dry linings/partitions/ceilings” and M20 “Plastered/rendered/roughcast coatings”. These were based on generic National Building Specification documents. They distinguished between skim coated plaster on plasterboard and thicker plaster coatings on blockwork or concrete walls or columns. In relation to plaster on plasterboard, K10 provided for “permissible” deviation across joints of 3 mm, external angles of 4 mm and internal angles 5 mm (Paragraph 650a); for the “skim coat plaster finish” of a thickness of 2-3mm, the finishing was to be “Trowel/float to a tight, matt, smooth surface with no hollows, abrupt changes of level or trowel marks”.
327.    As for M20, the plastering of masonry backgrounds is specified in Paragraphs 210a, b and c. The plastering was to comprise 13mm Thistle undercoat with a 2mm Thistle finish. Where the background substrates were dissimilar there were to be two 8mm coats of Thistle Bonding Coat over lath with a 2mm Thistle finish. Concrete surfaces were to receive an 11mm thick Thistle Bonding Coat undercoat and a 2mm Thistle finish. Paragraph 710a defined general standards applicable to all wet plastering as follows:
“Application Generally:…
Appearance of finished surfaces: Even and consistent. Free from rippling, hollows, reduce, cracks and crazing
Accuracy: “Finish to a true plane, to correct line and level, with angles and corners to a right angle unless specified otherwise, and with walls and reveals plumb and square.”
328.    Paragraph 715a specified the degree of surface flatness generally as follows:
“Deviation of plaster surface: measure from underside of a straight edge placed anywhere on surface – permissible deviation (maximum) for plaster not less than 13 mm thick: 3 mm in any consecutive length of 1.8 m”.
 A series of clauses specify the particular requirements for certain locations and backgrounds. So far as the finish is concerned, the requirement is (with one exception) stated to be: “Smooth as clause 777a” which provides that:
“Appearance: A tight, matt, smooth surface with no hollows, abrupt changes of level or trowel marks. Avoid water brush, excessive trowelling and over polishing.”
For one particular location, namely concrete walls around service stairs, Paragraph 210c also provided that:
“Extreme care is to be taken to ensure that all surfaces reflect the design intent with smooth and accurate transition between any adjacent radius dimensions and surfaces are perfectly flat and vertical.”
329.    Thus, NBS M20 deals with internal plaster coatings. It provides particular specifications related to specific backgrounds and specific locations. It deals with thick coatings (exceeding 13 mm thickness) onto solid backgrounds as well as skim coatings onto plasterboard backgrounds. Paragraph 715a specified the maximum permissible deviation for plaster not less than 13mm thick, namely 3mm in any consecutive length of 1.8m. There was no definition of dimensional limitations or any defined tolerance limits as to the deviations in the surface for thin coating work (i.e. under 13mm thick), such as would apply to skim coating of plasterboard, covered by K10. 
330.    WLC believed that a high quality finish was required. There was an exchange of correspondence between Simon Spiers (WLC) and Andrew Crispin (WLC) on 22 and 23 September 2005 concerning an appropriate contractor.  In his email dated 22 September 2005, Mr Spiers asked Mr Crispin:
“…Apart from David Andrews do we have a plastering sub-contractor who can provide the quality required on this project along with the workforce to cope with these three houses?”
In his reply dated 23 September 2005, Mr Crispin said:
“Given the quality required and the output/volume required, I maintain we can only propose one subcontractor – David Andrews. I suggest you email the whole Client team advising them that we are only aware of one plasterer who can achieve the quality required, given the volume, sequence and time restraints. Ask them to put forward names within 2 working days who we can talk to and obtain references on.
Failing that we tender to one contractor!”
331.    A problem with the quality of the plasterwork first became apparent in November 2006. Mr Mackay said that the issues with the plastering first became apparent when he was asked to look at the completed flooring in the drawing-room. Although the flooring looked “great”, his eyes were drawn to the plaster finish on the walls which to him looked appalling. He reported what he saw in an email to BLDA and others on 27 November 2006. Bev wrote to BLDA on 24 November 2006 that:
“Further to my walk around with Giles earlier today I would like to confirm and comment on the following:
1. Sub standard plastering to the drawing room. I gather that Walter Lilly were already aware of this and are proposing to re-skim. However does this have any knock-on effect in time. Can we room by room (rooms where the spray coat has been applied) have a walk about with the lighting on to check the quality of the plaster. This will enable us to cross check that WL are aware of such issues?…”
BLDA responded on 28 November 2006 stating that the plastering in question had been observed and had already been condemned. They said that the repair work was being delayed in order to avoid delaying completion of the flooring.
332.    The plastering works at Plot C were at least nominally completed in early 2007.  However, on 9 February 2007 Mr Mackay visited the site and walked around most of the rooms in the house and complained about sub-standard plaster in almost every room; he emailed Bev on the same day:
“I understand that some rooms are to be handed over for snagging next week. I cannot see the point in this whilst as far as I can see every room in the house has defective plastering. The corner/angles are not straight or square and the walls are not flat.
The coffers are not true and in some cases the ceiling details are lower on end from another – all of this is not acceptable and will be rejected.”
333.    On 21 February 2007 Mr Martin Walker (SLW) sent an email to Mr Ron Bates (WLC) saying:
“The clients have expressed grave concerns about the quality of the plaster finish to walls and ceilings, they have made it clear that they are dissatisfied with the current standard of workmanship, and remedial work is necessary.”
Mr Bates forwarded the email to the WLC team the same day saying that ‘it needed their action, mindful of the specification we are working to achieve.’
334.    On 27 February 2007 Mr Mackay provided his comments on the minutes of the site meeting held on 6 February 2007:
“3.04 We visited the site on 10.02.07 last week – the house was a complete mess – with joinery still being cut in several of the rooms and plaster being mixed in various areas – I had a conversation with the site manager about it and sent an e-mail. The house is nowhere near complete – amongst other things – the plasterwork in every area is defective for a job of this quality and “price”…”
By letter dated March 2007 to WLC, Knowles stated that the employer would deduct some £104,000 in respect of defective plaster throughout the house.
335.    On 8 March 2007 RLB sent an email to BLDA:
“…both sides of the wall to the studies are not acceptable due to excessive making good (patches), excessive undulations (despite perhaps being within tolerances) and the loss of bond to the plaster (hollowness).
Ian (Symes) (BLDA) and I spent a considerable time yesterday checking most of the walls in Plot C and he is to send me a note today of those that were outside tolerance or otherwise defective and therefore not acceptable….
The schedule of defects should be sent directly to WLC for their immediate attention.”
The results of Mr Symes’ inspection were contained in a report dated 7 March 2007 and he found defects in the rooms surveyed. The survey was discussed at a Client Meeting on 14 March 2007. It was recorded that:
“5.02 David Lloyd-Davis confirmed a snagging list for the majority of the plaster walls in Plot C had been issued. Vernon Bardsley and BLDA had examined these walls together. VB was concerned that BLDA were not using a straight edge. DLD did not agree and said that he himself had used a straight edge in one session.
5.03 Giles Mackay was concerned that the piecemeal way WLC were trying to patch up the plaster was not working and was only delaying more effective remedial work. DLD confirmed that he had warned WL that the method they were using to repair small areas of undulation was not helping and creating more problems.
5.04 DLD explained that the Architect could not dictate how remedial work should be done, but could only say if it was acceptable or not acceptable.”
336.    It is clear that BLDA at least considered that the plastering defects required WLC’s attention as is evident from its email to WLC that was circulated internally, on 14 March 2007:
“…Can we meet at Lots Road and have a practical session as to how you intend to complete the houses.
At the moment we have no clear idea of your programme and need certainty. I also need to understand how you intend to put right the defects in the lift shafts and the plastering being the most difficult to resolve”
337.    However, what WLC (Messrs Howie and Joyce) were contending was that, while there were some defects (which had begun to be repaired), there was substantial compliance with the specification. BLDA went some way to agreeing this in that it applied the same tolerance standard as that suggested by WLC, namely deviations not exceeding 3 mm in any consecutive 1.8 m direction were acceptable (as referred to in a report of Knowles dated 6 March 2007). It is also clear that even Knowles considered that the plastering defects said to exist in the coffered ceilings were exaggerated. BLDA said at the “Snagging and Outstanding Work” meeting on 6 March 2007 that Mr Lloyd Davis had seen many of the rooms and that “many may be within the specification and that the problem areas may be caused by visual deceptions relating to viewing angles”; he went on to say “there are two problems making it worse than it appears. The first coat of brush applied paint is naturally patchy and catches the light differently, and second, the fine finishing filler is being applied with a metal edge”; he suggested that a plastic edge be used. By 20 March 2007, Mr Joyce reported to a Progress Meeting that the remedial plasterwork had been finished and that the walls were within tolerance.
338.    The differences between the parties are reflected in an e-mail sent by SLW on 26 March 2007 to Mr Ron Bates of WLC in which he said:
“As you may know I met on site in Plot C drawing room with John Howie, David Lloyd Davis and others today primarily to establish if we could come to agreement on the quality issues in respect of the plastering.
I was disappointed that John was not prepared to engage in positive discussion and relied on the empirical test of tolerance contained in the specification without apparently taking note of the visual criteria. John’s suggestion that the specification provided for no greater quality than that found in commercial premises was particularly worrying.
Whilst it was pointed out that some of the plaster repairs still did not meet the tolerance John simply noted that snags were not complete and not ready to be offered for re-inspection. When asked when the snags would be complete and ready for re-inspection John was unwilling or unable to advise a timeframe. John was also unable to advise when the reports on the plaster quality commissioned by you weeks ago would be available.
Further, in response to my question as to when all the WLC works would be complete in Plot C, apart from those areas/items awaiting information, John was again unwilling to commit. Indeed he went on to say why should WLC “bust a gut” to finish the works when information remained to be provided and we should wait until WLC have completed all their work before critiquing it
My suggestion, repeated many times before the WLC should mitigate some of the delays by fully completing all the work they are able and “locking the doors” again appeared to fall on deaf ears…”
339.    Mr Joyce explained in evidence that WLC felt that BLDA were unreasonably snagging the plasterwork. They therefore called in an independent expert, namely the Federation of Plastering and Drywall Contractors technical panel who, after inspecting all of the rooms, reported on 20 March 2007 that the standard of dry lining work was of a “commercially acceptable standard” and recommended that the work be accepted by all parties as such. The report also said that the work was found “to be of a high standard” and that it was in effect visually acceptable.
340.    BLDA maintained that WLC seemed to be ignoring the specification requirements both as to visual quality and as to flatness. Thus, for example, in a handwritten note of a meeting held on 21 March 2007 (and not attended by WLC) it is recorded that: “DLD and VB have looked at the plaster in Plot C – WLC say they have finished the remedial works but this is clearly not the case. WLC seem to be taking the stance that the walls are within tolerance but DLD says the specification also has requirements with regard to aesthetics.”
341.    Similarly, in an email to Mr Mackay dated 30 March 2007, Mr David Lloyd-Davis said that:
“The visual quality of the plaster is referred to in our specification as well as a qualitative requirement for flatness. The specification is not that for “commercial premises”. In addition to the specification, at tender interview, WLC were made very aware by Second London Wall and BLDA of the quality expected on the project…”
This was however in response to an e-mail from Mr Mackay which complained that the specification put forward by BLDA was deficient.
342.    By letter dated the 30 March 2007, WLC wrote to Knowles complaining about the withholding of monies amongst other things in relation to the plaster. It asserted that the great majority of the plasterwork had been executed in accordance with the contractual requirements but it did accept that there were a small number of areas identified (in conjunction with the architect) where the quality did not achieve the specified standard.
343.    Meanwhile, Knowles on behalf of Mr Mackay had retained surveyors called Chantons in March 2007 to survey the premises. On 3 April 2007, Mr Mackay demonstrated in an e-mail to Knowles that he was taking a very personal interest in the exercise involving Chantons, in particular in relation to a meeting several days later; specifications should be got together “so we can prove the defects”; he called for lights on site to shine at the walls to “help show up these defects”, ending up that this was “our best chance to nail this once and for all”. On 5 April 2007 there was a site meeting at which two setting out engineers from Chantons were present.  Mr Joyce recalled in evidence that Mr Mackay claimed that all of the plastering in Plot C was defective and that he instructed one of the setting-out engineers to “prove” this by applying a carpenter’s square to both internal and external corners. He says that he was asked by Mr Mackay to agree that the plaster was “defective” but he refused to do so. There was then another meeting at which Mr Mackay was not present (attended by Mr Joyce, Mr Bates and Mr Rough for WLC and Mr Bardsley of RLB) at which Mr Joyce demonstrated the correct way to measure the surface tolerances of plaster. There is little doubt that a large majority of items previously identified as defective were found to be within the acceptable tolerance. However an agreed method for a detailed plastering survey was agreed on and the following week Chantons went through the house and physically marked on the walls those areas which were out of tolerance, by reference to the agreed method.
344.    On 12 April 2007 there was another meeting attended by the same people but Chantons’ representative put an alternative set of findings based on its interpretation of the specification; Mr Joyce however believed that that was an incorrect interpretation as he believed that they were not measuring the plaster in accordance with the British Standard or using the approved measuring equipment. However, what was done was to identify and mark on the relevant walls with tape the relatively few areas of plastering which were outside the agreed tolerances. Knowles wrote an e-mail on 18 April 2007 to Mr Mackay attaching what was said to be the agreed survey schedules which identify just over 40 relatively small areas of plasterwork. However, this document was never issued as such to WLC; it is curiously dated 19 October 2010 and it is likely that it was never issued to WLC. Mr Joyce said and I accept that the plastering defects marked out on-site were not very widespread and there were not many of them; he said that they were “just localised very small areas” and it did not take WLC very long to do the relevant remedial work.
345.    It is common ground that all or least the large bulk of the identified defective areas of plasterwork (as marked on the walls) were put right by about the end of April 2007. For instance at a Client Site Walk Around meeting on 23 April 2007 Mr Mackay agreed that the remedial work on the third floor looked better, albeit that he said that it required more work to be done to bring it to an acceptable standard. The work in question was substantially completed by 25 April 2007. It does appear that there were one or possibly two minor areas identified on 9 and 16 May 2007. It appears likely that several other minor plastering deficiencies were noticed in November 2007 albeit it is probable that they were put right.
346.    It is worthwhile observing both that the perceived problems with the plastering defects arose very shortly after Mr Mackay had retained Knowles and had embarked upon the strategy to put pressure on particularly BLDA and WLC and that it was he, Knowles and RLB who took the lead in complaining about the plasterwork defects. There can be no doubt that there were some defects but it is equally clear that they were exaggerated. I do not suggest that Mr Mackay deliberately and dishonestly exaggerated the extent of the defects but he was much too quick off the mark to criticise WLC. He was not supported wholly by his own architect in these criticisms. The truth is that ultimately, upon advice, he accepted that the specification drawn up by his own Design Team did not provide as high a quality as he might have expected for the plasterwork; it may be that the Design Team can be criticised for that and for producing a more “commercial” level of specification. He was also prepared to accept the accommodation reached between Chantons, RLB and WLC in April 2007 whereby only the areas marked by tape on the walls (and possibly ceilings) were to be put right.
347.    In my judgment, the plastering problem identified primarily between February and April 2007 was and turned out to be a very limited one which was put right within a short time. As will become apparent in considering the question of extension of time, I cannot begin to see how this relatively minor problem either did cause or could realistically be seen to have caused any overall delay.
348.    There are said to be some subsisting defects upon which Mr Josey reported in his first report. However, in this context the Architectural experts are agreed that as to cracking in finishes as noted, these are such that might occur during the defects liability period as a result of drying out and shrinkage and would be resolved as part of the contractor’s normal defects liability duties. They do not indicate a deficiency in construction. As to the crack in “His Study”, this is likely to have occurred as a result of blockwork shrinkage and remedial work would entail cutting out the plaster along the cracked line, filling/grouting the block work crack, fixing reinforcement mesh and reinstating plaster locally. In those circumstances, I do not consider that there is any liability on the part of WLC.
Snagging
349.    The issues about snagging relate on analysis to two periods, February 2007 to about March 2008 (whilst BLDA was still engaged) and April to July 2008. Their main relevance lies in whether or not the snagging operations caused any overall material delay.
350.    There is no doubt that BLDA and WLC considered in late 2006 and early 2007 that, all things being equal, there was a reasonable prospect of achieving Practical Completion in the early part of 2007. It is clear from earlier in this judgement however that it was understood that there were elements of the works that were not going to be complete by such an early stage. Indeed, as 2007 went on, for instance with the Leather in the Library and the Light Wall, it must have been clear to all that Practical Completion would be later rather than sooner.
351.    Part of the anticipation that Practical Completion would be achieved early in 2007 was based on Mr Mackay’s declared assertions that he did not wish WLC to carry out any other previously uninstructed work and that he or DMW would be instructing directly employed artists and tradesmen thereafter. Mr Howie said in evidence, which I accept, that the building to all intents and purposes looked complete by the middle of February 2007, that remaining major works such as outstanding external works had been omitted and that many of the otherwise outstanding works such as the Light Wall, the swimming pool and cinema ceilings and Stingray doors were all driven by the need for the Design Team to resolve design issues. This explains why it was resolved that the snagging process started as between BLDA and WLC in late February 2007.
352.    The snagging process effectively involved WLC preparing a given area for snagging and inviting BLDA to come in and identify what remained to be completed or put right. BLDA was to produce a list for that area and WLC and their sub-contractors would then work through that list and finish or put right the listed items. This was to be repeated for all of the rooms.
353.    At a site meeting on 6 February 2007, Mr Joyce agreed with BLDA that snagging must commence as soon as possible but he said that it would have to take place elementally because there were unfinished and delayed items in most rooms. On 8 February 2007, Mr Joyce wrote to BLDA offering Plot C as likely to be practically complete on 16 February 2007 and asked for an inspection for 19 February 2007. WLC wished to undertake an elemental snagging process and he confirmed that this would commence in conjunction with BLDA on 12 February 2007. BLDA’s response on the same day was that there were no areas which could be snagged. Notwithstanding this, Mr Syme of BLDA issued Preliminary Snagging List No 1 on 23 February 2007.
354.    Over the following months in 2007 more detailed snagging lists were provided and it is clear that a substantial number of the individual snags were put right. It is also clear that, almost without exception, the identified snags, although numerous, were minor, consisting of loose screws, dirty marked surfaces or poor paint finishes and the like. It is unnecessary and undesirable to examine these hundreds of items in any detail. There is no suggestion that that any one of the listed snags was particularly serious and there is no doubt that they could all have been put right promptly and expeditiously. However, as the earlier and later parts of this judgement make clear, there still remained throughout 2007 substantive work which remained incomplete; this for instance included the Light Wall, the Barrisol ceilings, the Leather in the Library and the Stingray doors. As 2007 went on, it was and must have become clear that, irrespective of the snagging which was being identified and was being put right, the Works would not be achieving Practical Completion by reason of other matters.
355.    There were in addition other issues between the parties relating to snagging. As 2007 went on, there was an increasing number of directly employed artists and tradesmen working for Mr and Mrs Mackay on the site and there can be little or no doubt that their presence contributed to the amount of snags which had to be addressed, albeit that the impacts in 2007 were limited. Nonetheless, I accept Mr Howie’s evidence that their presence disrupted the snagging process in 2007; he said for instance that BLDA had difficulties in snagging because artists and tradesmen were in the way and protection provided by WLC to its finished work was preventing them from getting on. Additionally, there was some dilatoriness on the part of BLDA in its participation in the snagging process; they engaged an independent consultant, Mr Syme, to do this exercise and it is clear that he was seriously overstretched both in terms of time and also because he had not previously been involved significantly in the project; this was highlighted in a letter of Mr Howie to BLDA of 19 September 2007.
356.    Mr Howie attached to his first statement a detailed analysis (Exhibit JCH1) of the snagging lists (issued in 2007) and when each snag was attended to. He also classified the snags in to categories: “Not a defect” (120), “Not WL – Out of Contract” (104), “Not WL – Damage by A&Ts” (4), “WL but de minimis” (1193), “WL not de minimis” (38), “Info required to complete” (57) and “Already PC (staff areas)” (138). He identifies a total of 1654 snags. Whilst it is possible that this classification is not 100% accurate, I am wholly satisfied that it is broadly accurate. The largest category (the WLC “de minimis” work) was such that I am satisfied that but for the other problems the snagging operation in 2007 did not materially or at all impact upon the overall completion. This is because I have no doubt that if the snagging was the main and critical item of work left to be completed it would all have been resolved in all probability within several weeks at most. In so far as there is any criticism in relation to the other heads, it is not valid for the reasons given by Mr Howie.
357.    Although Mr Howie was challenged to a very limited extent about JCH1, DMW (particularly Mr Mackay) and to a lesser extent its Counsel waited until the final written closing submissions to produce a detailed analysis of the lists and of Mr Howie’s work on the lists. This involved a more detailed analysis of the WLC diaries. However, Mr Mackay’s extensive work and many of DMW’s Counsel’s observations were simply not put to Mr Howie. It is generally unacceptable and undesirable, if any significant points are to be made on the evidence in closing, for key elements not to have been put to the relevant witnesses on the other side. It means that Mr Howie did not have the opportunity to react to any such points and it strongly gives the impression that the points only taken in the closing submissions were either not considered at all before the end of the evidence or have simply arisen as afterthoughts on what might have been the case. In this case, DMW’s Counsel accepted that Mr Mackay’s analysis attached to the closing submissions was in part materially based on documents which were not in the Court bundles. This again is very unsatisfactory. It leads me to the view that I should attach very little weight to this analysis. Insofar as DMW is simply making the observation (which it does) that in 2007 and early in 2008 few of the snags were attributable to damage or incompetence on the part of directly employed artists and tradesmen, I have broadly already accepted that and, indeed, Mr Howie’s own analysis shows only 4 of the 1654 snags were attributable to damage by them.
358.    It is common ground that the number of snags had reduced substantially by the end of 2007 (in December 2007 there are only some 69 snags). By the time that BLDA left in March 2008, a further 130 snags were identified.
359.    In relation to snags in 2008, it is clear, and I accept that throughout the period from about January through to July 2008 there was a much greater impact on WLC’s snagging operations as a result of the activities of the directly employed artists and tradesmen. The essence of what both Mr Joyce and Mr Howie say is that there were substantial numbers of workmen engaged by such artists and tradesmen and that they were substantially responsible for many of the further snags listed in 2008, initially by BLDA but after their dismissal later by or on behalf of Navigant. Navigant employed a firm called Hickton to do the snagging exercise. Mr Howie produced a further analysis (JCH2) of the Hickton snagging lists which showed that of the 1696 items listed, 1048 were attributable to directly employed artists and tradesmen, 145 required instructions from Navigant, 67 involved damage by others and only 436 (26%) needed to be addressed by WLC. WLC’s evidence, which I accept, was that matters which were the responsibility of WLC (which were extremely minor) were addressed promptly but their progress was impacted by all the other snagging work which was not its responsibility. There was and is a somewhat sterile debate on the evidence as to how many directly employed artists and tradesmen were on site. It is unnecessary to decide precisely how many but it is absolutely clear that there were a substantial number in 2008 in the period leading up to certified Practical Completion.
360.    I accept Mr Howie’s evidence and analysis in relation to the Hickton exercise. He said under cross-examination that his analysis was based on what was essentially agreed between Mr Gad of WLC and Hickton at the time. This was based on an Excel spreadsheet compiled by Mr Gad from the lists produced by Hickton onto which he put his comments as to who was responsible, these then being sent back to Hickton and Navigant, who agreed them. He said in evidence that it was “absolutely definitively agreed”. He was not challenged in any material way about the contents of his second exhibit and he was convincing. The efforts made by Mr Mackay in his extensive A3 analysis (attached to his Counsels’ closing submission) to seek to undermine that are wholly unconvincing because he was not directly involved in the snagging process; DMW decided not to call anyone from Navigant or Hickton as a witness. At most, Mr Mackay has simply tried on some ex post facto and second or third hand basis to try to undermine what Mr Howie has said. That is essentially an exercise to which I can give little weight.
361.    I will deal with the impact of the various snagging exercises on completion in the next chapter of this judgement which deals with extension of time.
Extension of Time
362.    It is first necessary to consider what the Contract between the parties requires in relation to the fixing of an appropriate extension of time. Whilst the Architect prior to the actual Practical Completion can grant a prospective extension of time, which is effectively a best assessment of what the likely future delay will be as a result of the Relevant Events in question, a court or arbitrator has the advantage when reviewing what extensions were due of knowing what actually happened. The Court or arbitrator must decide on a balance of probabilities what delay has actually been caused by such Relevant Events as have been found to exist; that is by analogy to the exercise that the Architect has to do within 12 weeks of Practical Completion under Clause 25.3.3. How the court or arbitrator makes that decision must be based on the evidence, both actual and expert.
363.    Clause 25.3.1, which deals with extensions of time being granted prior to Practical Completion, clearly envisages that the extension must relate to the extent to which “completion of the Works is likely to be delayed” by the Relevant Event or Events. The extension to be granted within 12 weeks after the date of Practical Completion (Clause 25.3.3) is to involve the fixing of a Completion Date which is “fair and reasonable having regard to any of the Relevant Events”. Reading the two sub-clauses in context and together, they essentially mean the same thing. If at the latest stage it is clear that the Relevant Event in question has actually delayed the Works by, say, 10 weeks, it would be an extraordinary state of affairs if the extension of time then granted as fair and reasonable was anything other than 10 weeks.
364.    In Balfour Beatty Building Ltd v Chestermount Properties Ltd (2003) 62 BLR 1, Mr Justice Colman had to address several issues (under a JCT contract in similar form to the Contract here) one of which was whether in granting an extension of time the Architect should grant as an extension only the number of days delay actually caused by the Relevant Event. The argument was run that, if towards the end of a period of culpable delay a variation order is issued which delays completion, the Contractor was entitled not simply to an extension for the period of delay actually caused by the variation but (by reason of its timing) to a full extension up until the time that the variation was executed. The learned judge said that the “net” method was correct. He said at Page 34:
“Fundamental to this exercise is an assessment of whether the relevant event occurring during a period of culpable delay has caused delay to the completion of the Works and, if so, how much delay.”
This is consistent with the wording of Clause 25 in this case.
365.    In the context of this contractual based approach to extension, one cannot therefore do a purely retrospective exercise. What one can not do is to identify the last of a number of events which delayed completion and then say it was that last event at the end which caused the overall delay to the Works. One needs to consider what critically delayed the Works as they went along. For instance in this case, it would be wrong to say that the problem with the Courtyard Sliding Doors delayed the Works until it emerged as a problem in April 2008. Put another way, it did not delay the Works (if at all) until it emerged as a problem which needed to be addressed.
366.    There has been a substantial debate between the parties as to how what is called concurrent (or sometimes concurrent and co-effective) causes of delay should be dealt with. This debate is only germane where at least one of the causes of delay is a Relevant Event and the other is not. It relates to where a period of delay is found to have been caused by two factors. Of course, the debate will depend upon the contractual terms in question but most of the debate in cases in this country and elsewhere has revolved around extension of time clauses similar to those contained in Clause 25 where the Architect has to grant an extension which is “fair and reasonable”. The two schools of thought, which currently might be described as the English and the Scottish schools, are the English approach that the Contractor is entitled to a full extension of time for the delay caused by the two or more events (provided that one of them is a Relevant Event) and the Scottish approach which is that the Contractor only gets a reasonably apportioned part of the concurrently caused delay. The Scottish Approach is highlighted in the Inner House case of City Inn Ltd v Shepherd Construction Ltd [2010] BLR 473.
367.    In Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32, Mr Justice Dyson had to decide primarily whether an arbitrator had jurisdiction to deal with a defence by an employer that events such as variations and late information had not delayed the contractor but that other matters were causes of the delay. At Paragraph 13, he referred to some common ground between the parties:
“Second, it is agreed that if there are two concurrent causes of delay, one of which is a relevant event, and the other is not, then the contractor is entitled to an extension of time for the period of delay caused by the relevant event notwithstanding the concurrent effect of the other event. Thus, to take a simple example, if no work is possible on a site for a week not only because of the exceptionally inclement weather (a relevant event), and if the failure to work during that week is likely to delay the Works beyond the completion date by one week, and then if he considers it fair and reasonable to do so, the architect is required to grant an extension of time of one week. He cannot refuse to do so on the grounds that the delay would have occurred in any event by reason of the shortage of labour.”
It could thus be said that the learned judge was simply repeating the common ground between the parties rather than reach a considered decision on the issue. That said, the judge seems to have “run with the ball” in his second and third sentences and appears to have endorsed that common ground.
368.    Mr Justice Edwards Stuart said in De Beers v Atos Origin IT Services UK Ltd [2011] BLR 274:
“177. The general rule in construction and engineering cases is that where there is concurrent delay to completion caused by matters for which both employer and contractor are responsible, the contractor is entitled to an extension of time but he cannot recover in respect of the loss caused by the delay. In the case of the former, this is because the rule where delay is caused by the employer is that not only must the contractor complete within a reasonable time but also the contractor must have a reasonable time within which to complete. It therefore does not matter if the contractor would have been unable to complete by the contractual completion date if there had been no breaches of contract by the employer (or other events which entitled the contractor to an extension of time), because he is entitled to have the time within which to complete which the contract allows or which the employer’s conduct has made reasonably necessary.”
369.    In a shipbuilding contract dispute in Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 Comm, Mr Justice Hamblen quoted as good law what Mr Justice Dyson said at Paragraph 13 in the Henry Boot case (above):
“277. It is to be noted that this example involves a relevant event which caused a period of actual delay to the progress of the works – no work could be done for a week due to the weather. If that is established then the contractor is entitled to his extension of time even if there is another concurrent cause of that same delay. A useful working definition of concurrent delay in this context is “a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency” – see the article Concurrent Delay by John Marrin QC (2002) 18 Const LJ No. 6 436.
370.    In any event, I am clearly of the view that, where there is an extension of time clause such as that agreed upon in this case and where delay is caused by two or more effective causes, one of which entitles the Contractor to an extension of time as being a Relevant Event, the Contractor is entitled to a full extension of time. Part of the logic of this is that many of the Relevant Events would otherwise amount to acts of prevention and that it would be wrong in principle to construe Clause 25 on the basis that the Contractor should be denied a full extension of time in those circumstances. More importantly however, there is a straight contractual interpretation of Clause 25 which points very strongly in favour of the view that, provided that the Relevant Events can be shown to have delayed the Works, the Contractor is entitled to an extension of time for the whole period of delay caused by the Relevant Events in question. There is nothing in the wording of Clause 25 which expressly suggests that there is any sort of proviso to the effect that an extension should be reduced if the causation criterion is established. The fact that the Architect has to award a “fair and reasonable” extension does not imply that there should be some apportionment in the case of concurrent delays. The test is primarily a causation one. It therefore follows that, although of persuasive weight, the City Inn case is inapplicable within this jurisdiction.
371.    The delay experts did not agree about very much. What they did agree in their Joint Statement of 13 December 2011 was as follows:
“4. It is necessary to analyse events primarily in the period after 16 February 2007 in order to assess the parties’ respective contentions…as to the causes of delay during that period. However, in so far as events prior to 16 February 2007 also need to be examined in order to set the parties’ contentions in their proper factual context then those matters will also be considered relevant.
5. It is important to have regard to the actual context in the period after February 2007, as opposed to examining events in isolation.
6. Very few programmes were formally issued by WLC after 16 February 2007. In particular there is no programme of all the works outstanding at that date which could sensibly be used as a baseline in a retrospective programme analysis. It is therefore not possible to carry out a “traditional” delay analysis which uses the Claimant’s programmes to identify the critical path during the period after 16 February 2007 in the way one might normally expect. It will instead be necessary for the experts to form a view as to what were the critical (or driving) delays in the period after 16 February 2007 without the assistance which would normally be available from contemporaneously produced programmes.
7. Despite the lack of programmes in the post 16 February 2007 period, it ought nevertheless to be possible to form conclusions on criticality during this period, based on an objective view of the available evidence.”
A note to Paragraph 6 refers to the fact that in May 2007 WLC produced a programme (revised from time to time thereafter) entitled “Target Programme for Recently Instructed Works” which did not identify other works going on or outstanding at the time. The experts considered that this programme did not provide sufficient foundation for a “traditional” programme-based delay analysis but Mr Robinson considered that it was nevertheless of some evidential value.
372.    There was some disagreement between the experts as to what “Practical Completion” meant. In reality it means completion for all practical purposes and what that completion entails must depend upon the nature, scope and contractual definitions of the Works, as they may have developed by way of variation or Architect’s instructions. Clause 17.1 of the Contract Conditions simply requires the Architect to certify when he or she considers that Practical Completion has been achieved. There is common ground between the experts, and rightly so, that de minimis snagging should not be a bar to Practical Completion unless there is so much of it that the building in question cannot be used for its intended purposes. Dr Aldridge however goes further and suggests that Practical Completion requirements can be relaxed in effect by agreement between the parties; he is correct to this extent. In this particular case, DMW through its Architect was entitled to omit items of work and it must follow that once an item of work is omitted it is no longer part of the Works and the fact that it has not been done or completed thereafter should not hold up Practical Completion.
373.    Both experts say that they have adopted an objective approach but Dr Aldridge accepted that there were subjective elements at least to some of the exercises which he did.
374.    For reasons summarised earlier in the judgement, I found Mr Robinson to be at least in this case the much better expert. He adopted a much more objective approach than Dr Aldridge and was much more careful in accepting what his client had told him. Dr Aldridge’s approach was, as he put it, to consider this question: “what were the most significant matters which, at any given time, were preventing practical completion from being achieved?” This on its face appears to be not an unreasonable question to pose but, in seeking to answer that, he proceeded in what was in many respects a subjective way. Thus, he suggested that the defective plasterwork (which was substantially addressed by WLC within a few weeks and well before numerous other items of work which were always bound to be completed months later) caused substantial delay on no basis other on analysis than it needed to be dealt with before Practical Completion could be certified. Again, he selected the problems with the Lift in 2007 as a major cause of delay in that year but this approach was wholly flawed for the following reasons:
(a) He tried to assert that the Lift problems were “significant” because by about March 2007 there was a possibility (and no more) that a 6 to 9 month operation of replacement might be required; this was clearly dependent on at the very least the lift shaft being materially out of vertical, which it never was and replacement was never done.
(b) He based his view in part on “significance” in effect on the strength of his clients’ views at the time about how serious a problem it was. The reality is that WLC actually did a significant amount of remedial work and the eventual re-cladding work was in the overall context of the job minor work. The clients’ views, leaving aside the fact that I have found them to be coloured (at least in the case of Mr Mackay), were found by the adjudicator at the time (whose view has not really been departed from in this case) to be grossly exaggerated and there had been a wrongful but substantial retention of money against this item.
(c) His view was also based in part on the physical impact on the upper floors of the work being done particularly in October and November 2007 on the re-cladding. He asserted, without any real factual basis, that this work would effectively have prevented completion of work on the upper floors. This was undermined by the facts that there was little work to be done in those upper floors by WLC at or after that time (the bulk remaining to be completed in the basement) and that directly employed contractors and some workmen were able to and did get access whilst the re-cladding work was being done. Indeed, meeting minutes indicate that those attending the Client Site Walk Around meetings were able with reasonable impunity to get access to all floors throughout September, October and November.
375.    Another serious flaw in the approach adopted by Dr Aldridge was his willingness to proceed on the basis that one could ignore a number of the possible causes of delay in so far as they affected work which might have been (but which was not) omitted by DMW or its Architect. By doing this, he felt able to seek to undermine various possible causes of delay as being causative because he could say that, if a particular item of work could or might be omitted, it could not be causing a delay. This was wholly illogical. If both parties were aware that the client was considering omitting an item of work (and as a result the Contractor did nothing on the item of work) and then it was omitted, then that may or may not cause delay depending on whether other items of work were dependent upon the omitted item of work being done. If only the client was aware that it might omit the item, whether it was eventually omitted or not, delay could still be caused if the Contractor’s progress was delayed. If the item is never omitted and the Contractor has to carry it out, the Contractor may still be delayed not only by the need to execute such work but also by the delayed decision as to whether the work should go ahead or not. The reality check should generally be to consider whether or not the actual item of work which is said to cause delay was actually omitted or not.
376.    The Court should be very cautious about taking into account, in the exercise of determining what delays were caused by what events, theoretical possibilities as to what one party or the other might have done (but did in fact not do). Thus, Dr Aldridge seemed to suggest that various items of work such as the Leather in the Library could be discounted in whole or in part as a cause of delay because it was possible that DMW might have omitted it altogether from the Works. In that example, of course, the Leather was not omitted. This possibility is and would be completely irrelevant to the exercise considering whether the Leather in the Library delayed the Works; it is not as if WLC was ordered to suspend work on the Leather in the Library.
377.    Whilst ultimately it must be for the Court to decide as a matter of fact what delayed the Works and for how long, I was impressed by the way Mr Robinson approached the exercise and unimpressed by Dr Aldridge’s approach in this case. What Mr Robinson did was to analyse on a month by month basis (broadly) from February 2007 onwards what was in reality impacting upon progress. What he sought to do was to identify as far as possible WLC’s actual progress with the Works on a monthly basis and its planned intentions for executing the remainder of the Works.
378.    Mr Robinson had regard to the likely longest sequence of the outstanding work on a monthly basis as being the primary pointer to what was delaying the work at any one time. This was a wholly logical approach and, indeed is the approach used by most delay experts when there is a usable baseline programme from which to work. The logic is simply that if there are, say, two outstanding items of work, A and B, and A is always going to take 20 weeks to complete but B is only going to take 10 weeks, it is A which is delaying the work because B is going to finish earlier; overall completion is therefore dictated by the length of time needed for A. Put another way, it does not matter if B takes 19 weeks, it will be the completion of A which has prevented completion. Thus, if one is seeking to ascertain what is delaying a contractor at any one time, one should generally have regard to the item of work with the longest sequence. There was some sterile debate about whether Mr Robinson was adopting a purely “prospective” approach when he made it clear that “as a reality check” he had regard to what actually happened. There is in my view nothing wrong with such a “reality check”. An example might be that, say in February 2007 WLC was saying albeit in good faith that an item of work would take 25 weeks from then onwards. If in reality it only took two weeks, one would need to have regard to the efficacy of the earlier statement that it would take longer. Therefore it is necessary to have regard to how long individual items actually took to perform and not just have regard to what one party or the other at the time was saying it would take.
379.    In the assessment of what events caused what overall or critical delay, one needs also to bear in mind that it is not necessarily the last item or area of work which is finished last which causes delay. Thus, often on building projects, the last item of work is the final clean up of the site. That may only take two people one day to do but it is (almost always) the job which must be done on the last day of the job. It is what delays that final operation which in itself takes no longer than it was always going to take which must be assessed. This is of some importance in this case because it is argued that snagging (or an excessive amount of it) itself delayed the project. It is, rightly, common ground that snagging always has to be done because, with the best will in the world, there will be minor deficiencies, blemishes or incomplete items of work which will be required to be completed before hand over. Obviously, if there is an excessive amount of snagging and therefore more time than would otherwise have been reasonably necessary to perform the de-snagging exercise has to be expended, it can potentially be a cause of delay in itself.
380.    The debate about the “prospective” or “retrospective” approach to delay analysis was also sterile because both delay experts accepted that, if each approach was done correctly, they should produce the same result. An underlying problem, accepted as such by both experts, was the absence of a contemporaneous critical path programme from February 2007 onwards. If there had been one and its logic was sound, then both experts would in all probability have done the prospective exercise, albeit in the light of the events which happened. When that exercise can be done, the experts take what are called time slices (usually every month) to review against the programming logic the actual progress achieved and likely to be achieved in the future. That may produce, for instance, a delay in Month 1 of three weeks caused by Factor X, which might be adjusted downwards (or indeed upwards) in Month 3, to take into account actual progress in relation to Factor X. That could not readily be done here because there was no such programme. In my judgement, WLC cannot in practice be criticised throughout 2007 for this because completion was perceived by all parties to be not very far away and there were numerous individual items of work which needed to be done, many of which were variations.
381.    Thus, Mr Robinson’s approach was a sensible variant on the conventional approach of delay experts which was to review on a month by month basis what in each month was probably delaying overall completion. He then applied a cross check by reference to what actually happened. However, both delay experts’ approach (albeit to a lesser extent Mr Robinson’s) involved in reality doing the exercise that the Court must do which is essentially a factual analysis as to what probably delayed the Works overall.
382.    Again, in the delay assessment exercise the Court should be very cautious about giving significant weight to the supposedly contemporaneous views of persons who did not give evidence. Obvious examples are BLDA, Knowles and Navigant all of whom could have given possibly useful evidence if they had been called. Thus, BLDA expressed the view in the summer of 2007 that the problems with the Lift were seriously impacting on overall completion. One can give that little weight because it is unclear whether the relevant person who made that statement had done any analysis or had considered all the matters which have been put in issue in these proceedings or even whether it was an informed view. It is also clear that BLDA was placed under the closest scrutiny and pressure by Mr Mackay who was not only constantly critical of them but also had retained Knowles in effect to keep them under control as he would have seen it. Knowles was effectively often telling the Design Team what it could and could not do and there was undoubtedly contractually improper pressure placed on BLDA and G&T. It is clear that Mr Mackay and Knowles put pressure on BLDA not to grant any further extensions of time; indeed Knowles was asked to review the extensions of time already granted. It is a fair inference that BLDA felt pressurised to withhold signs of accepting complaints or claims made by WLC.
383.    The Court should also be cautious about attaching weight to what Mr and Mrs Mackay thought was important. This is for two reasons, the first being the less than favourable view which I have formed about the reliability of Mr Mackay’s evidence. The second reason is that both Mr and Mrs Mackay did not, obviously or at all and perhaps not surprisingly, analyse what were the contractual risks and responsibilities of DMW and WLC respectively, particularly in relation to design and to some extent procurement. It remains unclear what DMW were advised by the Design Team or Knowles and, of course, the Court can not know what DMW was advised legally was the position. Much of the Mackays’ thinking was predicated upon the basis, at least ultimately, that WLC was responsible for the design of most of the matters in issue, such as the ABW, the Light Wall, the Courtyard Sliding Doors, and the Leather in the Library and their views appear to have been coloured by their incorrect assumption that WLC was responsible.
384.    These areas of caution highlighted above are important generally but also because a significant part of Dr Aldridge’s views were related to the “significance” of particular items or areas of work, on the basis that a “significant” area of work which was delayed would or at least could therefore be  critical work which delayed the Works overall. His views on what were “significant” works were substantially (albeit not entirely) dictated by what he ascertained or assumed was the view of Mr and Mrs Mackay or their Design Team as to significance.
385.    Another area of caution revolves around how one treats what the parties were saying at the time in relation to issues which later were resolved. An example of this relates to the Lift shaft, which initially was believed by some on DMW’s side to be vertically out of alignment. Within several months however, and certainly by the time of the Adjudicator’s decision on the issue in late July 2007, it was accepted on all sides that this complaint was not justified. In the early stages, there was a limited possibility that all the Lift and Lift shaft work might have to be taken out and replaced and that this could all take 6 to 9 months. In the result, this did not happen. In my view, it is therefore totally irrelevant in any analysis of what caused the delay, because certainly neither the supposed lack of verticality nor any need to replace the Lift was ever agreed upon, established or implemented. In logic also, the fact that one side (wrongly) perceives that a particular problem is more serious than it turns out to be is in itself unlikely to be relevant in ascertaining whether that problem caused delay.
386.    I will now turn to an analysis and assessment of what actually caused the overall delays in this project. In so doing, I will proceed on a month by month assessment because both experts accept that this would be relevant and helpful and this is a view with which I concur.
387.    It is first necessary to review the position as at 16 February 2007 which was the extended date for completion allowed for by BLDA. DMW now accept that the extensions of time until 16 February 2007 are not challengeable or at least they are not challenged. It is worth commenting that all the extensions of time granted in effect reflect delayed instructions or additional work. I said at the beginning of this judgement that this project was a “disaster waiting to happen” and this it proved to be. It is clear that Mr and Mrs Mackay were very unhappy with BLDA and that is a primary reason why Mr Mackay called in Knowles. Whether all the problems which occurred up to mid-February 2007 were the actionable fault of the Design Team can not now be ascertained, largely because this trial has not been concerned with the professional culpability of the Design Team. An example is the Leather in the Library (referred to in detail above) in which Mr Mackay apparently believed that he had approved the leather in about May 2005 but no-one seems to have told WLC about this let alone what the leather was. Either Mr Mackay is mistaken in his evidence or his Design Team let him down because they were telling WLC later that the leather was “to be confirmed”. Either way, that is not the fault of WLC, or indeed Adams. There may well also in mid-2006 have been a realisation on the part of the Design Team that the leather which had not been quoted for by Adams but which their client wanted would be too expensive, possibly compared with the budget. However, it was their decision (with the knowledge or consent of Mr Mackay or not) to seek further quotations for different types of leather. Again, the cause of the lateness of the instruction ultimately in relation to the Leather in the Library falls somewhere within the Design Team/Mackay axis and it matters not for this Court whose fault or responsibility within that axis it was.
388.    It was broadly common ground in January 2007 that there was a fair prospect that most of the works would be completed at least internally by the end of January 2007 (as referred to in the minutes of the site meeting held on 9 January 2007). External works were running several weeks behind this, albeit much of these works were omitted a few weeks later. However, WLC qualified its views, for instance in its Progress Report on 19 January 2007 which indicated that amongst other things the Light Wall would not be complete by the end of January 2007 along with various other work including work as yet uninstructed.
389.    The very fact that BLDA and WLC began seriously to talk about snagging in February 2007 suggests strongly that they both considered that the Works overall were not far off completion, because snagging invariably precedes Practical Completion. However, Mr Mackay started again to raise issues relating to plastering which doubtless bothered him but which in the result turned out to be exaggeration at least in relation to that for which WLC was responsible.
390.    In its letter of 13 February 2007, in the context of the proposed snagging regime WLC referred to the fact that its extension of time claims already indicated completion as late as May 2007, one of them being the “late leather selection & choice of stitching”. In its Report dated 16 February 2007, WLC indicated that significant delays continued to be recorded in relation to the pool areas, lifts, doors and frames, courtyards and external works. Although it continued to target completion within February 2007, it highlighted that the Light Wall, the Courtyard works, the library shelving and joinery and the installation of leather work generally (amongst several other items of work) would not be complete. This report was not challenged by anyone at the time as containing any material error, save possibly for the continuing furore emanating from DMW about the plasterwork. The other items of work which were listed in this report were not said by anyone at the time or during the trial as being items which did, would or might cause any overall delay to the project.
391.    In my judgement therefore as at 16 February 2007 the key or more important outstanding items of work were the Light Wall (the Second Generation of which had just been found to be insufficiently opaque), the Lift (which was beginning to be noted as defective), the Library joinery including the Leather which was to go on and behind it (no final instructions having then been given), the Barrisol ceilings in the cinema and the pool areas and the lighting above it and the Stingray doors (the ironmongery for which had still not been resolved).  This does not mean that there were not other items of work still to be completed and these included such of the plasterwork as needed repair, the snagging that remained to be done and other items of work which have not featured as relevant to the issues of delay.
392.    I will now turn to reviewing the project as it went along from mid-February 2007 through to mid-August 2008 when Practical Completion was certified. It was argued through cross-examination of Mr Robinson that it was artificial to review delay by reference to a monthly analysis, or, as he had done, as at the end of the month. In one sense, it is artificial because one could take any period of time or any time of the month to conduct one’s analysis; one could do it on a daily or a quarterly basis. It is however a proportionate and sensible basis to look at delays on a monthly basis and indeed most delay experts proceed on that basis. As a tribunal, let alone a delay expert, one has to get a handle on what was delaying the project as it went along.
End of February 2007
393.    On 27 February 2007, WLC produced to BLDA a List of Outstanding Works to which there was no, let alone a comprehensive, response. It estimated that the bulk of the outstanding work would be completed by about April although it was difficult to be sure about the Pool Hall and three of the WCs. The one item of work which it was clear was not going to be completed by then was the Leather in the Library. It was known by the end of February 2007 that Adams needed 17 to 19 weeks from the time they were given the “green light”. No approval had been given in relation to the stitching and there was no prospect of there being an immediate approval. It followed therefore that, as no one suggested at the time or during the trial that this was an unreasonable period, this leather work was not going to be finished until July 2007 at the earliest. As appears from BLDA’s email dated 2 March 2007 to Mr Mackay, even BLDA thought that the leather was on “the immediate critical path”.
394.    I discount the problems with the plasterwork as causing or contributing to any overall delay during this or indeed any later period. There clearly was a very substantial exaggeration (which may not have been deliberate) by Knowles and Mr Mackay as to any problem which could be attributed to a default on the part of WLC. In the result, although there were many areas which needed some attention by WLC, the remedial works overall were minor. Often, as one witness described it, all that was required was the brushing of a millimetre or two of plaster onto relatively small areas to make it sufficiently flat or level. The “reality check” in the case of the plastering defects is to consider how long in practice it would have taken if it had been the only thing holding up practical completion. The answer would have been no more than a few days work for several plasterers. It is inconceivable in those circumstances that this work which in the result was substantially completed by late April 2007 in any way materially delayed the works.
395.    I discount also the relevance of the lift defects at this stage. Although substantial complaints were being made by the end of February 2007, there was uncertainty as to what was going to be required. Some of these complaints were not justified.
396.    I do not consider that outstanding snagging was a cause of delay at this stage either. It was or must have been clear to all concerned, as it is now clear to the Court, that the Works overall were not going to be completed at least until July 2007 and it was and is more than probable that any snagging that needed to be done would and could be completed within that timeframe.
397.    Mr Robinson’s view in relation to the position as at the end of February 2007, with which I concur, is that on any proper analysis the Works were being critically delayed by the delayed instructions in relation to the design, procurement and installation of the Leather in the Library. This was a significant item of work and it had the longest sequence as at that stage; all things being equal, if there had been no problem either with the procurement of the Leather or with anything else, the Works would not and could not have been practically complete before the Leather work in the Library had been completed. Indeed, I find that in those circumstances all the Works would have been completed by then.
398.    Mr Robinson assesses the critical delay at this stage as 22 weeks from 16 February 2007. However, a more accurate analysis from the end of February 2007 would be 18 weeks on the assumption that BLDA, Bev or Mr Mackay gave Adams the “green light”. Adams had effectively quoted 17 to 19 weeks from that stage and 18 weeks would take completion to 12 July 2007. In my judgement therefore, looked at as at the end of February 2007, WLC had been delayed by 18 weeks as a result of the delayed instruction and approval in relation to the stitching to the leather.
End of March 2007
399.    Essentially the position remained the same in this period. The mechanical and electrical works were approaching completion during the early part of this month albeit that a few areas remained outstanding some of which was dependent upon completion of works by contractors directly employed by DMW (Sound Ideas and Odyssey Glass) and some other works which required more information; final commissioning remained to be done. The Light Wall remained in a state of flux whilst BLDA, Equation and Mr Mackay decided upon what was the best approach to overcome the opacity problem.
400.    The Leather in the Library continued as before with no decisions and no approval given to enable Adams to proceed. A further 31 days delay in that operation was therefore attributable to the continued failure to make decisions and instruct WLC and Adams what to do.
401.    By the end of March 2007, the Barrisol ceiling in the cinema was apparently complete but that in the swimming pool area was not; this was because it had been resolved that the ceiling fabric should not be installed until the dirt- causing works were completed (which they had not been). Such external works as remained within the responsibility of WLC were nearing completion.
402.    In relation to the Lift, some remedial works had been done and there was continuing discussion as to what was required. Although there was talk about the possibility of the whole Lift and Lift shaft being replaced, WLC made it clear that this was unnecessary and, if instructed, could only be instructed as a variation. I do not consider that it was ever considered by anyone to be a realistic option to replace everything and in the result it was never done; if it had been ordered, it would have had to have been by way of variation. There was a growing disagreement about what needed to be done but it is clear that Mr Mackay at that stage was disenchanted with the lift which he described as a “monstrosity”. Certainly, given what happened later, I do not consider that the Lift problems such as in truth there were (in contra-distinction to what DMW said they were) caused any delay in this month.
403.    Therefore, for similar reasons to those given in relation to February 2007, in my judgement WLC was delayed by a further 31 days in March 2007 by the continuing hiatus relating to the Leather in the Library. This would take the delay to Practical Completion up to at least 13 August 2007.
End of April 2007
404.    Similar considerations apply in relation to April. It was in this month that there was a final resolution in relation to the plastering defects and these were substantially put right by the end of April 2007; this demonstrates in the result that they did not materially impact on completion in any event. The position in relation to the Lift continued as before with there being differences between the parties but some remedial work was being continued by WLC. The Light Wall continued to give rise to debate but it was anticipated that following the production by Firman of a full-size sample on or by 25 April 2007 the Light Wall would be completed by 11 June 2007.
405.    There were numerous small items of work being discussed and worked on, some involving Sound Ideas. A number of doors were to be increased in height in some of the upper rooms. Again there has been no hint or suggestion that any of these other items of work impacted on the delay.
406.    On a parity of reasoning as before, my assessment is that the Works overall were delayed by the continuing lack of instructions and approval relating to the Leather in the Library. A further 30 days delay occurred which would take completion of to 13 September 2007. The Leather in the Library represented the longest clearly identifiable sequence of work judged at the end of April 2007.
End of May 2007
407.    It is clear that by May 2007 the Works, as a whole and with some very obvious exceptions, were closer to completion. Mr Whidborne of G&T said in an e-mail to Mr Mackay on 2 May 2007 that the “works are virtually complete apart from snagging”. There were various changes to the Works discussed as the month went on and a number of variation instructions (at least 20 in number) were issued in the month in relation to them. It was however not correct to say that the works were virtually complete except the snagging. Snagging work remained outstanding albeit that a substantial amount of the notified snagging had been put right or completed. It was not however the snagging which was driving completion at this stage. The Light Wall was incomplete and sub-contractors (Gruppo) were just starting to install different stone flooring to the Pool Hall which would take about six weeks to complete. There continued to be some problems relating to the Barrisol ceilings or the lighting above it in the cinema and the pool hall but, all things being equal, it can not have been anticipated that this would take more than a few weeks at most to resolve. The Stingray doors remained an issue as the free issue ironmongery had still not been issued. The lines remained drawn over the Lift with Mr Mackay wanting to have his own survey on verticality. 
408.    It was the Leather in the Library however which remained the key operation with the longest sequence both on an anticipated as well as a retrospective basis. The final revised sample was approved, albeit with some qualification, on the 16 May 2007 and on 22 May 2007, as Mr Joyce said in evidence, Adams confirmed its proposed programme; indeed on 24 May 2007, Adams issued manufacturing drawings for the Library shelving. On 1 June 2007, WLC confirmed the likely completion as mid September 2007.
409.    There was therefore no further delay overall caused by events in May 2007 and, all things being equal, completion would have occurred by mid- September 2007.
End of June 2007
410.    Most of the work done during June 2007 involved either additional instructed work or snagging and cleaning works. Indeed additional relatively minor variations were ordered by BLDA. The Third Generation of the Light Wall was delivered to site and installation began on 22 June 2007, although it was interrupted by BLDA’s instructions suspending work whilst decisions were made about the fibre-optic lighting and the scalloping effect which was emerging. As Mr Joyce said, this was because BLDA wanted both to arrange for DMW to inspect and to experiment with tape and diffusion silk to improve the spread of light. Nonetheless, this state of affairs was not considered so urgent that there would be overall delays. The Barrisol ceilings were again in a state of flux with that in the cinema to be taken down again; the problems were again to do with the lighting design. Although some ironmongery for the Stingray doors was supplied towards the end of June 2007, it was the wrong type.
411.    By June, it was fully accepted by DMW and BLDA that there were no problems with the verticality of the Lift Shaft. Mr Mackay indicated at the Client Site Walk Around meeting of 6 June 2007 that he would accept a bronze capping solution but Mr Bates of WLC indicated that once the remedial mastic work had been done all instructed work would have been completed in this area. There remained differences however as to the extent and scope of remedial work and WLC continued with remedial work. Adjudication was started on 20 June 2007 in relation to the withholding of money, including that in relation to the Lift.
412.    ABW emerged as an increasing problem. However, as I have formed the view that WLC was not contractually responsible for the problems experienced in relation to ABW and because ultimately all that was done by them was the staining requested by the Mackays on 19 September 2007, this did not at any time in 2007 delay WLC.
413.    It was the Leather which again was a key factor relating to progress. On 19 June 2007, BLDA’s instruction AI471C instructing the leather works to the Lower Hall Lobby was issued. This (amongst other variations) was the subject matter of WLC’s Extension of Time Request No 76 which suggested that an extension of time up to the week commencing 8 October 2007 was called for. A 14 week period was required for this work which, from the date of the order by WLC to Adams would take the completion to about 28 September 2007. It is clear however, and indeed turned out to be the case, that the Leather in the Library was in practice intimately associated by Adams with the Leather in the adjacent lobby area and that this additional work was to delay the overall Leather in the Library.
414.    In my judgement therefore, the Leather in the Library was delayed until about 28 September 2007. It was inevitably however going to be the case that following the completion of the Leather in the Library there would have to be final snagging and completion of the cleaning and other operations which would need to follow that work and the Light Wall. Thus, it is the case that the Works overall were delayed by reason of events in June 2007 and before by a further two weeks until 12 October 2007 and I accept the evidence of Mr Joyce and Mr Robinson in relation to this two week period.
End of July 2007
415.    A number of minor additional works were initiated during July 2007, many to do with additional or altered lighting (in the Lower Hall lobby, the Drawing Room, the swimming pool, the cinema ceiling and the first floor). A further 15 Architect’s Instructions were issued in this month.
416.    The Light Wall continued to give rise to difficulties and Firman was being required to experiment with lighting under the auspices of Equation who together with BLDA failed to give clear and finite instructions as to what was required. There was little progress but it was broadly being anticipated that the problems could and would be resolved by sometime in September, particularly following the issue by BLDA of AI490C which required, by way of variation, additional work thereto. By the end of July 2007, the Barrisol ceilings, although installed, were appreciated as being unsatisfactory so far as the lighting was concerned and this remained to be dealt with, albeit largely at the expense of Equation. The Stingray doors did not progress because of the late delivery of ironmongery from the free issue suppliers.
417.    The adjudicator issued his decision on 30 July 2007, deciding in effect that there had continued to be a substantially exaggerated set of complaints by DMW in relation to the Lift. However, he did find that there was a justification for withholding some £30,000 and in effect that there were some continuing defects. WLC had done some remedial work earlier in June and July 2007. Mr Mackay and family were away, apparently on holiday, from mid-July until September 2007 but, although the over-cladding solution was considered by the Mackays at a meeting on 11 July 2007 as acceptable, it seems to have been put on a “back-burner” until the adjudicator published his decision and the Mackays returned from holiday. This suggests that it was not considered by anyone in July and August 2007 as likely to impact overall in relation to delay. Accordingly, I do not consider that the Lift issues delayed that Works at this stage.
418.    The Leather in the Library was subject to a further important variation, AI481C which involved the running of a duct through the ceiling void and behind the library shelving. As Mr Joyce has said and I accept, this would and did affect the installation of the shelving and because the shelving was to be covered with leather, affected the Leather in the Library operation. That this did delay that operation is clear because the shelving could not be fully installed whilst this ducting operation was being completed. It was not to be completed until 6 September 2007 and at least five weeks was required thereafter to complete the installation. The impact of AI481C was to delay the Leather in the Library by just over six weeks (23 July (the date of issue) to 6 September 2007) but allowing for the fact that WLC envisaged that the Leather in the Library would be completed by the end of the first week in October 2007 and allowing again a further two weeks thereafter for the completion of final snagging and clean up, the Leather in the Library again delayed completion in this period up until about 21 October 2007.
End of August 2007
419.    August 2007 was taken up mostly with a combination of snagging and additional and varied works, much of which was to do with lighting, for instance in relation to the Cinema and the swimming pool ceiling. 16 further Architect’s Instructions were issued and a number of directly employed contractors attended to carry out works for Mr and Mrs Mackay. There was little progress on the Light Wall because Firman were not to be in a position to return the screens to site until early September 2007 although it was anticipated that the work would then only take about two weeks.
420.    The first delivery of leather joinery for the Library arrived on 15 August 2007 and by the end of August 2007 it was being anticipated that WLC would complete the Leather Work in the Library by the end of the first week in October, this primarily being attributable to the need to deal with the air duct variation issued on 23 July 2007.
421.    The Stingray doors work was delayed further by the late delivery of the free issue bronze angles and handles and there was a hiatus over a few days as to whether the doors were to swing in one or both directions.
422.    In relation to the Lift, WLC was proceeding to address snags identified by BLDA with identified works on 16 areas of imperfection in the surface of the mastic, 40 areas of void within the mastic joint, 43 packing pieces showing through the mastic, three areas of scratching and some cover pressings to be replaced. WLC replaced the cover pressings and the mastic and glass sub-contractors carried out some remedial works in the last week of August 2007. Otherwise WLC sought instructions from BLDA on how to overcome some of the mastic problems. The parties were obviously awaiting the return of the Mackays from holiday before deciding what an appropriate solution was.
423.    There was a continuing and serious problem in the lighting in the pool ceiling lighting described in the Barrisol ceiling Chapter of this judgement. Equation had essentially made errors and was at its own expense seeking to overcome them, albeit WLC and Norstead were deployed to effect the requisite remedial solutions. A series of Architect’s Instructions began to be issued in August 2007 to overcome these errors and it was inevitable that this would take time to achieve. It is difficult to be certain as to precisely how much delay overall was occasioned by these issues but there certainly was overall and additional delay being caused by these lighting variations and the time being taken to decide upon them. My best assessment on all the evidence is that by the end of August 2007 the Barrisol ceiling delays had caused and made it inevitable that an additional three weeks of delay overall would occur. This is in part at least borne out by the Target Programme for Recently Instructed Works dated 31 August 2007 produced by WLC which identified the works with longer sequences as the leather works in the Lower Hall and the lighting alterations instructed under AI498C, with completion overall indicated as mid to late November 2007. I do not see however that there were particular reasons which led to those leather works being extended, albeit that, as turned out to be the case, the lighting issues in the pool continued to have to be resolved over the next 9 to 10 weeks.
424.    Thus, the problems with the Barrisol ceiling lighting work rendered it inevitable that overall completion was delayed by another three weeks, that is until 11 November 2007.

Start your free trial today

Your trusted daily source of commercial real estate news and analysis. Register now for unlimited digital access throughout April.

Including:

  • Breaking news, interviews and market updates
  • Expert legal commentary, market trends and case law
  • In-depth reports and expert analysis

Up next…